Deedo IDDL-PUN-KHED7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects331
Registrations349some projects hold several
Completion still due125169 past their date
Median extension4 months51% of registrations extended
Regulatory cases8on 9 projects
7 in 10 registrations run late here
349 MahaRERA registrations in Khed and the places within it
34 not yet due91 extended, not yet due169 past even the latest date55 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Khed
331 projects registered with MahaRERA in this taluka and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Meena Residency | No date on record | — | — |
| Navkar Park | No date on record | — | — |
| Nikunj Heights | No date on record | — | — |
| Pavani Park | No date on record | — | — |
| Prestige Park Phase-II | No date on record | — | — |
| Prime City | No date on record | — | — |
| Purva Heights | No date on record | — | — |
| Radhesyam Residency | No date on record | — | — |
| Riya Regency | No date on record | — | — |
| Saarvi Nakshatra | No date on record | — | — |
| Sai Crown | No date on record | — | — |
| Sai Empire | No date on record | — | — |
| Sai Enclave | No date on record | — | — |
| Sai Siddhi Residency | No date on record | — | — |
| Samarth Platinum | No date on record | — | — |
| Sanjog Residency | No date on record | — | — |
| Sanvi Heights - E, F, G, H Wings | No date on record | — | — |
| Sarangi Residency | No date on record | — | — |
| Savali Residancy | No date on record | — | — |
| Shiv Nisarg | No date on record | — | — |
| Shivsagar Residency | No date on record | — | — |
| Shreekrushna-Leela Park | No date on record | — | — |
| Shruti Pushp | No date on record | — | — |
| Shubh Vastu | No date on record | — | — |
| Siddhivinayak Park | No date on record | — | — |
Nearby: other talukas in Pune
Most active promoters
- Jagrutsara Structures Llp21 projects
- Sara Builders & Developers7 projects
- Anand Deoram Tambe4 projects
- Naiknavare Housing Developments Pvt. Ltd4 projects
- Shivam Developers Pvt. Ltd4 projects
- Shree Sai Associates4 projects
- Intercontinental Infrastructure Limited3 projects
- Mahendra Sayaji Pacharane3 projects
- Mangesh Vasant Gundal3 projects
- Maple Estates3 projects
Khed, in questions
How many projects in Khed run late?
7 in 10 MahaRERA registrations (260 of 349): their completion date was extended or has passed, data through 6 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Khed by Deedo. Medians on fewer than 3 deeds are not shown.
Data through6 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology