Residential / Group Housing · 1 building · 18 unitsRERA P52100052468

Blue Bell

Deedo IDDP-PUN-KCDR

Its promised completion date, Mar 2026, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 17% of its units are booked.

Kiwale, Pune 412101 · Property rates in Kiwale · by M G Builders & Developers

Delivery8 mo past duePromised Mar 2026 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales17% booked3 of 18 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Mar 2026, has passed and MahaRERA does not show it completed

  • This projectRegistered 8 Sep 2023, completion promised 31 Mar 2026, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100052468
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000524688 Sep 202331 Mar 202631 Mar 2026M G Builders & DevelopersProject page
Documents135

1 document held by Deedo, 134 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN FIRM.pdf · uploaded 12 Jun 2023Source

Legal

  • Legal Title report1 Copy of the legal title report_11zon.pdf · uploaded 12 Jun 2023Source
  • Declaration Form BFORM B.pdf · uploaded 12 Jun 2023Source
  • Declaration Form BProperty Card.pdf · uploaded 2 May 2026Source

Migrated

  • 1 PAN CardPAN FIRM.pdf · uploaded 12 Jun 2023Source
  • 1 Copy of the legal title report1 Copy of the legal title report_11zon.pdf · uploaded 12 Jun 2023Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 12 Jun 2023Source
Show all 135 documentsShow fewer documents

Migrated

  • 1 Declaration in FORM BFORM B.pdf · uploaded 12 Jun 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 12 Jun 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 12 Jun 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTEREST IN OTHER REAL ESTATE ORGNAZETIONS.pdf · uploaded 12 Jun 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Final_compressed.pdf · uploaded 3 Jul 2023Source
  • 1 Proforma of Agreement for saleAFS -FINAL.pdf · uploaded 3 Jul 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation in AL.pdf · uploaded 3 Jul 2023Source
  • 1 Deviation Report with respect to model copy of AgreementNo Deviation in AFS.pdf · uploaded 3 Jul 2023Source
  • 1 a Details of encumbrances concerned to FinanceFINANCIAL AND LEGAL.pdf · uploaded 4 Jul 2023Source
  • 1 b Details of encumbrances concerned to LegalFINANCIAL AND LEGAL.pdf · uploaded 4 Jul 2023Source
  • 2 a Details of encumbrances concerned to Financeencumbrances concerned to Finance final.pdf · uploaded 15 Jul 2023Source
  • 2 b Details of encumbrances concerned to Legalencumbrances concerned to Finance final.pdf · uploaded 15 Jul 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentLAYOUT.pdf · uploaded 15 Jul 2023Source
  • 1 Declaration about Commencement CertificateDeclaration Commencement Certificate.pdf · uploaded 17 Jul 2023Source
  • 1 Proforma of Allotment letterAL-FINAL-1.pdf · uploaded 17 Jul 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDECLARATION ABOUT SEPRATE BANK ACCOUNT.pdf · uploaded 21 Jul 2023Source
  • 1 CERSAI detailsCERSAI FOR MG.pdf · uploaded 24 Jul 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentFINAL COMMENCEMENT CERTIFIACTE.pdf · uploaded 22 Aug 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentSCATION COPY.pdf · uploaded 12 Mar 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 12 Mar 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -01.pdf · uploaded 12 Mar 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM- 02 NEW.pdf · uploaded 12 Mar 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -03_compressed.pdf · uploaded 12 Mar 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)form -01.PDF · uploaded 9 Oct 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form - 01.PDF · uploaded 9 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_compressed.pdf · uploaded 9 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 9 Oct 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 02.pdf · uploaded 9 Oct 2024Source
  • 3 Disclosure of sold/ booked inventorySold Unsold Inventory Dec -23.pdf · uploaded 9 Oct 2024Source
  • 4 Disclosure of sold/ booked inventorySOLD UNSOLD NEW MAR -24.pdf · uploaded 9 Oct 2024Source
  • 5 Disclosure of sold/ booked inventorySOLD UNSOLD NEW JUNE -24.pdf · uploaded 9 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)M G builders and developers .pdf · uploaded 15 Oct 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 17 Oct 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 03.pdf · uploaded 19 Oct 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 19 Oct 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 19 Oct 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM2A.pdf · uploaded 20 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)M G Builders form 1.PDF · uploaded 29 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -03 DEC -24.pdf · uploaded 29 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 29 Jan 2025Source
  • 1 Disclosure of sold/ booked inventorySOLD BOOKED INVENTORY.pdf · uploaded 30 Jan 2025Source
  • 2 Disclosure of sold/ booked inventorySOLD BOOKED INVENTORY.pdf · uploaded 30 Jan 2025Source
  • Form 3FORM -03.pdf · uploaded 28 Jul 2025Source
  • Form 1FORM -01.pdf · uploaded 28 Jul 2025Source
  • Form 2FORM- 02 NEW.pdf · uploaded 28 Jul 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventory Dec -23.pdf · uploaded 28 Jul 2025Source
  • Form 1form -01.PDF · uploaded 28 Jul 2025Source
  • Form 2FORM 2.pdf · uploaded 28 Jul 2025Source
  • Form 3FORM 3_compressed.pdf · uploaded 28 Jul 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD NEW MAR -24.pdf · uploaded 28 Jul 2025Source
  • Form 1Form - 01.PDF · uploaded 28 Jul 2025Source
  • Form 2FORM 02.pdf · uploaded 28 Jul 2025Source
  • Form 3Form 03.pdf · uploaded 28 Jul 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD NEW JUNE -24.pdf · uploaded 28 Jul 2025Source
  • Form 1Form 1.pdf · uploaded 28 Jul 2025Source
  • Form 2form 2.pdf · uploaded 28 Jul 2025Source
  • Form 3Form 3.pdf · uploaded 28 Jul 2025Source
  • Disclosure of Sold and Booked InventorySOLD BOOKED INVENTORY.pdf · uploaded 28 Jul 2025Source
  • Form 1M G Builders form 1.PDF · uploaded 28 Jul 2025Source
  • Form 2FORM 2.pdf · uploaded 28 Jul 2025Source
  • Form 3FORM -03 DEC -24.pdf · uploaded 28 Jul 2025Source
  • Disclosure of Sold and Booked InventorySOLD BOOKED INVENTORY.pdf · uploaded 28 Jul 2025Source
  • Form 1Form 1.pdf · uploaded 23 Feb 2026Source
  • Form 2Form 2.pdf · uploaded 23 Feb 2026Source
  • Form 3FORM 3.pdf · uploaded 23 Feb 2026Source
  • Disclosure of Sold and Booked Inventorysold inventory.pdf · uploaded 23 Feb 2026Source
  • Form 1Form 1.PDF · uploaded 23 Feb 2026Source
  • Form 2FORM 2.pdf · uploaded 23 Feb 2026Source
  • Form 3FORM 3.pdf · uploaded 23 Feb 2026Source
  • Disclosure of Sold and Booked Inventorysold inventory.pdf · uploaded 23 Feb 2026Source
  • Form 1M G Builders Form 1.PDF · uploaded 23 Feb 2026Source
  • Form 2Form 2.pdf · uploaded 23 Feb 2026Source
  • Form 3FORM 3.pdf · uploaded 23 Feb 2026Source
  • Disclosure of Sold and Booked Inventorysold inventory.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 1FORM -01.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 1form -01.PDF · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 1M G Builders form 1.PDF · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 1M G Builders Form 1.PDF · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 1Form 1.PDF · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 2FINAL Form 2.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 2FORM- 02 NEW.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 2FORM 2 (A).pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 2FINAL Form 2.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 3FORM -03_compressed.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 3FORM -03.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 3FORM 3_compressed (1).pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 3FORM -03 DEC -24.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 3FORM 3.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 3FORM 3.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 3FORM 3.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 3FORM 3.pdf · uploaded 23 Feb 2026Source
  • Withdrawal Update Form 1FINAL FORM 1.PDF · uploaded 12 Aug 2026Source
  • Withdrawal Update Form 2FINAL FORM 2.pdf · uploaded 12 Aug 2026Source
  • Withdrawal Update Form 3FINAL FORM 3.pdf · uploaded 12 Aug 2026Source
  • Form 1form 1.pdf · uploaded 8 Sep 2026Source
  • Form 2form 2.pdf · uploaded 8 Sep 2026Source
  • Form 3form 3.pdf · uploaded 8 Sep 2026Source
  • Disclosure of Sold and Booked Inventorysold.pdf · uploaded 8 Sep 2026Source
  • Form 2A (FY 2023-2024)FORM 2A 31-03-2024.pdf · uploaded 8 Sep 2026Source
  • Form 2A (FY 2024-2025)FORM 2A 31-03-2025.pdf · uploaded 8 Sep 2026Source
  • Form 2A (FY 2025-2026)FORM 2A 31-3-2026.pdf · uploaded 8 Sep 2026Source
  • Form 5 (FY 2023-2024)FORM 5.pdf · uploaded 10 Sep 2026Source
  • Form 5 (FY 2024-2025)FORM 5 FY 2024-25.pdf · uploaded 10 Sep 2026Source
  • Form 5 (FY 2025-2026)FORM 5 FY 2025-26.pdf · uploaded 11 Sep 2026Source

Technical

  • DocumentLAYOUT.pdf · uploaded 12 Jun 2023Source
  • DocumentLAYOUT.pdf · uploaded 15 Jul 2023Source
  • DocumentSCATION COPY.pdf · uploaded 12 Mar 2024Source

Technical (Architect)

  • Documentform -01.PDF · uploaded 9 Oct 2024Source
  • DocumentForm - 01.PDF · uploaded 9 Oct 2024Source
  • DocumentForm 1.pdf · uploaded 17 Oct 2024Source
  • DocumentM G Builders form 1.PDF · uploaded 29 Jan 2025Source
  • DocumentFINAL FORM 1.PDF · uploaded 11 Aug 2026Source

Technical (Engineer)

  • DocumentFORM 2.pdf · uploaded 9 Oct 2024Source
  • DocumentFORM 02.pdf · uploaded 9 Oct 2024Source
  • Documentform 2.pdf · uploaded 19 Oct 2024Source
  • DocumentFORM 2.pdf · uploaded 29 Jan 2025Source
  • DocumentFINAL FORM 2.pdf · uploaded 11 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 41/1B/2/19(P) CTS 1679

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK18 units in all
Address
41/1b/2/19(P) Cts 1679, Dehuroad, KiwalePIN 412101
Village
Kiwale, Haveli taluka
Land area for this project
441 sq m (4,751 sq ft)
Permissible built-up area
1,742 sq m (18,750 sq ft)
Sanctioned built-up area
1,742 sq m (18,750 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
203
Developed in phases
No

Survey, CTS, gat or plot numbers

41/1B/2/19(P) CTS 1679

Land as published on MahaRERA's project page

41/1B/2/19(P) CTS 1679

Boundaries

North
By Part Of Sry No-41-2 Cts No-1665 And 1657
South
By 30 Ft Wide Colony Road
East
By Plot No-20 Cts No-1678 Out Of Pendse Colony
West
By Plot No -18 Cts No-1680 Out Of Pendse Colony

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking18 units

3 of 18 units booked (17%), as the promoter reported to MahaRERA

2BHK · 12 units3BHK · 6 units
TypeCarpet areaUnitsBooked
2BHK55.83 sq m · 601 sq ft122
3BHK109.51 sq m · 1,179 sq ft61

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAmol Kulkarni—
Chartered accountantGanesh D Devkar—
EngineerAvinash H Hole—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Kiwale

All 123 projects in Kiwale · Compare Blue Bell with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology