Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 0% of its units are booked.

Kiwale, Pune 412101 · Property rates in Kiwale · by Mrs Druti Pravin Totlani

DeliveryExtended 4 moPromised Dec 2026 · now due Apr 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 72 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2027

  • This projectRegistered 17 Feb 2026, completion promised 31 Dec 2026, revised to 30 Apr 2027.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

6 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100081097
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210008109717 Feb 202631 Dec 202630 Apr 2027Mrs Druti Pravin TotlaniProject page
Documents48

1 document held by Deedo, 47 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan Card.pdf · uploaded 28 Nov 2024Source

Legal

  • Legal Title reportLegal title Report Latest.pdf · uploaded 28 Nov 2024Source
  • Declaration Form BAffadavit cum Declaration.pdf · uploaded 28 Nov 2024Source
  • Other – LegalScan20240827202604_compressed-1-12.pdf · uploaded 29 Nov 2024Source
  • Other – LegalScan20240827202604_compressed-13-24.pdf · uploaded 29 Nov 2024Source

Migrated

  • 1 PAN CardPan Card.pdf · uploaded 28 Nov 2024Source
  • 1 Copy of the legal title reportLegal title Report Latest.pdf · uploaded 28 Nov 2024Source
Show all 48 documentsShow fewer documents

Migrated

  • 1 a Details of encumbrances concerned to FinanceSelf Declaration regarding Encumbrances.pdf · uploaded 28 Nov 2024Source
  • 1 Copy of Layout Approval (in case of layout)ddrrr001 - converted.pdf · uploaded 28 Nov 2024Source
  • 1 Declaration in FORM BAffadavit cum Declaration.pdf · uploaded 28 Nov 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentCommecment Certificate.pdf · uploaded 28 Nov 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentddrrr002 - converted.pdf · uploaded 28 Nov 2024Source
  • 1 CERSAI detailsCERSAI Declaration (2).pdf · uploaded 28 Nov 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Format1 Bank Declaration.pdf · uploaded 28 Nov 2024Source
  • 1 Deviation Report with respect to Allotment letterDeviation report.pdf · uploaded 28 Nov 2024Source
  • 1 b Details of encumbrances concerned to LegalSelf Declaration regarding Encumbrances.pdf · uploaded 28 Nov 2024Source
  • 1 Other – TechnicalDeclaration cum undertaking (1).pdf · uploaded 28 Nov 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation report Agreement to Sale.pdf · uploaded 28 Nov 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A Disclosure of Interest.pdf · uploaded 28 Nov 2024Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B HDFC.pdf · uploaded 28 Nov 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDisclosure of secured and unsecured finance.pdf · uploaded 28 Nov 2024Source
  • 1 Proforma of Allotment letterModel form of AL-Mysha.pdf · uploaded 29 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Archt Certi (1).pdf · uploaded 29 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Adobe Scan 3 Apr 2025.pdf · uploaded 29 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Vritti.pdf · uploaded 29 Nov 2024Source
  • 1 Other – LegalScan20240827202604_compressed-1-12.pdf · uploaded 29 Nov 2024Source
  • 2 Other – LegalScan20240827202604_compressed-13-24.pdf · uploaded 29 Nov 2024Source
  • 1 Declaration about Commencement CertificateFormat D-Mysha.pdf · uploaded 29 Nov 2024Source
  • 1 Proforma of Agreement for saleAFS-Mysha.pdf · uploaded 29 Nov 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentYAHOOM_1.pdf · uploaded 2 Apr 2025Source
  • 3 Commencement Certificates / NA Order for plotted development20251202025348_00001.pdf · uploaded 3 Dec 2025Source
  • 3 Building Plan Approval / NA Order for plotted developmentddrrr004 - converted.pdf · uploaded 3 Dec 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentddrrr003 - converted.pdf · uploaded 3 Dec 2025Source
  • Withdrawal Update Form 1Form 1 (3).pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2form 2 (5).pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3form 3 (10).pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 1form 1.pdf · uploaded 17 Jul 2026Source
  • Withdrawal Update Form 2form2.pdf · uploaded 17 Jul 2026Source
  • Withdrawal Update Form 3form 3.pdf · uploaded 17 Jul 2026Source
  • Form 5 (FY 2025-2026)FORM 5 (1).pdf · uploaded 25 Sep 2026Source

Technical

  • Documentddrrr001 - converted.pdf · uploaded 28 Nov 2024Source
  • Documentddrrr002 - converted.pdf · uploaded 28 Nov 2024Source
  • Other – TechnicalDeclaration cum undertaking (1).pdf · uploaded 28 Nov 2024Source
  • Documentddrrr003 - converted.pdf · uploaded 3 Dec 2025Source
  • Documentddrrr004 - converted.pdf · uploaded 3 Dec 2025Source

Technical (Architect)

  • Documentform 1.pdf · uploaded 17 Jul 2026Source

Technical (Engineer)

  • Documentform2.pdf · uploaded 17 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 2, 3

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK72 units in all
Address
Sr No 35/5B/1, 2, 3, 4, 5 Kiwale, Dehuroad, Dehuroad, DehuroadPIN 412101
Village
Kiwale, Haveli taluka
Land area for this project
4,200 sq m (45,208 sq ft)
Permissible built-up area
3,902 sq m (42,001 sq ft)
Sanctioned built-up area
3,902 sq m (42,001 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
76
Developed in phases
Yes

Survey, CTS, gat or plot numbers

2345 KiwaleSr No 35/5B/1

Land as published on MahaRERA's project page

Sr No 35/5B/1, 2, 3, 4, 5 Kiwale, Dehuroad

Boundaries

North
By Sr no 35 Hissa no 5
South
By Sr no 36
East
By Sr no 35 Hissa no 5B 5
West
By Sr no 35 Hissa no 5B 3

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking72 units

0 of 72 units booked (0%), as the promoter reported to MahaRERA

1BHK · 36 units2BHK · 36 units
BuildingTypeCarpet areaUnitsBooked
A Wing - A Building1BHK42.01 sq m · 452 sq ft120
A Wing - Building B2BHK55.03 sq m · 592 sq ft120
B Wing - A Building1BHK42.01 sq m · 452 sq ft120
B Wing - B Building1BHK42.62 sq m · 459 sq ft60
B Wing - B Building2BHK55.03 sq m · 592 sq ft60
C Wing - B Building1BHK42.62 sq m · 459 sq ft60
C Wing - B Building2BHK55.03 sq m · 592 sq ft60
D Wing - B Building2BHK55.03 sq m · 592 sq ft120

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr Aashoke Pawar—
Chartered accountantM s Azam Mulani and Associates—
Chartered accountantRinkesh Gupta—
EngineerAshok Waghmare—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Kiwale

All 123 projects in Kiwale · Compare Mysha with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology