Shree Umiya Buildcon
Deedo IDDD-98CBOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Delivery record
3 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Datta ViharP52100016362 | Manchar (Ct) | Certificate Signed | 31 Dec 2019 | 30 Dec 2021 | +24 mo |
| Tathastu Phase-IP52100055321 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | On date |
| TathastuP52100079143 | Chovisawadi | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 mo |
| TathastuPR1260002501478 | Chovisawadi | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| TathastuPM1260002602714 | Chovisawadi | Not on record | 31 Dec 2029 | — | On date |
Shree Umiya Buildcon, in questions
Does Shree Umiya Buildcon finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shree Umiya Buildcon registered with MahaRERA?
3 projects under 5 MahaRERA registrations; 2 completed on MahaRERA.
Does Shree Umiya Buildcon have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.