Completion was pushed back 4 months, to Feb 2027; no MahaRERA orders on record; 49% of its units are booked.

Mundhawa, Pune 411036 · Property rates in Mundhawa · by Swamiji Developers

DeliveryExtended 4 moPromised Oct 2026 · now due Feb 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales49% booked17 of 35 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Feb 2027

  • This projectRegistered 3 May 2023, completion promised 5 Oct 2026, revised to 5 Feb 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100050771
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000507713 May 20235 Oct 20265 Feb 2027Swamiji DevelopersProject page
Documents94

1 document held by Deedo, 93 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardpancard.pdf · uploaded 21 Mar 2023Source

Legal

  • Legal Title reportlegal report - format A.pdf · uploaded 5 Apr 2023Source
  • Declaration Form Bform B.pdf · uploaded 5 Apr 2023Source

Migrated

  • 1 PAN Cardpancard.pdf · uploaded 21 Mar 2023Source
  • 1 Copy of Layout Approval (in case of layout)layout approval.pdf · uploaded 21 Mar 2023Source
  • 2 Copy of Layout Approval (in case of layout)NA order.pdf · uploaded 21 Mar 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentbuiliding sanction plan.pdf · uploaded 21 Mar 2023Source
Show all 94 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificates.pdf · uploaded 21 Mar 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentNA order.pdf · uploaded 21 Mar 2023Source
  • 1 Declaration about Commencement CertificateDeclaration about Commencement Certificate.pdf · uploaded 21 Mar 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 21 Mar 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 21 Mar 2023Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold inventory.pdf · uploaded 21 Mar 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA certificate (form 3).pdf · uploaded 21 Mar 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations.pdf · uploaded 21 Mar 2023Source
  • 1 Proforma of Agreement for saleProforma of Agreement for sale.pdf · uploaded 21 Mar 2023Source
  • 1 Proforma of Allotment letterProforma of allotment letter.pdf · uploaded 21 Mar 2023Source
  • 1 Copy of the legal title reportlegal report - format A.pdf · uploaded 5 Apr 2023Source
  • 1 a Details of encumbrances concerned to Financeself declaration encumbrance concern - legal.pdf · uploaded 5 Apr 2023Source
  • 1 b Details of encumbrances concerned to Legalself declaration encumbrance concern - legal.pdf · uploaded 5 Apr 2023Source
  • 1 Declaration in FORM Bform B.pdf · uploaded 5 Apr 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the samedeclaration about separate bank account format A.pdf · uploaded 5 Apr 2023Source
  • 1 Deviation Report with respect to Allotment letterdeclaration for no deviation for allotment letter.pdf · uploaded 5 Apr 2023Source
  • 1 Deviation Report with respect to model copy of Agreementdeclaration for no deviation for AIS (agreeement for sale).pdf · uploaded 5 Apr 2023Source
  • 1 CERSAI detailsCresai Details.pdf · uploaded 14 Apr 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA Form I Jun 23- 040324.pdf · uploaded 7 Mar 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA Form I Sep 23 040324.pdf · uploaded 7 Mar 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA Form I Dec 23- 040324.pdf · uploaded 7 Mar 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate-Jun-23.pdf · uploaded 7 Mar 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate-Sep-23.pdf · uploaded 7 Mar 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate-Dec-23.pdf · uploaded 7 Mar 2024Source
  • 2 Disclosure of sold/ booked inventorySold and Unslod booked inventory 3062023.pdf · uploaded 7 Mar 2024Source
  • 3 Disclosure of sold/ booked inventorysold and unsold book inventory 3092023.pdf · uploaded 7 Mar 2024Source
  • 4 Disclosure of sold/ booked inventorysold and unsold booked inventory 31122023.pdf · uploaded 7 Mar 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Jun-23.pdf · uploaded 7 Mar 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Sept 23.pdf · uploaded 7 Mar 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Dec 23.pdf · uploaded 7 Mar 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA Form I-Architect.pdf · uploaded 7 May 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng certifcate - converted.pdf · uploaded 7 May 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Mar 24.pdf · uploaded 7 May 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)AR Certificate-June 24.pdf · uploaded 8 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_30th Jun 2024.pdf · uploaded 8 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate-June 24.pdf · uploaded 8 Oct 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentComencement Certificate.pdf · uploaded 8 Oct 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan.pdf · uploaded 8 Oct 2024Source
  • 2 Disclosure of sold/ booked inventoryDisclosure of sold and unsold inventory.pdf · uploaded 8 Oct 2024Source
  • 1 Declaration about Commencement CertificateDeclaration About Commencement Certificate.pdf · uploaded 8 Oct 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)AR Certificate-Sep 24.pdf · uploaded 14 Nov 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Sep-24.pdf · uploaded 14 Nov 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)ER Certificate- Sep 24.pdf · uploaded 14 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Dec 24.pdf · uploaded 5 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Dec 2024.pdf · uploaded 5 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Dec 24.pdf · uploaded 5 Feb 2025Source
  • 1 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD BOOKED INVENTORY.pdf · uploaded 5 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Dec- 24.pdf · uploaded 6 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arc cer mar-25.pdf · uploaded 3 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Mar-25.pdf · uploaded 3 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Form 2 Mar-25.pdf · uploaded 3 May 2025Source
  • 1 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLDBOOKED INVENTORY 2.pdf · uploaded 3 May 2025Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 29 Sep 2025Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 29 Sep 2025Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 29 Sep 2025Source
  • Withdrawal Update Form 1RERA Form I Sep_2025.pdf · uploaded 17 Dec 2025Source
  • Withdrawal Update Form 2Engineers Form site super.pdf · uploaded 17 Dec 2025Source
  • Withdrawal Update Form 3F3-MOONSTONE (SEPT-25).pdf · uploaded 17 Dec 2025Source
  • Withdrawal Update Form 1Form1 Architects certificate.pdf · uploaded 27 Jan 2026Source
  • Withdrawal Update Form 2From 2 Engineer certificate.pdf · uploaded 27 Jan 2026Source
  • Withdrawal Update Form 3From 3 Swamiji _organized.pdf · uploaded 27 Jan 2026Source
  • Withdrawal Update Form 1Form-1 Arch certificate Moonstone.pdf · uploaded 16 May 2026Source
  • Withdrawal Update Form 2Form-2 moonstone.pdf · uploaded 16 May 2026Source
  • Withdrawal Update Form 3F3-MOONSTONE.pdf · uploaded 16 May 2026Source
  • Withdrawal Update Form 1F1 (2).pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2F2.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3Form 3 swamiji.pdf · uploaded 20 Jul 2026Source
  • Form 2A (FY 2025-2026)Form_2A.pdf · uploaded 6 Aug 2026Source
  • Form 5 (FY 2023-2024)FORM 5 FY 2023-24 MOONSTONE 1.pdf · uploaded 20 Aug 2026Source
  • Form 5 (FY 2024-2025)FORM 5 FY 2024-25 MOONSTONE 3.pdf · uploaded 20 Aug 2026Source
  • Form 5 (FY 2025-2026)FORM 5 FY 2025-26 MOONSTONE 2.pdf · uploaded 20 Aug 2026Source

Technical

  • DocumentNA order.pdf · uploaded 21 Mar 2023Source
  • Documentlayout approval.pdf · uploaded 21 Mar 2023Source
  • Documentbuiliding sanction plan.pdf · uploaded 21 Mar 2023Source
  • DocumentBuilding Plan.pdf · uploaded 8 Oct 2024Source

Technical (Architect)

  • DocumentAR Certificate-June 24.pdf · uploaded 8 Oct 2024Source
  • DocumentAR Certificate-Sep 24.pdf · uploaded 14 Nov 2024Source
  • DocumentForm 1_Dec 24.pdf · uploaded 5 Feb 2025Source
  • DocumentForm 1_Dec- 24.pdf · uploaded 6 Feb 2025Source
  • DocumentArc cer mar-25.pdf · uploaded 3 May 2025Source
  • DocumentF1 (2).pdf · uploaded 20 Jul 2026Source

Technical (Engineer)

  • DocumentEngineers Certificate-June 24.pdf · uploaded 8 Oct 2024Source
  • DocumentER Certificate- Sep 24.pdf · uploaded 14 Nov 2024Source
  • DocumentForm 2_Dec 24.pdf · uploaded 5 Feb 2025Source
  • DocumentEngineers Form 2 Mar-25.pdf · uploaded 3 May 2025Source
  • DocumentF2.pdf · uploaded 20 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel S. NO. 33/3A/1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, Shop35 units in all
Address
S. No. 33/3a/1, S. No. 33/3a/1, Keshav Nagar, Mundhwa, Pune, Near Old Orbis SchoolPIN 411036
Village
Mundhawa, Haveli taluka
Land area for this project
604 sq m (6,501 sq ft)
Permissible built-up area
1,448 sq m (15,585 sq ft)
Sanctioned built-up area
1,448 sq m (15,585 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
27
Developed in phases
No

Survey, CTS, gat or plot numbers

S. NO. 33/3A/1

Land as published on MahaRERA's project page

S. NO. 33/3A/1

Boundaries

North
Road
South
Mr Vyavare Property
East
Road
West
Shapoorji And Palanji Property

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking35 units

17 of 35 units booked (49%), as the promoter reported to MahaRERA

1BHK · 26 units2BHK · 4 unitsShop · 5 units
TypeCarpet areaUnitsBooked
1BHK27.23 sq m · 293 sq ft61
1BHK29 sq m · 312 sq ft60
1BHK29.13 sq m · 314 sq ft51
1BHK34.02 sq m · 366 sq ft22
1BHK36.48 sq m · 393 sq ft33
1BHK41.11 sq m · 443 sq ft11
1BHK44.32 sq m · 477 sq ft11
1BHK49.41 sq m · 532 sq ft21
Show all 15 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
2BHK52.41 sq m · 564 sq ft22
2BHK60.3 sq m · 649 sq ft22
Shop7.72 sq m · 83 sq ft10
Shop8.15 sq m · 88 sq ft10
Shop10.2 sq m · 110 sq ft11
Shop11.62 sq m · 125 sq ft11
Shop13.31 sq m · 143 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRupesh Jamkhindikar—
Chartered accountantAmogh Ghule—
Chartered accountantPankaj P Patil—
EngineerVishal Abasaheb Kunjir—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Mundhawa

All 146 projects in Mundhawa · Compare Moonstone with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology