RERA projects in Manchar (Ct)
28 projects under 29 MahaRERA registrations, registered 2017–2026. 48% have a completion date extended beyond the one promised.
Locality
28RERA projects
29Registrationssome projects hold several
11Completion still due18 past their completion date
4 monthsMedian extension beyond promised date48% of registrations extended
0Regulatory casesnone on MahaRERA's lists
62Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 12 |
| 2018 | 1 |
| 2019 | 1 |
| 2020 | 2 |
| 2021 | 2 |
| 2022 | 0 |
| 2023 | 1 |
| 2024 | 3 |
| 2025 | 4 |
| 2026 | 3 |
Projects in Manchar (Ct)
28 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| The Central Park Phase-1Supreme Infra | PR1260002602293 | 14 Oct 2026 | 31 Dec 2030 | — | Not yet due | 0 |
| The Central Park Phase-2Supreme Infra | PR1260002602031 | 24 Sep 2026 | 31 Dec 2033 | 31 Dec 2033 | Not yet due | 0 |
| Aarambh ResidencySupreme Infra | PR1260002502973 | 18 Mar 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Anandi MalharReliable Constructions | PR1260002501174 | 10 Oct 2025 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Crystal CrownCrystal Developers | PR1260002501160 | 9 Oct 2025 | 5 Mar 2029 | 5 Jul 2029 | Extended 4 mo | 0 |
| Megh Malhar ResidencySungrace Infra Projects | P52100080196 | 6 May 2025 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| SRP Business SquareS R P Developer | P52100079309 | 28 Feb 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Kuber Mudra MeadowsVikas Vilas Bhalgat | P52100077821 | 7 Nov 2024 | 29 Aug 2027 | 29 Dec 2027 | Extended 4 mo | 0 |
| Saffron VillasNupur Landmarks Private Limited | P52100056443 | 31 May 2024 | 1 Jan 2028 | 1 May 2028 | Extended 4 mo | 0 |
| Yamunai ResidencyShivshri Developers | P52100056046 | 10 May 2024 | 26 Jan 2028 | 26 May 2028 | Extended 4 mo | 0 |
| 24 ElementsS.p. Builders And Developers | P52100052370 | 21 Aug 2023 | 2 May 2026 | 2 May 2026 | Promised date passed | 0 |
| Magnam ParkShri Bhairav Builders | P52100028080 | 31 Jan 2021 | 30 Jun 2023 | 30 Jun 2023 | Promised date passed | 0 |
| SairajLaxmideep Infrastructures | P52100026844 | 31 Oct 2020 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Nakashtra Residency DhanishthaSupreme Infra | P52100026061 | 12 Aug 2020 | 25 Jun 2026 | 25 Jun 2026 | Promised date passed | 0 |
| Project At 168 19 Gulmohar ResidencySungrace Infra Projects | P52100023626 | 24 Dec 2019 | 30 Dec 2024 | 30 Dec 2024 | Promised date passed | 0 |
| Datta ViharShree Umiya Buildcon | P52100016362 | 8 May 2018 | 31 Dec 2019 | 30 Dec 2021 | Extended 24 mo | 0 |
| Sai PoojaValse Gholap Associates | P52100013314 | 22 Sep 2017 | 15 May 2018 | 15 May 2018 | Promised date passed | 0 |
| Sonigara KimayaSonigara Sawant Enterprises | P52100012331 | 1 Sep 2017 | 14 Jul 2022 | 25 Nov 2022 | Extended 4 mo | 0 |
| Lalbag PrestigeReliable Construction | P52100010952, P52100028585 | 31 Aug 2017 | 30 Jun 2025 | 30 Jun 2025 | Promised date passed | 0 |
| Ganraya PlazaVasant Vishnu Bankhele With Atul Baliram Thorat Association Of Persons | P52100009301 | 22 Aug 2017 | 31 Dec 2018 | 31 Dec 2018 | Promised date passed | 0 |
| Nirman ResidencyNirman Group | P52100009602 | 22 Aug 2017 | 30 Sep 2018 | 30 Sep 2018 | Promised date passed | 0 |
| Shubhshivam ResidencyM/S Adhiraj Associats | P52100008241 | 18 Aug 2017 | 31 Dec 2018 | 31 Dec 2019 | Extended 12 mo | 0 |
| Project At S.no 168 H No 7/A/B/C/28b/30/8/29/3f/3ySungrace Infra Projects | P52100007062 | 17 Aug 2017 | 30 Dec 2024 | 30 Dec 2024 | Promised date passed | 0 |
| Sai VrundavanPrabhakar Baburao Thorat | P52100007037 | 17 Aug 2017 | 31 Mar 2019 | 31 Mar 2019 | Promised date passed | 0 |
| Laxmi Pujan ResidencyLaxmi Pujan Developers | P52100006418 | 14 Aug 2017 | 31 Dec 2018 | 7 Jan 2020 | Extended 13 mo | 0 |
Other localities in Ambegaon
Most active promoters
By projects registered here, as named on MahaRERA.
- Sungrace Infra Projects4 projects
- Supreme Infra4 projects
- Adhya Properties1 project
- Crystal Developers1 project
- Laxmideep Infrastructures1 project
- Laxmi Pujan Developers1 project
- M/S Adhiraj Associats1 project
- Nirman Group1 project
- Nupur Landmarks Private Limited1 project
- Prabhakar Baburao Thorat1 project
Data through14 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology