Skip to content
Residential / Group Housing · 1 building · 36 unitsRERA P52100016362

Datta Vihar

Deedo IDDP-PUN-ZTDT

MahaRERA shows it completed, after its date was pushed back 2 years; no MahaRERA orders on record; 94% of its units are booked.

Manchar (Ct), Pune 410503 · by Shree Umiya Buildcon

DeliveryCompletedCompletion / occupancy certificate on MahaRERA · after a 2 yrs extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales94% booked34 of 36 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 2 years

  • This projectRegistered 8 May 2018, completion promised 31 Dec 2019, revised to 30 Dec 2021.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100016362
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000163628 May 201831 Dec 201930 Dec 2021Shree Umiya BuildconProject page
Documents29

2 documents held by Deedo, 27 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPAN.pdf · uploaded 14 Apr 2018Source

Legal

  • Declaration Form BDECLARATION.pdf · uploaded 14 Apr 2018Source
  • Legal Title reportTITLE REPORT.pdf · uploaded 14 Apr 2018Source

Migrated

  • 1 PAN CardPAN.pdf · uploaded 14 Apr 2018Source
  • 1 Copy of the legal title reportTITLE REPORT.pdf · uploaded 14 Apr 2018Source
  • 1 Details of encumbrancesCERTIFICATE ENCUMBRANCES.pdf · uploaded 14 Apr 2018Source
Show all 29 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)plan 2.pdf · uploaded 14 Apr 2018Source
  • 1 Building Plan Approval (IOD)plan 1.pdf · uploaded 14 Apr 2018Source
  • 2 Building Plan Approval (IOD)plan 2.pdf · uploaded 14 Apr 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentdoc 1.pdf · uploaded 14 Apr 2018Source
  • 1 Declaration in FORM BDECLARATION.pdf · uploaded 14 Apr 2018Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1.pdf · uploaded 14 Apr 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2.pdf · uploaded 14 Apr 2018Source
  • 1 Certificates of CA (Form 3)FORM 3 RERA.pdf · uploaded 14 Apr 2018Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 14 Apr 2018Source
  • 2 Proforma of Allotment letterAGREEMENT DRAFT COPY.pdf · uploaded 1 May 2018Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1.pdf · uploaded 24 Dec 2019Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2.pdf · uploaded 24 Dec 2019Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2A.pdf · uploaded 24 Dec 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 Shree Umiya Buildcon.pdf · uploaded 3 Jan 2020Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOCCUPANCY CERTIFICATE.pdf · uploaded 5 Dec 2020Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4.pdf · uploaded 8 Apr 2021Source

Technical

  • Documentplan 1.pdf · uploaded 14 Apr 2018Source
  • Documentplan 2.pdf · uploaded 14 Apr 2018Source
  • Documentplan 2.pdf · uploaded 14 Apr 2018Source

Technical (Architect)

  • DocumentFORM 1.pdf · uploaded 24 Dec 2019Source

Technical (Engineer)

  • DocumentFORM 2.pdf · uploaded 24 Dec 2019Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 124/2

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1 BHK36 units in all
Address
124/2, Gokarneshwar Nagar, Dobi MalaPIN 410503
Village
Manchar (CT), Ambegaon taluka
Land area for this project
1,800 sq m (19,375 sq ft)
Permissible built-up area
1,611 sq m (17,336 sq ft)
Sanctioned built-up area
1,611 sq m (17,336 sq ft)
Recreational open space
257 sq m (2,767 sq ft)
Designated bank account
109
Developed in phases
No

Survey, CTS, gat or plot numbers

124/2

Land as published on MahaRERA's project page

124/2

Boundaries

North
Property Of Bankhele
South
Property Of Kharmale And Bankhele
East
Property Of Daine
West
Gramapanchayat Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking36 units

34 of 36 units booked (94%), as the promoter reported to MahaRERA

1 BHK · 36 units
TypeCarpet areaUnitsBooked
1 BHK31.87 sq m · 343 sq ft21
1 BHK32.43 sq m · 349 sq ft22
1 BHK35.66 sq m · 384 sq ft22
1 BHK35.91 sq m · 387 sq ft22
1 BHK35.97 sq m · 387 sq ft44
1 BHK36.13 sq m · 389 sq ft22
1 BHK36.22 sq m · 390 sq ft22
1 BHK36.41 sq m · 392 sq ft22
Show all 14 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
1 BHK36.63 sq m · 394 sq ft22
1 BHK36.84 sq m · 397 sq ft22
1 BHK36.97 sq m · 398 sq ft43
1 BHK37.05 sq m · 399 sq ft44
1 BHK37.32 sq m · 402 sq ft22
1 BHK37.97 sq m · 409 sq ft44

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPrecision Architect & Planner—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology