Skip to content

RERA projects in Munjeri

10 projects under 10 MahaRERA registrations, registered 2023–2026. 80% have a completion date extended beyond the one promised.

Locality
10RERA projects
10Registrations
9Completion still due1 past their completion date
4 monthsMedian extension beyond promised date80% of registrations extended
0Regulatory casesnone on MahaRERA's lists
12Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20231
20241
20256
20262

Projects in Munjeri

10 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
The EverettSerianee Corrp LLPPM126101260005910 Apr 202631 Mar 203031 Jul 2030Extended 4 mo0
Urban RevivaM/s Urban Cityscapes LLPPM12600025020278 Jan 202631 Dec 202730 Apr 2028Extended 4 mo0
KrutarthMajestique Duropolis Pvt LtdPR126000250080316 Sep 202531 Dec 202930 Apr 2030Extended 4 mo0
IKON InfiniaIKON Landmarks LLPPR126000250066226 Aug 202530 Apr 202830 Apr 2028Not yet due0
Antariksh ResidencyO & B AssociatesPR126000250040329 Jul 202531 Dec 202730 Apr 2028Extended 4 mo0
Pratibha SadanMomsha Pratibha Sadan LLPP521000807673 Jul 202531 Dec 202730 Apr 2028Extended 4 mo0
The CapitalMainland Spaces LLPP5210008038129 May 202531 Dec 202830 Apr 2029Extended 4 mo0
Pg AshwinPlatinum PrideP521000787037 Jan 202530 Jun 202730 Oct 2027Extended 4 mo0
Shreedhar NilayOpulent LandmarksP521000783666 Dec 202431 Dec 202830 Apr 2029Extended 4 mo0
Tejasvi HeritageTejasvi DevelopersP5210005316017 Oct 202330 Jun 202630 Jun 2026Promised date passed0

Other localities in Haveli

Most active promoters

By projects registered here, as named on MahaRERA.

  1. IKON Landmarks LLP1 project
  2. Mainland Spaces LLP1 project
  3. Majestique Duropolis Pvt Ltd1 project
  4. Momsha Pratibha Sadan LLP1 project
  5. M/s Urban Cityscapes LLP1 project
  6. O & B Associates1 project
  7. Opulent Landmarks1 project
  8. Platinum Pride1 project
  9. Serianee Corrp LLP1 project
  10. Tejasvi Developers1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology