Residential / Group Housing · 1 building · 55 unitsRERA P52100034704

L-Square Prime

Deedo IDDP-PUN-FM64

Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 0% of its units are booked.

Moshi, Pune 412105 · Property rates in Moshi · by Lodha And Lalwani Associates

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 55 units · as the promoter reported to MahaRERAPrice₹6,770 /sq ft1.4% below Moshi · 24 registered sales

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 20 Apr 2022, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

All 35 deeds →
Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Sep 2026Unit 97/37Resale624 sq ftView Resale, Sep 2026
May 2026Unit 97/37Resale851 sq ftView Resale, May 2026
Mar 2026Unit 97/37Resale624 sq ftView Resale, Mar 2026
Feb 2026L-Square Prime · 407Mortgage—View Mortgage, Feb 2026
Feb 2026Unit 97/37Resale614 sq ftView Resale, Feb 2026
Feb 2026Unit 97/37Resale851 sq ftView Resale, Feb 2026
Jan 2026L-Square Prime · 106Mortgage—View Mortgage, Jan 2026
Dec 2025L-Square Prime · 206Mortgage—View Mortgage, Dec 2025
Nov 2025Unit 97/37Resale628 sq ftView Resale, Nov 2025
Nov 2025Unit 97/37Resale628 sq ftView Resale, Nov 2025

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100034704
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210003470420 Apr 202231 Dec 202630 Apr 2027Lodha And Lalwani AssociatesProject page
Documents125

1 document held by Deedo, 124 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CRAD.pdf · uploaded 30 Mar 2022Source

Legal

  • Legal Title reportSearch Report.pdf · uploaded 18 Dec 2021Source
  • Declaration Form BForm B.pdf · uploaded 18 Dec 2021Source
  • Declaration Form Bform b new.pdf · uploaded 7 Apr 2022Source

Migrated

  • 1 Copy of the legal title reportSearch Report.pdf · uploaded 18 Dec 2021Source
  • 1 Details of encumbrancesEncu letter.pdf · uploaded 18 Dec 2021Source
  • 1 Copy of Layout Approval (in case of layout)HPSC1374.pdf · uploaded 18 Dec 2021Source
Show all 125 documentsShow fewer documents

Migrated

  • 2 Copy of Layout Approval (in case of layout)HPSC1376.pdf · uploaded 18 Dec 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommessment Certificate.pdf · uploaded 18 Dec 2021Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 18 Dec 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 18 Dec 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 18 Dec 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentHPSC1376.pdf · uploaded 6 Jan 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 8 Mar 2022Source
  • 1 Proforma of Allotment letterAgreement of Sale from CA Surana-converted.pdf · uploaded 8 Mar 2022Source
  • 1 CERSAI detailsCERSAI Report.pdf · uploaded 16 Mar 2022Source
  • 2 Proforma of Allotment letterProfarma allotment letter.pdf · uploaded 22 Mar 2022Source
  • 1 PAN CardPAN CRAD.pdf · uploaded 30 Mar 2022Source
  • 2 Declaration in FORM Bform b new.pdf · uploaded 7 Apr 2022Source
  • 1 Declaration about Commencement Certificatedeclataion Certificate.pdf · uploaded 8 Apr 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentHPSC1658_compressed.pdf · uploaded 23 Aug 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)DocScanner Aug 3, 2023 3-13 PM.pdf · uploaded 23 Aug 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q2 FY 22-23.pdf · uploaded 16 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q1 FY 22-23.pdf · uploaded 16 Feb 2025Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q4 FY 22-23 (1).pdf · uploaded 16 Feb 2025Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q3 FY 2022-2023 (1).pdf · uploaded 16 Feb 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q2 FY 22-2023.pdf · uploaded 16 Feb 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q1 FY 22-23 fINAL.pdf · uploaded 16 Feb 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q3 FY 22-23 UDIN.pdf · uploaded 16 Feb 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q4 FY 22-23 UDIN.pdf · uploaded 16 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q2 FY 22-23 UDIN.pdf · uploaded 16 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q1 FY 22-23 UDIN.pdf · uploaded 16 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q2 FY 22-23.pdf · uploaded 16 Feb 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q4 FY 22-23.pdf · uploaded 16 Feb 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q3 FY 22-23.pdf · uploaded 16 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q 1 FY 22-23 Final.pdf · uploaded 16 Feb 2025Source
  • 4 Disclosure of sold/ booked inventoryDisclosure Of Sold Inventory Q4 FY 22-23.pdf · uploaded 16 Feb 2025Source
  • 3 Disclosure of sold/ booked inventoryDisclosure Of Sold Inventory Q3 FY 22-23.pdf · uploaded 16 Feb 2025Source
  • 2 Disclosure of sold/ booked inventoryDisclosure Of Sold Inventory Q2 FY 22-23.pdf · uploaded 16 Feb 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure Of Sold Inventory Q1 FY 22-23 Final.pdf · uploaded 16 Feb 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A FY 22-23.pdf · uploaded 16 Feb 2025Source
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q3 FY 24-25.pdf · uploaded 17 Feb 2025Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q1 FY 24-25.pdf · uploaded 17 Feb 2025Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q1 FY 24-25.pdf · uploaded 17 Feb 2025Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q4 FY 23-24.pdf · uploaded 17 Feb 2025Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q3 FY 23-24.pdf · uploaded 17 Feb 2025Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q1 Fy 23-24.pdf · uploaded 17 Feb 2025Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q1 FY 23-24.pdf · uploaded 17 Feb 2025Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3Q3 FY 24-25.pdf · uploaded 17 Feb 2025Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 Q2 FY 24-25.pdf · uploaded 17 Feb 2025Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q1 Fy 24-25.pdf · uploaded 17 Feb 2025Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q4 FY 23-24.pdf · uploaded 17 Feb 2025Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q3 Fy 23-24.pdf · uploaded 17 Feb 2025Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q2 FY 23-24.pdf · uploaded 17 Feb 2025Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q1 FY 23-24.pdf · uploaded 17 Feb 2025Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q3 FY 24-25.pdf · uploaded 17 Feb 2025Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q2 FY 24-25.pdf · uploaded 17 Feb 2025Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q1 FY 24-25.pdf · uploaded 17 Feb 2025Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q4 Fy 23-24.pdf · uploaded 17 Feb 2025Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q3 FY 23-24.pdf · uploaded 17 Feb 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q1 FY 23-24.pdf · uploaded 17 Feb 2025Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q2 FY 23-24.pdf · uploaded 17 Feb 2025Source
  • 6 Disclosure of sold/ booked inventoryDisclosure Of Sold Booked Inventory Q2 FY 23-24.pdf · uploaded 17 Feb 2025Source
  • 11 Disclosure of sold/ booked inventoryDisclosure Of Sold Booked Inventory Q3 FY 24-25.pdf · uploaded 17 Feb 2025Source
  • 10 Disclosure of sold/ booked inventoryDisclosure Of Sold Inventory Q2 FY 24-25.pdf · uploaded 17 Feb 2025Source
  • 9 Disclosure of sold/ booked inventoryDisclosure Of Sold Booked Inventory.pdf · uploaded 17 Feb 2025Source
  • 8 Disclosure of sold/ booked inventoryDisclosure Of Sold Booked Inventory Q4 FY 23-24.pdf · uploaded 17 Feb 2025Source
  • 7 Disclosure of sold/ booked inventoryDisclosure Of Sold Booked Inventory Q3 FY 23-24.pdf · uploaded 17 Feb 2025Source
  • 5 Disclosure of sold/ booked inventoryDisclosure Of Sold Book Inventory Q1 FY 23-24.pdf · uploaded 17 Feb 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Fy 23-24 (1).pdf · uploaded 17 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 FY 22-23.pdf · uploaded 18 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 FY 23-24.pdf · uploaded 18 Feb 2025Source
  • Form 1FORM 1 31 12 2024.pdf · uploaded 13 Oct 2025Source
  • Form 2FORM 2 31 12 2024.pdf · uploaded 13 Oct 2025Source
  • Form 3FORM 3 31 12 2024.pdf · uploaded 13 Oct 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD 31 12 2024.pdf · uploaded 13 Oct 2025Source
  • Form 1FORM 1 31 03 2025.pdf · uploaded 6 Feb 2026Source
  • Form 2FORM 2 31 03 2025.pdf · uploaded 6 Feb 2026Source
  • Form 3Form 3 Q4 24-25.pdf · uploaded 6 Feb 2026Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD 31 03 2025.pdf · uploaded 6 Feb 2026Source
  • Form 1FORM 1 30 06 2025.pdf · uploaded 6 Feb 2026Source
  • Form 2FORM 2 30 06 2025.pdf · uploaded 6 Feb 2026Source
  • Form 3Form 3 Q1 FY 25-26.pdf · uploaded 6 Feb 2026Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD 30 06 2025.pdf · uploaded 6 Feb 2026Source
  • Form 1FORM 1 30 09 2025.pdf · uploaded 6 Feb 2026Source
  • Form 2FORM 2 30 09 2025.pdf · uploaded 6 Feb 2026Source
  • Form 3Form 3 Q2 FY 25-26.pdf · uploaded 6 Feb 2026Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD 30 09 2025.pdf · uploaded 6 Feb 2026Source
  • Withdrawal Update Form 1FORM 1 30 09 2025.pdf · uploaded 12 Feb 2026Source
  • Withdrawal Update Form 1FORM 1 30 09 2025.pdf · uploaded 12 Feb 2026Source
  • Withdrawal Update Form 2FORM 2 30 09 2025.pdf · uploaded 12 Feb 2026Source
  • Withdrawal Update Form 2FORM 2 30 09 2025.pdf · uploaded 12 Feb 2026Source
  • Withdrawal Update Form 3Form 3 Q2 FY 25-26.pdf · uploaded 12 Feb 2026Source
  • Withdrawal Update Form 3Form 3 Q2 FY 25-26.pdf · uploaded 12 Feb 2026Source

Technical

  • DocumentHPSC1374.pdf · uploaded 18 Dec 2021Source
  • DocumentHPSC1376.pdf · uploaded 18 Dec 2021Source
  • DocumentHPSC1376.pdf · uploaded 6 Jan 2022Source
  • DocumentHPSC1658_compressed.pdf · uploaded 23 Aug 2023Source

Technical (Architect)

  • DocumentForm 1 Q1 FY 22-23.pdf · uploaded 16 Feb 2025Source
  • DocumentForm 1 Q2 FY 22-23.pdf · uploaded 16 Feb 2025Source
  • DocumentForm 1 Q1 FY 22-23 fINAL.pdf · uploaded 16 Feb 2025Source
  • DocumentForm 1 Q2 FY 22-2023.pdf · uploaded 16 Feb 2025Source
  • DocumentForm 1 Q3 FY 2022-2023 (1).pdf · uploaded 16 Feb 2025Source
  • DocumentForm 1 Q4 FY 22-23 (1).pdf · uploaded 16 Feb 2025Source
  • DocumentForm 1 Q1 FY 23-24.pdf · uploaded 17 Feb 2025Source
  • DocumentForm 1 Q1 Fy 23-24.pdf · uploaded 17 Feb 2025Source
  • DocumentForm 1 Q3 FY 23-24.pdf · uploaded 17 Feb 2025Source
  • DocumentForm 1 Q4 FY 23-24.pdf · uploaded 17 Feb 2025Source
  • DocumentForm 1 Q1 FY 24-25.pdf · uploaded 17 Feb 2025Source
  • DocumentForm 1 Q1 FY 24-25.pdf · uploaded 17 Feb 2025Source
  • DocumentForm 1 Q3 FY 24-25.pdf · uploaded 17 Feb 2025Source
  • DocumentFORM 1 30 09 2025.pdf · uploaded 12 Feb 2026Source

Technical (Engineer)

  • DocumentForm 2 Q 1 FY 22-23 Final.pdf · uploaded 16 Feb 2025Source
  • DocumentForm 2 Q2 FY 22-23.pdf · uploaded 16 Feb 2025Source
  • DocumentForm 2 Q3 FY 22-23.pdf · uploaded 16 Feb 2025Source
  • DocumentForm 2 Q4 FY 22-23.pdf · uploaded 16 Feb 2025Source
  • DocumentForm 2 Q1 FY 23-24.pdf · uploaded 17 Feb 2025Source
  • DocumentForm 2 Q2 FY 23-24.pdf · uploaded 17 Feb 2025Source
  • DocumentForm 2 Q3 FY 23-24.pdf · uploaded 17 Feb 2025Source
  • DocumentForm 2 Q4 Fy 23-24.pdf · uploaded 17 Feb 2025Source
  • DocumentForm 2 Q1 FY 24-25.pdf · uploaded 17 Feb 2025Source
  • DocumentForm 2 Q2 FY 24-25.pdf · uploaded 17 Feb 2025Source
  • DocumentForm 2 Q3 FY 24-25.pdf · uploaded 17 Feb 2025Source
  • DocumentFORM 2 30 09 2025.pdf · uploaded 12 Feb 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel PLOT NO 97/37, SECTOR NO 06

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK55 units in all
Address
Sector No 06, Plot No 97/37, Sector No 6, Plot No 97/37, MoshiPIN 412105
Village
Moshi, Haveli taluka
Land area for this project
2,024 sq m (21,789 sq ft)
Permissible built-up area
5,107 sq m (54,972 sq ft)
Sanctioned built-up area
5,107 sq m (54,972 sq ft)
Designated bank account
140
Developed in phases
No

Survey, CTS, gat or plot numbers

PLOT NO 97/37SECTOR NO 06

Land as published on MahaRERA's project page

SECTOR NO 06, PLOT NO 97/37

Boundaries

North
Open Space
South
12 5 Partava Remaining Area
East
Plot No 97 21 To 97 23
West
12 M Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking55 units

0 of 55 units booked (0%), as the promoter reported to MahaRERA

2BHK · 26 units3BHK · 29 units
TypeCarpet areaUnitsBooked
2BHK56.7 sq m · 610 sq ft140
2BHK57 sq m · 614 sq ft60
2BHK57.04 sq m · 614 sq ft60
3BHK75.29 sq m · 810 sq ft10
3BHK78.44 sq m · 844 sq ft120
3BHK78.58 sq m · 846 sq ft150
3BHK88.29 sq m · 950 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectUmesh S Namde—
Chartered accountantLalit Ashok Pawar—
EngineerVishal Dalvi—

Source: MahaRERA project page. Contact details are not shown.

L-Square Prime in numbers

Registered deals, summarised

Deedo has 35 registered documents at L-Square Prime, from Apr 2023 to Sep 2026: 24 sales, 1 leave and licence agreement, 9 mortgages. The median registered sale since Apr 2023 works out to about ₹6,800 per sq ft, at a median of ₹44 L a deal; 96% of sales were resales.

What is the price per sq ft at L-Square Prime?
The median registered sale since Apr 2023 works out to about ₹6,800 per sq ft, at a median of ₹44 L a deal; 96% of sales were resales.
How many properties have been sold at L-Square Prime?
24 sales are registered at L-Square Prime, 23 of them resales.
Are properties at L-Square Prime rented out?
Yes: 1 leave and licence agreement is registered at L-Square Prime.
Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at L-Square Prime by Deedo, last updated with deals registered in Sep 2026.

Latest deal · Resale · Sep 2026

₹25–50 L

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · registered documents (Index II)Data through is when MahaRERA's project page was last read.Report a problemMethodology