Crystalplaza
Deedo IDDP-PUN-HJTPIts promised completion date, Aug 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 88% of its units are booked.
Moshi, Pune 412105 · Property rates in Moshi · by S H Developers
Buying a flat here?
See every deed registered on it.
Its promised completion date, Aug 2024, has passed and MahaRERA does not show it completed
- This projectRegistered 23 Oct 2021, completion promised 25 Aug 2024, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
- Rental · Mar 2025
- Loan closure · Jan 2025No amount
- Other · Nov 2024No amount
- Primary sale · Sep 2024
- Mortgage · Sep 2024
- Primary sale · Oct 2023
- Resale · Oct 2023
- Resale · Sep 2023
- Primary sale · Sep 2023
- Primary sale · Aug 2023No amount
| Month | Flat | Kind | Area | Price | Record |
|---|---|---|---|---|---|
| Mar 2025 | Main building · 2 | Rental | — | View Rental, Mar 2025 | |
| Jan 2025 | Main building · 2 | Loan closure | 565 sq ft | View Loan closure, Jan 2025 | |
| Nov 2024 | Not on record | Other | — | View Other, Nov 2024 | |
| Sep 2024 | Main building · 402 | Primary sale | 513 sq ft | View Primary sale, Sep 2024 | |
| Sep 2024 | Main building · 2 | Mortgage | 565 sq ft | View Mortgage, Sep 2024 | |
| Oct 2023 | Main building · 401 | Primary sale | 538 sq ft | View Primary sale, Oct 2023 | |
| Oct 2023 | Main building · 403 | Resale | 457 sq ft | View Resale, Oct 2023 | |
| Sep 2023 | Main building · 3 | Resale | 318 sq ft | View Resale, Sep 2023 | |
| Sep 2023 | Main building · 2 | Primary sale | 253 sq ft | View Primary sale, Sep 2023 | |
| Aug 2023 | Main building · 3 | Primary sale | 318 sq ft | View Primary sale, Aug 2023 |
3 buildings
Open a building to see every flat, floor by floor.
- Building (P52100031406)Size not on record100% booked
- Crystal Plaza9 floors · 16 units88% booked
- Main buildingSize not on record
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100031406
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100031406 | 23 Oct 2021 | 25 Aug 2024 | 25 Aug 2024 | S H Developers | Project page |
Documents73
2 documents held by Deedo, 71 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
- PAN Cardpan card S H Developers.pdf · uploaded 1 Sep 2021Source
Legal
Migrated
- 1 PAN Cardpan card S H Developers.pdf · uploaded 1 Sep 2021Source
Show all 73 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportSearch Report New Final.pdf · uploaded 1 Sep 2021Source
- 1 Details of encumbrancesencombrance Certificate.pdf · uploaded 1 Sep 2021Source
- 1 Copy of Layout Approval (in case of layout)Layout plan 1 Final.pdf · uploaded 1 Sep 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentLayout plan 2 Final.pdf · uploaded 1 Sep 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentcommencement letter.pdf · uploaded 1 Sep 2021Source
- 1 Declaration about Commencement CertificateCommencement Certificate.pdf · uploaded 1 Sep 2021Source
- 1 Declaration in FORM BForm B Final.pdf · uploaded 1 Sep 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Form No 3.pdf · uploaded 1 Sep 2021Source
- 1 Proforma of Allotment letterRERA DRAFT.pdf · uploaded 1 Sep 2021Source
- 1 OtherS H Developers PD Final.pdf · uploaded 1 Sep 2021Source
- 2 Copy of Layout Approval (in case of layout)Floor Plan_compressed.pdf · uploaded 22 Apr 2022Source
- 3 Copy of Layout Approval (in case of layout)Floor Plan 2_compressed.pdf · uploaded 22 Apr 2022Source
- 2 Building Plan Approval / NA Order for plotted developmentBuilding Plan_compressed.pdf · uploaded 22 Apr 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentCommencement Certificate_compressed.pdf · uploaded 22 Apr 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_compressed.pdf · uploaded 22 Apr 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng Certificate.pdf · uploaded 22 Apr 2022Source
- 2 Declaration about Commencement Certificatecommencement certificate F.pdf · uploaded 27 Apr 2022Source
- 1 CERSAI detailsCERSAI_Search_Report.pdf · uploaded 27 Apr 2022Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Form No 3 Final.pdf · uploaded 27 Apr 2022Source
- 1 Disclosure of sold/ booked inventorydescloser of sold-2.pdf · uploaded 2 May 2022Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)PDF CA Form No 3 Final.pdf · uploaded 4 May 2022Source
- 2 Otherformat c concent.pdf · uploaded 4 May 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)S H DEVELOPERS FORM 5 2021-22.pdf · uploaded 15 Apr 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)arct June.pdf · uploaded 7 Nov 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)arct sept.pdf · uploaded 7 Nov 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)jun eng.pdf · uploaded 7 Nov 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)sep eng.pdf · uploaded 7 Nov 2023Source
- 2 Disclosure of sold/ booked inventoryInventory June.pdf · uploaded 7 Nov 2023Source
- 3 Disclosure of sold/ booked inventorysep eng.pdf · uploaded 7 Nov 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)December 2021.pdf · uploaded 16 Dec 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)March 2022.pdf · uploaded 16 Dec 2023Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)June 2022.pdf · uploaded 16 Dec 2023Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Septemebr 2022.pdf · uploaded 16 Dec 2023Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)December 2022.pdf · uploaded 16 Dec 2023Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)March 2023.pdf · uploaded 16 Dec 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)December 2021.pdf · uploaded 16 Dec 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)December 2022.pdf · uploaded 16 Dec 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)June 2022.pdf · uploaded 16 Dec 2023Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)March 2022.pdf · uploaded 16 Dec 2023Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)March 2023.pdf · uploaded 16 Dec 2023Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Septemebr 2022.pdf · uploaded 16 Dec 2023Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)December 2022.pdf · uploaded 16 Dec 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)1 FORM 3 December 2021.pdf · uploaded 16 Dec 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)2 FORM 3 March 2022.pdf · uploaded 16 Dec 2023Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)3 FORM 3 June 2022.pdf · uploaded 16 Dec 2023Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)4 FORM 3 September 2022.pdf · uploaded 16 Dec 2023Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)5 FORM 3 December 2022.pdf · uploaded 16 Dec 2023Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)6 FORM 3 March 2023.pdf · uploaded 16 Dec 2023Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)7 FORM 3 June 2023.pdf · uploaded 16 Dec 2023Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)8 FORM 3 September 2023.pdf · uploaded 16 Dec 2023Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)artc.pdf · uploaded 22 Jan 2024Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)eng.pdf · uploaded 22 Jan 2024Source
- 4 Disclosure of sold/ booked inventoryInventory.pdf · uploaded 22 Jan 2024View
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 2022-23.pdf · uploaded 2 Feb 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 2022-23.pdf · uploaded 2 Feb 2024Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Formation Certificate.pdf · uploaded 20 Apr 2024Source
- 1 Other – TechnicalForm 4 Completion.pdf · uploaded 1 May 2024Source
Technical
- DocumentLayout plan 1 Final.pdf · uploaded 1 Sep 2021Source
- DocumentLayout plan 2 Final.pdf · uploaded 1 Sep 2021Source
- DocumentFloor Plan_compressed.pdf · uploaded 22 Apr 2022Source
- DocumentFloor Plan 2_compressed.pdf · uploaded 22 Apr 2022Source
- DocumentBuilding Plan_compressed.pdf · uploaded 22 Apr 2022Source
- Other – TechnicalForm 4 Completion.pdf · uploaded 1 May 2024Source
Technical (Architect)
- Documentartc.pdf · uploaded 22 Jan 2024Source
Technical (Engineer)
- Documenteng.pdf · uploaded 22 Jan 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel GAT 184 P MOSHI HAVELI PUNE
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, 4BHK, Office space, Shop16 units in all
- Address
- Gat 184 P Moshi Haveli Pune, Alandi Road, SastewadiPIN 412105
- Village
- Moshi, Haveli taluka
- Land area for this project
- 500 sq m (5,382 sq ft)
- Permissible built-up area
- 1,369 sq m (14,740 sq ft)
- Sanctioned built-up area
- 1,309 sq m (14,094 sq ft)
- Designated bank account
- 122
- Developed in phases
- No
- Also registered as
- Tal Plajha, टल प्लाझा, Tal Plaza
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
GAT 184 P MOSHI HAVELI PUNE
Boundaries
- North
- 24 M Wide Road
- South
- GAT NO 184 p
- East
- Gat No 190
- West
- 7 50 M Wide Existing Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking16 units
14 of 16 units booked (88%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 51.07 sq m · 550 sq ft | 1 | 1 |
| 1BHK | 52.15 sq m · 561 sq ft | 1 | 1 |
| 2BHK | 51.9 sq m · 559 sq ft | 1 | 1 |
| 2BHK | 55.1 sq m · 593 sq ft | 1 | 1 |
| 2BHK | 63.25 sq m · 681 sq ft | 1 | 0 |
| 2BHK | 66.85 sq m · 720 sq ft | 1 | 0 |
| 2BHK | 70.61 sq m · 760 sq ft | 1 | 1 |
| 4BHK | 156.12 sq m · 1,680 sq ft | 1 | 1 |
Show all 16 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Office space | 35.6 sq m · 383 sq ft | 1 | 1 |
| Office space | 198.23 sq m · 2,134 sq ft | 1 | 1 |
| Office space | 214.9 sq m · 2,313 sq ft | 1 | 1 |
| Shop | 12.9 sq m · 139 sq ft | 1 | 1 |
| Shop | 17.85 sq m · 192 sq ft | 1 | 1 |
| Shop | 23.5 sq m · 253 sq ft | 1 | 1 |
| Shop | 29 sq m · 312 sq ft | 1 | 1 |
| Shop | 29.5 sq m · 318 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Dipak Nanekar | — |
| Chartered accountant | Ca Ganesh N Gapat | — |
| Engineer | Sanket Hawaldar | — |
Source: MahaRERA project page. Contact details are not shown.
Crystalplaza in numbers
Registered deals, summarised
Deedo has 20 registered documents at Crystalplaza, from Dec 2019 to Mar 2025: 11 sales, 2 leave and licence agreements, 1 mortgage. The median registered sale since Dec 2019 works out to about ₹6,900 per sq ft, at a median of ₹30 L a deal; 18% of sales were resales.
- What is the price per sq ft at Crystalplaza?
- The median registered sale since Dec 2019 works out to about ₹6,900 per sq ft, at a median of ₹30 L a deal; 18% of sales were resales.
- How many properties have been sold at Crystalplaza?
- 11 sales are registered at Crystalplaza, 2 of them resales.
- Are properties at Crystalplaza rented out?
- Yes: 2 leave and licence agreements are registered at Crystalplaza.
- Where does this data come from?
- The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Crystalplaza by Deedo, last updated with deals registered in Mar 2025.
Latest deal · Rental · Mar 2025
Under ₹25 L total