Deedo IDDP-PUN-9DCGCompletion was pushed back 4 months, to Jul 2028; no MahaRERA orders on record; 71% of its units are booked.
Munjeri, Pune 411037 · by Infinity Shine India Private Limited
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Jul 2028
- This projectRegistered 22 Sep 2023, completion promised 31 Mar 2028, revised to 31 Jul 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
3 buildings
Open a building to see every flat, floor by floor.
- Building - A8 floors · 12 units58% booked
- Building - B7 floors · 28 units86% booked
- Building - C7 floors · 28 units61% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100052779
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100052779 | 22 Sep 2023 | 31 Mar 2028 | 31 Jul 2028 | Infinity Shine India Private Limited | Project page |
Documents116
1 document held by Deedo, 115 filings listed on MahaRERA's project page
Finance
- PAN CardPAN Vriddhi I.pdf · uploaded 7 Sep 2023Source
Legal
Show all 116 documentsShow fewer documents
Migrated
- 2 b Details of encumbrances concerned to LegalEncu Legal.pdf · uploaded 4 Sep 2023Source
- 1 Declaration in FORM BForm B Promoter.pdf · uploaded 4 Sep 2023Source
- 1 CERSAI detailsCersai Dec.pdf · uploaded 4 Sep 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDiscloser.pdf · uploaded 4 Sep 2023Source
- 1 Proforma of Allotment letterAllotment.pdf · uploaded 4 Sep 2023Source
- 1 Proforma of Agreement for saleAgreement.pdf · uploaded 4 Sep 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 4 Sep 2023Source
- 1 Deviation Report with respect to Allotment letterNo Deviation Allotment.pdf · uploaded 4 Sep 2023Source
- 1 PAN CardPAN Vriddhi I.pdf · uploaded 7 Sep 2023Source
- 1 Copy of the legal title reportSTR RERA I_compressed.pdf · uploaded 7 Sep 2023Source
- 2 Copy of the legal title reportSTR II_compressed.pdf · uploaded 7 Sep 2023Source
- 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN_RERA.pdf · uploaded 7 Sep 2023Source
- 1 Building Plan Approval / NA Order for plotted development03.pdf · uploaded 7 Sep 2023Source
- 2 Building Plan Approval / NA Order for plotted development02.pdf · uploaded 7 Sep 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 7 Sep 2023Source
- 1 Declaration about Commencement CertificateFormat D Tabular.pdf · uploaded 7 Sep 2023Source
- 1 Deviation Report with respect to model copy of AgreementNo Deviation Agreement Infinity.pdf · uploaded 7 Sep 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)3.pdf · uploaded 13 Sep 2023Source
- 1 Disclosure of sold/ booked inventoryVriddhi.pdf · uploaded 15 Mar 2024Source
- 2 Copy of Layout Approval (in case of layout)1.pdf · uploaded 8 Apr 2024Source
- 3 Building Plan Approval / NA Order for plotted development2.pdf · uploaded 8 Apr 2024Source
- 4 Building Plan Approval / NA Order for plotted development3.pdf · uploaded 8 Apr 2024Source
- 5 Building Plan Approval / NA Order for plotted development4 .pdf · uploaded 8 Apr 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 8 Apr 2024Source
- 2 Declaration about Commencement CertificateVriddhi - Format - D .pdf · uploaded 10 Apr 2024Source
- 2 Disclosure of sold/ booked inventoryVriddhi-sold unsold.pdf · uploaded 10 May 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate.pdf · uploaded 27 Jun 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 31122023.pdf · uploaded 27 Jun 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)310324.pdf · uploaded 27 Jun 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 300923.pdf · uploaded 27 Jun 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate 31122023.pdf · uploaded 27 Jun 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate 31032024.pdf · uploaded 27 Jun 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)From 2A.pdf · uploaded 1 Jul 2024Source
- 3 Disclosure of sold/ booked inventoryVriddhi sold unsold Jun 24.pdf · uploaded 24 Jul 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Ar30092023.pdf · uploaded 11 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Ar31122023.pdf · uploaded 11 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Ar 31032024.pdf · uploaded 11 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Ar30062024.pdf · uploaded 11 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_30062024.pdf · uploaded 11 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Ar30092023.pdf · uploaded 11 Oct 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Ar31122023.pdf · uploaded 11 Oct 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Ar 31032024.pdf · uploaded 11 Oct 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Ar30062024.pdf · uploaded 11 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_30062024.pdf · uploaded 11 Oct 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 6 Dec 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 6 Dec 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)RERA FORM 5 Infinity Shine india Pvt Ltd Phase 1 .pdf · uploaded 17 Dec 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Infinity Shine Q2.pdf · uploaded 30 Dec 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Infinity Shine India Pvt Ltd Q1_compressed.pdf · uploaded 3 Jan 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Infinity Shine India Pvt Ltd_compressed.pdf · uploaded 7 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM - 1.pdf · uploaded 8 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 8 Feb 2025Source
- 1 Disclosure of sold/ booked inventoryVriddhi.pdf · uploaded 15 Feb 2025Source
- 1 Disclosure of sold/ booked inventoryVriddhi - dec 24_compressed (1).pdf · uploaded 23 Mar 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Infinity Shine India Pvt Ltd_compressed (1).pdf · uploaded 11 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryVriddhi mar 25_compressed.pdf · uploaded 11 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM - 1 .pdf · uploaded 14 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form - 2.pdf · uploaded 14 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form -2A(24-25).pdf · uploaded 22 Apr 2025Source
- Withdrawal Update Form 1Infinity Shine India pvt Ltd Form 01 - 30-06-2025.pdf · uploaded 21 Aug 2025Source
- Withdrawal Update Form 2Engineer Certificate 31032024.pdf · uploaded 21 Aug 2025Source
- Withdrawal Update Form 3Form 3 Infinity Shine India Pvt Ltd Q1_compressed.pdf · uploaded 21 Aug 2025Source
- Form 1Form 1.pdf · uploaded 12 Nov 2025Source
- Form 2Form 2.pdf · uploaded 12 Nov 2025Source
- Form 3FORM 3 Q2 vriddhi.pdf · uploaded 12 Nov 2025Source
- Disclosure of Sold and Booked InventoryVriddhi 30-09-25.pdf · uploaded 12 Nov 2025Source
- Form 5 (FY 2024-2025)Infinity Shine India Pvt Ltd FORM 5.pdf · uploaded 11 Dec 2025Source
- Form 1Form 1 - 31-12-2025.pdf · uploaded 14 Feb 2026Source
- Form 2form2-31-12-2025.pdf · uploaded 14 Feb 2026Source
- Form 3Form - 3.pdf · uploaded 14 Feb 2026Source
- Disclosure of Sold and Booked Inventoryvriddhi sold unsold inventry.pdf · uploaded 14 Feb 2026Source
- Form 1Vriddhi form1.pdf · uploaded 18 Apr 2026Source
- Form 2Vriddhi form 2.pdf · uploaded 18 Apr 2026Source
- Form 3Vriddhi form 3.pdf · uploaded 18 Apr 2026Source
- Disclosure of Sold and Booked InventoryVriddhi.pdf · uploaded 18 Apr 2026Source
- Form 2A (FY 2023-2024)Vriddhi form 2A - 31-12-2023.pdf · uploaded 18 Jul 2026Source
- Form 2A (FY 2024-2025)Vriddhi form 2A - 01-04-2024.pdf · uploaded 18 Jul 2026Source
- Form 2A (FY 2025-2026)Vriddhi form 2A - 01-04-2025.pdf · uploaded 18 Jul 2026Source
- Form 2A (FY 2026-2027)Vriddhi form 2A - 01-04-2026.pdf · uploaded 18 Jul 2026Source
- Form 1Vriddhi form 01 - 30-06-2026.pdf · uploaded 20 Jul 2026Source
- Form 2Vriddhi Form 02 - 30-06-2026.pdf · uploaded 20 Jul 2026Source
- Form 3Infinity Shine Form 03_compressed.pdf · uploaded 20 Jul 2026Source
- Disclosure of Sold and Booked InventoryVriddhi - Jun 26.pdf · uploaded 20 Jul 2026Source
Technical
- DocumentLAYOUT PLAN_RERA.pdf · uploaded 7 Sep 2023Source
- Document03.pdf · uploaded 7 Sep 2023Source
- Document02.pdf · uploaded 7 Sep 2023Source
- Document1.pdf · uploaded 8 Apr 2024Source
- Document2.pdf · uploaded 8 Apr 2024Source
- Document3.pdf · uploaded 8 Apr 2024Source
- Document4 .pdf · uploaded 8 Apr 2024Source
Technical (Architect)
- DocumentAr30092023.pdf · uploaded 11 Oct 2024Source
- DocumentAr31122023.pdf · uploaded 11 Oct 2024Source
- DocumentAr 31032024.pdf · uploaded 11 Oct 2024Source
- DocumentAr30062024.pdf · uploaded 11 Oct 2024Source
- DocumentAr30092023.pdf · uploaded 11 Oct 2024Source
- DocumentAr31122023.pdf · uploaded 11 Oct 2024Source
- DocumentAr 31032024.pdf · uploaded 11 Oct 2024Source
- DocumentAr30062024.pdf · uploaded 11 Oct 2024Source
- DocumentForm 1.pdf · uploaded 6 Dec 2024Source
- DocumentFORM - 1.pdf · uploaded 8 Feb 2025Source
- DocumentFORM - 1 .pdf · uploaded 14 Apr 2025Source
- DocumentInfinity Shine India pvt Ltd Form 01 - 30-06-2025.pdf · uploaded 21 Aug 2025Source
Technical (Engineer)
- DocumentForm 2_30062024.pdf · uploaded 11 Oct 2024Source
- DocumentForm 2_30062024.pdf · uploaded 11 Oct 2024Source
- Documentform 2.pdf · uploaded 6 Dec 2024Source
- DocumentForm 2.pdf · uploaded 8 Feb 2025Source
- DocumentForm - 2.pdf · uploaded 14 Apr 2025Source
- DocumentEngineer Certificate 31032024.pdf · uploaded 21 Aug 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 1853 (Old S.No.440/A/1/2) BibwewadiMunjeriat Haveli
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- Office space, Showroom 01, Showroom 02, 3BHK68 units in all
- Address
- 1853 (Old S.No.440/A/1/2) Bibwewadi-Munjeri, Pune Satara road, MunjeriPIN 411037
- Village
- Pune (M Corp.), Pune City taluka
- Land area for this project
- 2,500 sq m (26,910 sq ft)
- Permissible built-up area
- 8,734 sq m (94,007 sq ft)
- Sanctioned built-up area
- 8,734 sq m (94,007 sq ft)
- Designated bank account
- 220
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
1853 (Old S.No.440/A/1/2) Bibwewadi-Munjeri
Boundaries
- North
- Existing Plot
- South
- Existing Plot
- East
- Nala
- West
- Pune Satara Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking68 units
48 of 68 units booked (71%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Building - A | Office space | 61.31 sq m · 660 sq ft | 4 | 2 |
| Building - A | Office space | 89.83 sq m · 967 sq ft | 4 | 3 |
| Building - A | Office space | 152.62 sq m · 1,643 sq ft | 2 | 0 |
| Building - A | Showroom 01 | 167.97 sq m · 1,808 sq ft | 1 | 1 |
| Building - A | Showroom 02 | 108.64 sq m · 1,169 sq ft | 1 | 1 |
| Building - B | 3BHK | 98.29 sq m · 1,058 sq ft | 28 | 24 |
| Building - C | 3BHK | 82.26 sq m · 885 sq ft | 7 | 3 |
| Building - C | 3BHK | 83.55 sq m · 899 sq ft | 7 | 3 |
| Building - C | 3BHK | 91.6 sq m · 986 sq ft | 14 | 11 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Jay Aeram | — |
| Chartered accountant | Sriram Tawani | — |
| Engineer | Arun Kumar Sutar | — |
| Other | Vikram Tilekar | — |