Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 63% of its units are booked.

Lonavala (M Cl), Pune 410405 · Property rates in Lonavala (M Cl) · by Iraah Lifespaces LLP

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales63% booked5 of 8 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 24 Feb 2023, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

6 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100049733
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210004973324 Feb 202331 Dec 202630 Apr 2027Iraah Lifespaces LLPProject page
Documents80

1 document held by Deedo, 79 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardIraah Lifespaces LLP PAN.pdf · uploaded 10 Jan 2023Source

Legal

  • Legal Title reportTitle Report-1.pdf · uploaded 10 Jan 2023Source
  • Declaration Form BForm B Affidavit.pdf · uploaded 10 Jan 2023Source

Migrated

  • 1 PAN CardIraah Lifespaces LLP PAN.pdf · uploaded 10 Jan 2023Source
  • 1 Copy of the legal title reportTitle Report-1.pdf · uploaded 10 Jan 2023Source
  • 1 a Details of encumbrances concerned to Finance1A 1B.pdf · uploaded 10 Jan 2023Source
  • 1 b Details of encumbrances concerned to Legal1A 1B.pdf · uploaded 10 Jan 2023Source
Show all 80 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentSanctioned Plan.pdf · uploaded 10 Jan 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentSanctioned Plan Section.pdf · uploaded 10 Jan 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 10 Jan 2023Source
  • 1 Declaration in FORM BForm B Affidavit.pdf · uploaded 10 Jan 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architects certficate.pdf · uploaded 10 Jan 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Eng.pdf · uploaded 10 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A.pdf · uploaded 10 Jan 2023Source
  • 1 CERSAI detailsCERSAI.pdf · uploaded 10 Jan 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA.pdf · uploaded 10 Jan 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 10 Jan 2023Source
  • 1 Proforma of Agreement for saleAFS Sanaya Iraah Lonavala as per rera.pdf · uploaded 10 Jan 2023Source
  • 1 Proforma of Allotment letterDraft Allotment Letter.pdf · uploaded 10 Jan 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration bank details.pdf · uploaded 10 Jan 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation t Allotment.pdf · uploaded 10 Jan 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation to AFS.pdf · uploaded 10 Jan 2023Source
  • 1 Copy of Layout Approval (in case of layout)1 Building Plan Approval _ NA Order for plotted development (4).pdf · uploaded 24 Jan 2023Source
  • 1 Other – TechnicalForm D lonavala.pdf · uploaded 24 Jan 2023Source
  • 1 Declaration about Commencement CertificateForm D CC.pdf · uploaded 22 Feb 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate 310323.pdf · uploaded 10 Oct 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate 300623.pdf · uploaded 10 Oct 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng 3103 Stellar 8.pdf · uploaded 10 Oct 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng 3006 Stellar 8.pdf · uploaded 10 Oct 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA 3103 Stellar 8.pdf · uploaded 10 Oct 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA 3006 Stellar 8.pdf · uploaded 10 Oct 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch 311223.pdf · uploaded 15 Oct 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch 310324.pdf · uploaded 15 Oct 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch 300624.pdf · uploaded 15 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Cerificate 300923.pdf · uploaded 15 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA 300923.pdf · uploaded 15 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA 311223.pdf · uploaded 15 Oct 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA 310324.pdf · uploaded 15 Oct 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA 300624.pdf · uploaded 15 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng 310324.pdf · uploaded 15 Oct 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng Stellar 8 311223.pdf · uploaded 15 Oct 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng Stellar 8 311223.pdf · uploaded 15 Oct 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng Stellar 8 300923.pdf · uploaded 15 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng 300624.pdf · uploaded 15 Oct 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Certiicate.pdf · uploaded 29 Nov 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA certificate Q7.pdf · uploaded 29 Nov 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng certificate.pdf · uploaded 29 Nov 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 2023-24.pdf · uploaded 15 Jan 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 2023-24.pdf · uploaded 15 Jan 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) (2).pdf · uploaded 28 Jan 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5.pdf · uploaded 30 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA stellar.pdf · uploaded 17 Jun 2025Source
  • Form 3CA 2025.pdf · uploaded 26 Jun 2025Source
  • Form 1Arch Certificate March 2025.pdf · uploaded 26 Jun 2025Source
  • Form 2Eng March 2025.pdf · uploaded 26 Jun 2025Source
  • Disclosure of Sold and Booked InventoryDeclaration Sold - Unsold.pdf · uploaded 26 Jun 2025Source
  • Form 1Arch Certificate December 2024.pdf · uploaded 26 Jun 2025Source
  • Form 2Eng December 2024.pdf · uploaded 26 Jun 2025Source
  • Form 3CA December 2024.pdf · uploaded 26 Jun 2025Source
  • Disclosure of Sold and Booked InventoryDeclaration Sold - Unsold.pdf · uploaded 26 Jun 2025Source
  • Form 2A (FY 2023-2024)1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24) (2).pdf · uploaded 26 Jun 2025Source
  • Form 5 (FY 2023-2024)1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24) (1).pdf · uploaded 26 Jun 2025Source

Technical

  • DocumentSanctioned Plan.pdf · uploaded 10 Jan 2023Source
  • DocumentSanctioned Plan Section.pdf · uploaded 10 Jan 2023Source
  • Document1 Building Plan Approval _ NA Order for plotted development (4).pdf · uploaded 24 Jan 2023Source
  • Other – TechnicalForm D lonavala.pdf · uploaded 24 Jan 2023Source

Technical (Architect)

  • DocumentArchitect Certificate 300623.pdf · uploaded 10 Oct 2023Source
  • DocumentArchitect Cerificate 300923.pdf · uploaded 15 Oct 2024Source
  • DocumentArch 311223.pdf · uploaded 15 Oct 2024Source
  • DocumentArch 310324.pdf · uploaded 15 Oct 2024Source
  • DocumentArch 300624.pdf · uploaded 15 Oct 2024Source
  • DocumentArch Certiicate.pdf · uploaded 29 Nov 2024Source

Technical (Engineer)

  • DocumentEng 3006 Stellar 8.pdf · uploaded 10 Oct 2023Source
  • DocumentEng 310324.pdf · uploaded 15 Oct 2024Source
  • DocumentEng 300624.pdf · uploaded 15 Oct 2024Source
  • DocumentEng Stellar 8 300923.pdf · uploaded 15 Oct 2024Source
  • DocumentEng Stellar 8 311223.pdf · uploaded 15 Oct 2024Source
  • DocumentEng Stellar 8 311223.pdf · uploaded 15 Oct 2024Source
  • DocumentEng certificate.pdf · uploaded 29 Nov 2024Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 49/2/A/1/2

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
Villa, Bungalow8 units in all
Address
49/2/A/1/2, Gold Valley, TungarliPIN 410405
Village
Lonavala (M Cl), Mawal taluka
Land area for this project
3,990 sq m (42,948 sq ft)
Permissible built-up area
1,496 sq m (16,105 sq ft)
Sanctioned built-up area
1,462 sq m (15,739 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
171
Developed in phases
Yes

Survey, CTS, gat or plot numbers

49/2/A/1/2

Land as published on MahaRERA's project page

49/2/A/1/2

Boundaries

North
Survey No 49-2 Part
South
Dp Road 12 Mtr
East
Dp Road And Survey No 49 -1a -1b
West
Survey No 49-2 Part And Survey No 50

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking8 units

5 of 8 units booked (63%), as the promoter reported to MahaRERA

Villa · 2 unitsBungalow · 6 units
BuildingTypeCarpet areaUnitsBooked
A-1Villa164.44 sq m · 1,770 sq ft10
A-4Bungalow164.44 sq m · 1,770 sq ft11
A-5Villa164.44 sq m · 1,770 sq ft10
A-6Bungalow164.44 sq m · 1,770 sq ft11
B-2 / B-3Bungalow164.44 sq m · 1,770 sq ft22
C-7 / C-8Bungalow164.44 sq m · 1,770 sq ft21

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Architectrajesh chouhan—
EngineerPrashant Prabhkar Shinde—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Lonavala (M Cl)

All 40 projects in Lonavala (M Cl) · Compare Stellar 8 with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology