Skip to content
Others · 5 buildings · 251 unitsRERA P52100002439

Gagan Ela

Deedo IDDP-PUN-YP3P

MahaRERA shows it completed, after its date was pushed back 2 years and 6 months; no MahaRERA orders on record; 80% of its units are booked.

Mohammadwadi, Pune 411060 · Property rates in Mohammadwadi · by Gagan Landmarks Llp

DeliveryCompletedCompletion / occupancy certificate on MahaRERA · after a 2 yrs 6 mo extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales80% booked200 of 251 units · as the promoter reported to MahaRERAPrice₹8,030 /sq ft1.4% below Mohammadwadi · 70 registered sales

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 2 years and 6 months

  • This projectRegistered 1 Aug 2017, completion promised 30 Dec 2022, revised to 30 Jun 2025.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

All 270 deeds →
Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Oct 2026BPrimary sale1,150 sq ftView Primary sale, Oct 2026
Oct 2026APrimary sale733 sq ftView Primary sale, Oct 2026
Oct 2026APrimary sale733 sq ftView Primary sale, Oct 2026
Oct 2026CPrimary sale309 sq ftView Primary sale, Oct 2026
Oct 2026CPrimary sale391 sq ftView Primary sale, Oct 2026
Oct 2026APrimary sale736 sq ftView Primary sale, Oct 2026
Oct 2026APrimary sale736 sq ftView Primary sale, Oct 2026
Oct 2026APrimary sale736 sq ftView Primary sale, Oct 2026
Oct 2026APrimary sale736 sq ftView Primary sale, Oct 2026
Sep 2026BPrimary sale1,126 sq ftView Primary sale, Sep 2026

5 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100002439
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000024391 Aug 201730 Dec 202230 Jun 2025Gagan Landmarks LLPProject page
Documents241

2 documents held by Deedo, 239 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardEla Pan card.pdf · uploaded 25 Jul 2017Source

Legal

  • Legal Title reportTITLE CERTIFICATE 19-07-2017.pdf · uploaded 25 Jul 2017Source
  • Declaration Form BForm B.pdf · uploaded 31 Jul 2017Source
  • Declaration Form BEla form B Dec 17.pdf · uploaded 4 Apr 2018Source
  • OtherGAGAN ELA SHOP COMPLETION.pdf · uploaded 17 Oct 2019Source
  • Declaration Form BForm B.pdf · uploaded 11 Jul 2023Source
Show all 241 documentsShow fewer documents

Legal

  • Declaration Form BForm B.pdf · uploaded 11 Jul 2023Source
  • Declaration Form BForm B_0001.pdf · uploaded 26 Nov 2024Source

Migrated

  • 1 PAN CardEla Pan card.pdf · uploaded 25 Jul 2017Source
  • 1 Copy of the legal title reportTITLE CERTIFICATE 19-07-2017.pdf · uploaded 25 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)1-5.pdf · uploaded 25 Jul 2017Source
  • 1 Building Plan Approval (IOD)2-5.pdf · uploaded 25 Jul 2017Source
  • 2 Building Plan Approval (IOD)3-5.pdf · uploaded 25 Jul 2017Source
  • 3 Building Plan Approval (IOD)4-5.pdf · uploaded 25 Jul 2017Source
  • 4 Building Plan Approval (IOD)5-5.pdf · uploaded 25 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Ela Architect Certificate.pdf · uploaded 25 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentELA CC.pdf · uploaded 26 Jul 2017Source
  • 1 Details of encumbrancesEla encumbrance.pdf · uploaded 27 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ela engg cert.pdf · uploaded 27 Jul 2017Source
  • 1 Certificates of CA (Form 3)ela ca cert.pdf · uploaded 27 Jul 2017Source
  • 1 Proforma of Allotment letterUNIT-AGREEMENT.pdf · uploaded 27 Jul 2017Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 31 Jul 2017Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg Cert Landmarks.pdf · uploaded 31 Mar 2018Source
  • 2 Certificates of CA (Form 3)CA Cert Landmarks.pdf · uploaded 31 Mar 2018Source
  • 2 Details of encumbrancesEla encumbrance Certificate Dec 17.pdf · uploaded 4 Apr 2018Source
  • 2 Declaration in FORM BEla form B Dec 17.pdf · uploaded 4 Apr 2018Source
  • 2 Proforma of Allotment letterUNIT-AGREEMENT GAGAN ELA REVISED.pdf · uploaded 4 Apr 2018Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate Mar'18 Ela.pdf · uploaded 19 Jun 2018Source
  • 3 Certificates of CA (Form 3)CA Certificate Mar'18 Ela.pdf · uploaded 19 Jun 2018Source
  • 1 Certificates of CA (Form 5)Form 5 Gagan Landmark.pdf · uploaded 30 Sep 2018Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Gagan Ela Architects Certificate (2).pdf · uploaded 4 Jan 2019Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Gagan Ela Engineer Certificate.pdf · uploaded 4 Jan 2019Source
  • 4 Certificates of CA (Form 3)CA certificate.pdf · uploaded 4 Jan 2019Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Cretificates.pdf · uploaded 5 Apr 2019Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate 0.pdf · uploaded 5 Apr 2019Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer's Certificate.pdf · uploaded 5 Apr 2019Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer's Certificate 1.pdf · uploaded 5 Apr 2019Source
  • 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer's Certificate.pdf · uploaded 5 Apr 2019Source
  • 5 Certificates of CA (Form 3)CA Certificate (1).pdf · uploaded 5 Apr 2019Source
  • 6 Certificates of CA (Form 3)CA Certificate 2 .pdf · uploaded 5 Apr 2019Source
  • 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate Ela.pdf · uploaded 15 Jun 2019Source
  • 2 Certificates of CA (Form 5)Form 5.pdf · uploaded 28 Sep 2019Source
  • 1 OtherGAGAN ELA SHOP COMPLETION.pdf · uploaded 17 Oct 2019Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate march 2019.pdf · uploaded 26 Dec 2019Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Ela Architects Certificate.pdf · uploaded 26 Dec 2019Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate September 2019.pdf · uploaded 26 Dec 2019Source
  • 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate March 2019.pdf · uploaded 26 Dec 2019Source
  • 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate June 2019.pdf · uploaded 26 Dec 2019Source
  • 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate September 2019.pdf · uploaded 26 Dec 2019Source
  • 7 Certificates of CA (Form 3)C A Certificate March 2019.pdf · uploaded 26 Dec 2019Source
  • 8 Certificates of CA (Form 3)C A Certificate June 2019.pdf · uploaded 26 Dec 2019Source
  • 9 Certificates of CA (Form 3)C A Certificate September 2019.pdf · uploaded 26 Dec 2019Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 14 Aug 2020Source
  • 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 14 Aug 2020Source
  • 10 Certificates of CA (Form 3)Form 3.pdf · uploaded 14 Aug 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5.pdf · uploaded 30 Sep 2020Source
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 4 Nov 2020Source
  • 13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 4 Nov 2020Source
  • 11 Certificates of CA (Form 3)From 3.pdf · uploaded 4 Nov 2020Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)From 5 Gagan Ela.pdf · uploaded 6 Feb 2021Source
  • 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT'S CERTIFICATE.pdf · uploaded 20 Sep 2021Source
  • 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects Certificate.pdf · uploaded 20 Sep 2021Source
  • 14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 20 Sep 2021Source
  • 15 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 20 Sep 2021Source
  • 12 Certificates of CA (Form 3)From 3.pdf · uploaded 20 Sep 2021Source
  • 13 Certificates of CA (Form 3)From 3.pdf · uploaded 20 Sep 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)From 5.pdf · uploaded 30 Sep 2021Source
  • 5 Building Plan Approval (IOD)1-8.pdf · uploaded 30 Oct 2021Source
  • 6 Building Plan Approval (IOD)Wing A.pdf · uploaded 30 Oct 2021Source
  • 7 Building Plan Approval (IOD)Wing B.pdf · uploaded 30 Oct 2021Source
  • 8 Building Plan Approval (IOD)7-8.pdf · uploaded 30 Oct 2021Source
  • 9 Building Plan Approval (IOD)8-8.pdf · uploaded 30 Oct 2021Source
  • 10 Building Plan Approval (IOD)Wing A.pdf · uploaded 30 Oct 2021Source
  • 11 Building Plan Approval (IOD)Wing B.pdf · uploaded 30 Oct 2021Source
  • 12 Building Plan Approval (IOD)Wing B.pdf · uploaded 30 Oct 2021Source
  • 13 Building Plan Approval (IOD)Wing C.pdf · uploaded 30 Oct 2021Source
  • 14 Building Plan Approval (IOD)MADA.pdf · uploaded 30 Oct 2021Source
  • 15 Building Plan Approval (IOD)Wing A.pdf · uploaded 30 Oct 2021Source
  • 16 Building Plan Approval (IOD)Wing B.pdf · uploaded 30 Oct 2021Source
  • 17 Building Plan Approval (IOD)Wing C.pdf · uploaded 30 Oct 2021Source
  • 18 Building Plan Approval (IOD)MADA.pdf · uploaded 30 Oct 2021Source
  • 2 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 1 Nov 2021Source
  • 3 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 1 Nov 2021Source
  • 4 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 1 Nov 2021Source
  • 19 Building Plan Approval (IOD)Wing A 1.pdf · uploaded 1 Nov 2021Source
  • 20 Building Plan Approval (IOD)Wing A (2).pdf · uploaded 1 Nov 2021Source
  • 21 Building Plan Approval (IOD)Wing B.pdf · uploaded 1 Nov 2021Source
  • 22 Building Plan Approval (IOD)Wing c.pdf · uploaded 1 Nov 2021Source
  • 23 Building Plan Approval (IOD)9-9.pdf · uploaded 1 Nov 2021Source
  • 24 Building Plan Approval (IOD)Wing A.pdf · uploaded 1 Nov 2021Source
  • 25 Building Plan Approval (IOD)Wing B.pdf · uploaded 1 Nov 2021Source
  • 26 Building Plan Approval (IOD)Wing C.pdf · uploaded 1 Nov 2021Source
  • 27 Building Plan Approval (IOD)MADA.pdf · uploaded 1 Nov 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentLayout CC.pdf · uploaded 1 Nov 2021Source
  • 3 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 1 Nov 2021Source
  • 4 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 1 Nov 2021Source
  • 5 Commencement Certificates / NA Order for plotted developmentLayout CC.pdf · uploaded 1 Nov 2021Source
  • 1 Declaration about Commencement CertificateCC Declaration.pdf · uploaded 1 Nov 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Quality assurance.pdf · uploaded 1 Nov 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Quality assurance.pdf · uploaded 1 Nov 2021Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Sold inventory.pdf · uploaded 1 Nov 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)From 5.pdf · uploaded 1 Nov 2021Source
  • 3 Details of encumbrancesEncumbrance Certificate.pdf · uploaded 4 Feb 2022Source
  • 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Archtect Certificate.pdf · uploaded 14 Apr 2022Source
  • 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 14 Apr 2022Source
  • 16 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 14 Apr 2022Source
  • 17 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 14 Apr 2022Source
  • 18 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 14 Apr 2022Source
  • 14 Certificates of CA (Form 3)From 3.pdf · uploaded 14 Apr 2022Source
  • 15 Certificates of CA (Form 3)From 3.pdf · uploaded 14 Apr 2022Source
  • 14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 11 Aug 2022Source
  • 15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects Certificate.pdf · uploaded 11 Aug 2022Source
  • 16 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects Certificate.pdf · uploaded 11 Aug 2022Source
  • 17 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 11 Aug 2022Source
  • 18 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 11 Aug 2022Source
  • 19 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 11 Aug 2022Source
  • 20 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 11 Aug 2022Source
  • 21 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 11 Aug 2022Source
  • 22 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 11 Aug 2022Source
  • 23 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 11 Aug 2022Source
  • 16 Certificates of CA (Form 3)Form 3.pdf · uploaded 11 Aug 2022Source
  • 17 Certificates of CA (Form 3)Form 3.pdf · uploaded 11 Aug 2022Source
  • 18 Certificates of CA (Form 3)Form 3.pdf · uploaded 11 Aug 2022Source
  • 19 Certificates of CA (Form 3)Form 3.pdf · uploaded 11 Aug 2022Source
  • 20 Certificates of CA (Form 3)Form 3.pdf · uploaded 11 Aug 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 Gagan Ela.pdf · uploaded 6 Dec 2022Source
  • 19 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 16 Dec 2022Source
  • 24 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 16 Dec 2022Source
  • 21 Certificates of CA (Form 3)Form 3.pdf · uploaded 16 Dec 2022Source
  • 20 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 10 Feb 2023Source
  • 25 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 10 Feb 2023Source
  • 22 Certificates of CA (Form 3)Form 3.pdf · uploaded 10 Feb 2023Source
  • 21 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 9 May 2023Source
  • 26 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 9 May 2023Source
  • 23 Certificates of CA (Form 3)Form 3.pdf · uploaded 9 May 2023Source
  • 4 Details of encumbrancesEncumbrance certificate.pdf · uploaded 11 Jul 2023Source
  • 3 Declaration in FORM BForm B.pdf · uploaded 11 Jul 2023Source
  • 4 Declaration in FORM BForm B.pdf · uploaded 11 Jul 2023Source
  • 22 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 11 Jul 2023Source
  • 27 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 11 Jul 2023Source
  • 24 Certificates of CA (Form 3)Form 3.pdf · uploaded 11 Jul 2023Source
  • 2 Declaration about Commencement CertificateDclaration CC.pdf · uploaded 19 Jul 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Quality Certificate.pdf · uploaded 19 Jul 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Quality Certificate.pdf · uploaded 19 Jul 2023Source
  • 2 Disclosure of sold/ booked inventorySold Unsold Inventory.pdf · uploaded 19 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Gagan Ela.pdf · uploaded 25 Oct 2023Source
  • 23 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 22 Nov 2023Source
  • 28 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 22 Nov 2023Source
  • 25 Certificates of CA (Form 3)Form 3.pdf · uploaded 22 Nov 2023Source
  • 24 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 18 Mar 2024Source
  • 29 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 18 Mar 2024Source
  • 26 Certificates of CA (Form 3)Form 3.pdf · uploaded 18 Mar 2024Source
  • 25 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 12 Aug 2024Source
  • 30 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 12 Aug 2024Source
  • 27 Certificates of CA (Form 3)Form 3.pdf · uploaded 12 Aug 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Ela Form 5.pdf · uploaded 28 Oct 2024Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 15 Nov 2024Source
  • 2 Certificates of CA (Form 3)Form 3.pdf · uploaded 15 Nov 2024Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 15 Nov 2024Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 19 Nov 2024Source
  • 3 Certificates of CA (Form 3)Form 3.pdf · uploaded 19 Nov 2024Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 19 Nov 2024Source
  • 1 Declaration in FORM BForm B_0001.pdf · uploaded 26 Nov 2024Source
  • 2 Disclosure of sold/ booked inventorySold Booked inventory 30 09 2023_0001_11zon.pdf · uploaded 29 Nov 2024Source
  • 3 Disclosure of sold/ booked inventorySold Booked inventory 31 12 2023_0001_11zon.pdf · uploaded 29 Nov 2024Source
  • 4 Disclosure of sold/ booked inventorySold Booked inventory 31 03 2024_0001_11zon.pdf · uploaded 29 Nov 2024Source
  • 5 Disclosure of sold/ booked inventorySold Booked inventory 30 06 2024_0001_11zon.pdf · uploaded 29 Nov 2024Source
  • 6 Disclosure of sold/ booked inventorySold Booked inventory 30 09 2024_0001_11zon.pdf · uploaded 29 Nov 2024Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 18 Jan 2025Source
  • 1 Certificates of CA (Form 3)Form 3.pdf · uploaded 18 Jan 2025Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 18 Jan 2025Source
  • 1 Disclosure of sold/ booked inventorySold Unsold Gagan Ela 31 12 2024_compressed.pdf · uploaded 6 Feb 2025Source
  • 1 Other – TechnicalPert chart gagan ela.pdf · uploaded 13 Mar 2025Source
  • 1 Disclosure of sold/ booked inventoryForm 3 gagan ela.pdf · uploaded 21 Mar 2025Source
  • 2 Disclosure of sold/ booked inventorySold Unsold Gagan Ela.pdf · uploaded 21 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Gagan Ela Form 2A Name added.pdf · uploaded 25 Mar 2025Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 17 Apr 2025Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 17 Apr 2025Source
  • 1 Certificates of CA (Form 3)Form 3.pdf · uploaded 5 May 2025Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 5 May 2025Source
  • Occupational CertificateGagan Ela Full Completion.pdf · uploaded 30 Jun 2025Source
  • Occupational CertificateOccupancy certificate verification.pdf · uploaded 10 Jul 2025Source
  • Occupational CertificateCommencement Certificate.pdf · uploaded 10 Jul 2025Source
  • Occupational CertificateCommencement Certificate verification.pdf · uploaded 10 Jul 2025Source
  • Occupational CertificateHPSCANNER7701.pdf · uploaded 10 Jul 2025Source
  • Occupational CertificateHPSCANNER7702.pdf · uploaded 10 Jul 2025Source
  • Occupational CertificateHPSCANNER7703.pdf · uploaded 10 Jul 2025Source
  • Occupational CertificateHPSCANNER7704.pdf · uploaded 10 Jul 2025Source
  • Occupational CertificateHPSCANNER7705.pdf · uploaded 10 Jul 2025Source
  • Occupational CertificateHPSCANNER7706.pdf · uploaded 10 Jul 2025Source
  • Occupational CertificateHPSCANNER7707.pdf · uploaded 10 Jul 2025Source
  • Occupational CertificateHPSCANNER7708.pdf · uploaded 10 Jul 2025Source
  • Occupational CertificateHPSCANNER7709.pdf · uploaded 10 Jul 2025Source
  • Occupational CertificateHPSCANNER7710.pdf · uploaded 10 Jul 2025Source
  • Occupational CertificateHPSCANNER7711.pdf · uploaded 10 Jul 2025Source
  • Form 5 (FY 2024-2025)Form 5.pdf · uploaded 2 Dec 2025Source

Technical

  • Document1-5.pdf · uploaded 25 Jul 2017Source
  • Document2-5.pdf · uploaded 25 Jul 2017Source
  • Document3-5.pdf · uploaded 25 Jul 2017Source
  • Document4-5.pdf · uploaded 25 Jul 2017Source
  • Document5-5.pdf · uploaded 25 Jul 2017Source
  • Document1-8.pdf · uploaded 30 Oct 2021Source
  • DocumentWing A.pdf · uploaded 30 Oct 2021Source
  • DocumentWing B.pdf · uploaded 30 Oct 2021Source
  • Document7-8.pdf · uploaded 30 Oct 2021Source
  • Document8-8.pdf · uploaded 30 Oct 2021Source
  • DocumentWing A.pdf · uploaded 30 Oct 2021Source
  • DocumentWing B.pdf · uploaded 30 Oct 2021Source
  • DocumentWing B.pdf · uploaded 30 Oct 2021Source
  • DocumentWing C.pdf · uploaded 30 Oct 2021Source
  • DocumentMADA.pdf · uploaded 30 Oct 2021Source
  • DocumentWing A.pdf · uploaded 30 Oct 2021Source
  • DocumentWing B.pdf · uploaded 30 Oct 2021Source
  • DocumentWing C.pdf · uploaded 30 Oct 2021Source
  • DocumentMADA.pdf · uploaded 30 Oct 2021Source
  • DocumentWing A 1.pdf · uploaded 1 Nov 2021Source
  • DocumentWing A (2).pdf · uploaded 1 Nov 2021Source
  • DocumentWing B.pdf · uploaded 1 Nov 2021Source
  • DocumentWing c.pdf · uploaded 1 Nov 2021Source
  • Document9-9.pdf · uploaded 1 Nov 2021Source
  • DocumentWing A.pdf · uploaded 1 Nov 2021Source
  • DocumentWing B.pdf · uploaded 1 Nov 2021Source
  • DocumentWing C.pdf · uploaded 1 Nov 2021Source
  • DocumentMADA.pdf · uploaded 1 Nov 2021Source
  • DocumentLayout.pdf · uploaded 1 Nov 2021Source
  • DocumentLayout.pdf · uploaded 1 Nov 2021Source
  • DocumentLayout.pdf · uploaded 1 Nov 2021Source
  • Other – TechnicalPert chart gagan ela.pdf · uploaded 13 Mar 2025Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 12 Aug 2024Source
  • DocumentForm 1.pdf · uploaded 15 Nov 2024Source
  • DocumentForm 1.pdf · uploaded 19 Nov 2024Source
  • DocumentForm 1.pdf · uploaded 18 Jan 2025Source
  • DocumentForm 1.pdf · uploaded 17 Apr 2025Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 12 Aug 2024Source
  • DocumentForm 2.pdf · uploaded 15 Nov 2024Source
  • DocumentForm 2.pdf · uploaded 19 Nov 2024Source
  • DocumentForm 2.pdf · uploaded 18 Jan 2025Source
  • DocumentForm 2.pdf · uploaded 17 Apr 2025Source
  • DocumentForm 2.pdf · uploaded 5 May 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 23/7/1, 23/7/2

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
2 BHK, 2BHK, Pent house, Pent House, PentHouse, 3 BHK, 3BHK, 1BHK, 1RK, Shop251 units in all
Address
23/7/1, 23/7/2, 23/7/3 P, NIBM Road, MohammadwadiPIN 411060
Village
Mohammadwadi, Haveli taluka
Land area for this project
9,098 sq m (97,934 sq ft)
Permissible built-up area
15,460 sq m (1,66,414 sq ft)
Sanctioned built-up area
4,928 sq m (53,044 sq ft)
Recreational open space
874 sq m (9,403 sq ft)
Designated bank account
76
Developed in phases
Yes
Also registered as
Gagan Ela Commercial Complex, Ganga Ella

Survey, CTS, gat or plot numbers

23/7/123/7/223/7/3 P

Land as published on MahaRERA's project page

23/7/1, 23/7/2, 23/7/3 P

Boundaries

North
S No 24
South
Road
East
S no 23
West
S No 23

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking251 units

200 of 251 units booked (80%), as the promoter reported to MahaRERA

2 BHK · 15 units2BHK · 105 unitsPent house · 2 unitsPent House · 9 unitsPentHouse · 1 unit3 BHK · 8 units3BHK · 52 units1BHK · 18 units1RK · 6 unitsShop · 35 units
BuildingTypeCarpet areaUnitsBooked
A2 BHK53.49 sq m · 576 sq ft11
A2 BHK53.95 sq m · 581 sq ft11
A2 BHK54.27 sq m · 584 sq ft44
A2 BHK54.55 sq m · 587 sq ft64
A2 BHK59.3 sq m · 638 sq ft11
A2 BHK61.46 sq m · 662 sq ft22
A2BHK54.6 sq m · 588 sq ft86
A2BHK55 sq m · 592 sq ft76
Show all 74 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
A2BHK55.02 sq m · 592 sq ft65
A2BHK55.06 sq m · 593 sq ft85
A2BHK55.08 sq m · 593 sq ft85
A2BHK56.54 sq m · 609 sq ft77
A2BHK56.55 sq m · 609 sq ft66
A2BHK56.72 sq m · 611 sq ft1312
A2BHK60.51 sq m · 651 sq ft75
A2BHK60.61 sq m · 652 sq ft74
A2BHK61.48 sq m · 662 sq ft22
A2BHK61.81 sq m · 665 sq ft1110
A2BHK61.99 sq m · 667 sq ft1514
APent house69.97 sq m · 753 sq ft22
APent House70.76 sq m · 762 sq ft11
APent House71.21 sq m · 766 sq ft11
APent House75.24 sq m · 810 sq ft22
APent House76.73 sq m · 826 sq ft11
APentHouse71.24 sq m · 767 sq ft11
B3 BHK78.94 sq m · 850 sq ft11
B3 BHK79.97 sq m · 861 sq ft11
B3 BHK82.81 sq m · 891 sq ft10
B3 BHK82.82 sq m · 891 sq ft11
B3 BHK90.7 sq m · 976 sq ft10
B3 BHK90.9 sq m · 978 sq ft10
B3 BHK94.63 sq m · 1,019 sq ft11
B3 BHK96.65 sq m · 1,040 sq ft11
B3BHK79.02 sq m · 851 sq ft11
B3BHK79.92 sq m · 860 sq ft55
B3BHK79.93 sq m · 860 sq ft77
B3BHK81.23 sq m · 874 sq ft85
B3BHK81.27 sq m · 875 sq ft62
B3BHK83.28 sq m · 896 sq ft64
B3BHK83.46 sq m · 898 sq ft62
B3BHK91.18 sq m · 981 sq ft74
B3BHK91.38 sq m · 984 sq ft63
BPent House112 sq m · 1,206 sq ft11
BPent House113.29 sq m · 1,219 sq ft10
BPent House117.01 sq m · 1,259 sq ft11
BPent House124.99 sq m · 1,345 sq ft11
Commercial and MHADA1BHK36.96 sq m · 398 sq ft33
Commercial and MHADA1BHK37.02 sq m · 398 sq ft1210
Commercial and MHADA1BHK38.73 sq m · 417 sq ft33
Commercial and MHADA1RK30.22 sq m · 325 sq ft31
Commercial and MHADA1RK32.23 sq m · 347 sq ft31
Commercial and MHADAShop28.15 sq m · 303 sq ft22
Commercial and MHADAShop14.62 sq m · 157 sq ft11
Commercial and MHADAShop14.63 sq m · 157 sq ft11
Commercial and MHADAShop14.96 sq m · 161 sq ft10
Commercial and MHADAShop15.92 sq m · 171 sq ft22
Commercial and MHADAShop15.93 sq m · 171 sq ft11
Commercial and MHADAShop17.96 sq m · 193 sq ft11
Commercial and MHADAShop20.51 sq m · 221 sq ft11
Commercial and MHADAShop20.7 sq m · 223 sq ft21
Commercial and MHADAShop20.72 sq m · 223 sq ft11
Commercial and MHADAShop20.82 sq m · 224 sq ft11
Commercial and MHADAShop22.28 sq m · 240 sq ft33
Commercial and MHADAShop22.33 sq m · 240 sq ft22
Commercial and MHADAShop22.51 sq m · 242 sq ft55
Commercial and MHADAShop37.48 sq m · 403 sq ft22
Commercial and MHADAShop37.5 sq m · 404 sq ft22
Commercial and MHADAShop37.57 sq m · 404 sq ft11
Commercial and MHADAShop38.92 sq m · 419 sq ft11
Commercial and MHADAShop45.15 sq m · 486 sq ft11
Commercial and MHADAShop45.17 sq m · 486 sq ft11
Commercial and MHADAShop46.07 sq m · 496 sq ft11
Commercial and MHADAShop46.88 sq m · 505 sq ft11
Commercial and MHADAShop47.42 sq m · 510 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals40

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMr.Rahul Malvadkar—
EngineerMr.Rajesh Mankani—
OtherMr.Ghansham—
OtherMr.Ghule—
OtherMr.Gurudatta—
OtherMr.Janardhan Ghule—
OtherMr.Kishor Khetwat—
OtherMr.Nitin Kamathe—
Show all 40 professionalsShow fewer professionals
RoleNameRegistration no.
OtherMr.Ramu Chavan—
OtherMr.Sachin Bhangire—
OtherMr.Shekhar Tamhane—
OtherMr. Soudagar—
Registered real estate agentAddressofchoice Realty Pvt Ltd—
Registered real estate agentAjaypalsingh Harpalsingh Hoonjan—
Registered real estate agentAkash Amolokchand Khater—
Registered real estate agentAmit Arvind Sodani—
Registered real estate agentAmit Surendra Partani—
Registered real estate agentAsfaque Ahmed Sayyed—
Registered real estate agentAshish Modi—
Registered real estate agentBhisham Suresh Parwani—
Registered real estate agentBluenest Properties LLP—
Registered real estate agentEstateMint Pvt Ltd—
Registered real estate agentHusain Kutubuddin Khumanpurwala—
Registered real estate agentInvestadvise Wealth Management Private Limited—
Registered real estate agentKirankumar Tarachand Chopda—
Registered real estate agentKutubuddin Gulamali Khumanpurwala—
Registered real estate agentMint Lifespaces—
Registered real estate agentMurtaza Husaini Hathaiwala—
Registered real estate agentMustafa Mufazzal kachwala—
Registered real estate agentOptimus Realtors—
Registered real estate agentParag Madhukar Kamble—
Registered real estate agentParesh Lachman Hardwani—
Registered real estate agentPremlata Estate Solutions Pvt. Ltd.—
Registered real estate agentPrerana Ventures LLP—
Registered real estate agentRajan Gautam—
Registered real estate agentRaviraj Gangaprasad Thanvi—
Registered real estate agentSignet Space Realty Private Limited—
Registered real estate agenttaher zakir tailor—
Registered real estate agentThomas C Abraham—
Registered real estate agentVikas Satish Gupta—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Mohammadwadi

All 1,034 projects in Mohammadwadi · Compare Gagan Ela with another project

Gagan Ela in numbers

Registered deals, summarised

Deedo has 270 registered documents at Gagan Ela, from Feb 2017 to Oct 2026: 70 sales, 115 leave and licence agreements, 70 mortgages. The median registered sale since Feb 2017 works out to about ₹8,000 per sq ft, at a median of ₹61 L a deal; 16% of sales were resales.

What is the price per sq ft at Gagan Ela?
The median registered sale since Feb 2017 works out to about ₹8,000 per sq ft, at a median of ₹61 L a deal; 16% of sales were resales.
How many properties have been sold at Gagan Ela?
70 sales are registered at Gagan Ela, 11 of them resales.
Are properties at Gagan Ela rented out?
Yes: 115 leave and licence agreements are registered at Gagan Ela, at a median rent since Feb 2017 of about ₹23,000 a month with a deposit of about ₹55,000.
Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Gagan Ela by Deedo, last updated with deals registered in Oct 2026.

Latest deal · Primary sale · Oct 2026

₹75 L–1 Cr

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · registered documents (Index II)Data through is when MahaRERA's project page was last read.Report a problemMethodology