Deedo IDDP-PUN-7PY1Completion was pushed back 4 months, to Jul 2028; no MahaRERA orders on record; 0% of its units are booked.
Manjari Bk, Pune 412307 · Property rates in Manjari Bk · by Aware Construction
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Jul 2028
- This projectRegistered 16 Jun 2025, completion promised 31 Mar 2028, revised to 31 Jul 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100080578
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100080578 | 16 Jun 2025 | 31 Mar 2028 | 31 Jul 2028 | Aware Construction | Project page |
Documents62
1 document held by Deedo, 61 filings listed on MahaRERA's project page
Finance
Show all 62 documentsShow fewer documents
Migrated
- 2 PAN CardPAN CARD - BALAJI AWARE.pdf · uploaded 30 Mar 2025Source
- 3 PAN CardPAN CARD - SUSHRITA SUMAN.pdf · uploaded 30 Mar 2025Source
- 4 PAN CardPAN CARD - LANDOWNER.pdf · uploaded 30 Mar 2025Source
- 1 PAN CardPAN CARD - AWARE CONSTRUCTION.pdf · uploaded 30 Mar 2025Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE_compressed.pdf · uploaded 30 Mar 2025Source
- 1 Building Plan Approval / NA Order for plotted developmentSANCTION PLAN_compressed.pdf · uploaded 30 Mar 2025Source
- 1 a Details of encumbrances concerned to FinanceNO ENCUMBRANCE - Financial and Legal.pdf · uploaded 12 Apr 2025Source
- 1 Copy of Layout Approval (in case of layout)LAND LAYOUT.pdf · uploaded 12 Apr 2025Source
- 1 Declaration in FORM BAFFIDAVIT FORM B - DEVELOPER.pdf · uploaded 12 Apr 2025Source
- 2 Declaration in FORM BAFFIDAVIT FORM B - LANDOWNER.pdf · uploaded 12 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - ARCHITECT CERTIFICATE.pdf · uploaded 12 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 - ENGINEER CERTIFICATE.pdf · uploaded 12 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure of Sold, Booked inventory.pdf · uploaded 12 Apr 2025Source
- 1 b Details of encumbrances concerned to LegalNO ENCUMBRANCE - Financial and Legal.pdf · uploaded 12 Apr 2025Source
- 1 Disclosure for secured/unsecured finance availed for the projectDeclaration - Secured Unsecured Finance.pdf · uploaded 12 Apr 2025Source
- 1 Copy of the legal title reportLEGAL TITLE REPORT - NEW.pdf · uploaded 30 May 2025Source
- 1 Proforma of Allotment letterALLOTMENT LETTER - DRAFT REVISED_compressed.pdf · uploaded 30 May 2025Source
- 2 Commencement Certificates / NA Order for plotted developmentCONFIRMATION MAIL FROM PMRDA - SCREENSHOT.pdf · uploaded 30 May 2025Source
- 1 Declaration about Commencement CertificateFORMAT D Declaration - Commencement Certificate - new.pdf · uploaded 30 May 2025Source
- 1 Deviation Report with respect to Allotment letterDeclaration - Deviation with respect to allotment letter - NEW.pdf · uploaded 30 May 2025Source
- 1 Other – TechnicalAnnexure A - Declaration - Cum Undertaking.pdf · uploaded 30 May 2025Source
- 2 Other – TechnicalCONFIRMATION MAIL FROM PMRDA - SCREENSHOT.pdf · uploaded 30 May 2025Source
- 1 Deviation Report with respect to model copy of AgreementDeclaration - Deviation with respect to model copy of agreement- NEW.pdf · uploaded 30 May 2025Source
- 1 Proforma of Agreement for saleAGREEMENT FOR SALE DRAFT - REVISED AS PER RERA STANDARD FORMAT.pdf · uploaded 30 May 2025Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)BANK DECLARATION FORMAT B - DEVELOPER.pdf · uploaded 30 May 2025Source
- 2 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)BANK DECLARATION FORMAT B - LANDOWNER_compressed.pdf · uploaded 30 May 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 WITH LANDOWNERS UNIT CONSIDERATION_compressed.pdf · uploaded 12 Jun 2025Source
- 1 CERSAI detailsUNDERTAKING - FOR CERSAI REPORT.pdf · uploaded 12 Jun 2025Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)BANK DECLARATION FORMAT A.pdf · uploaded 12 Jun 2025Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsANNEXURE A - PARTNER 1.pdf · uploaded 12 Jun 2025Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsANNEXURE A - PARTNER 2.pdf · uploaded 12 Jun 2025Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 18 Aug 2025Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 18 Aug 2025Source
- Withdrawal Update Form 3FORM 3.pdf · uploaded 18 Aug 2025Source
- Withdrawal Update Form 1FORM 1 30 09 25.pdf · uploaded 8 Nov 2025Source
- Withdrawal Update Form 2FORM 2 30 09 25.pdf · uploaded 8 Nov 2025Source
- Withdrawal Update Form 3FORM 3 30 09 25.pdf · uploaded 8 Nov 2025Source
- Withdrawal Update Form 1FORM 1 - 31-12-25.pdf · uploaded 28 Jan 2026Source
- Withdrawal Update Form 2FORM 2 - 31-12-25.pdf · uploaded 28 Jan 2026Source
- Withdrawal Update Form 3FORM 3 - 31-12-25.pdf · uploaded 28 Jan 2026Source
- Withdrawal Update Form 1FORM 1 - 31-03-2026.pdf · uploaded 25 Apr 2026Source
- Withdrawal Update Form 2FORM 2 - 31-03-2026.pdf · uploaded 25 Apr 2026Source
- Withdrawal Update Form 3FORM 3 - 31-03-2026.pdf · uploaded 25 Apr 2026Source
- Withdrawal Update Form 1FORM 1 - 30-06-26.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 2FORM 2 - 30-06-26.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 3FORM 3 - 30-06-26.pdf · uploaded 20 Jul 2026Source
- Form 5 (FY 2025-2026)RERA FORM 5 FY 25-26.pdf · uploaded 8 Sep 2026Source
- Form 2A (FY 2025-2026)FORM 2A - FY 2025-26.pdf · uploaded 30 Sep 2026Source
Technical
- DocumentSANCTION PLAN_compressed.pdf · uploaded 30 Mar 2025Source
- DocumentLAND LAYOUT.pdf · uploaded 12 Apr 2025Source
- Other – TechnicalAnnexure A - Declaration - Cum Undertaking.pdf · uploaded 30 May 2025Source
- Other – TechnicalCONFIRMATION MAIL FROM PMRDA - SCREENSHOT.pdf · uploaded 30 May 2025Source
Technical (Architect)
- DocumentFORM 1 - 30-06-26.pdf · uploaded 20 Jul 2026Source
Technical (Engineer)
- DocumentFORM 2 - 30-06-26.pdf · uploaded 20 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel HISSA NO. 4, SR. NO. 80
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Land owners share24 units in all
- Address
- Sr. No. 80, Hissa No. 4, Manjari Bk, Manjari BkPIN 412307
- Village
- MANJARI Bk, Haveli taluka
- Land area for this project
- 875 sq m (9,418 sq ft)
- Permissible built-up area
- 2,778 sq m (29,903 sq ft)
- Sanctioned built-up area
- 1,469 sq m (15,812 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 109
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
SR. NO. 80, HISSA NO. 4
Boundaries
- North
- Property Of Savita Uttam Kalbhor
- South
- Property Of Rajshree Sanjay Kalate
- East
- Sr No 81 Property Of Ravi Garden Society
- West
- Internal Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking24 units
0 of 24 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 33.06 sq m · 356 sq ft | 6 | 0 |
| 2BHK | 53.73 sq m · 578 sq ft | 6 | 0 |
| Land owners share | 33.06 sq m · 356 sq ft | 6 | 0 |
| Land owners share | 53.73 sq m · 578 sq ft | 6 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Mukta Bramha Bolke | — |
| Chartered accountant | Pravin Eknath Pise | — |
| Chartered accountant | Vaibhav S Bhise & Associates | — |
| Engineer | Tejas Shivaji Yede | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Manjari Bk
- MAGNACITY - Tower A1RERA PR1262022601769
- Mizura Residences by EsbeeRERA PM1260002502579
- The AstriaRERA PR1260002502313
- Dhvanil HarmonyRERA PR1260002502288
- The GreciaRERA PM1260002500700
- Birla Evam Phase 1RERA PR1261012500295
- Shakuntala SankulRERA P52100080673
- Airawat HeritageRERA P52100080637
All 45 projects in Manjari Bk · Compare Radhe with another project