RERA projects in Karandoli

1 project under 1 MahaRERA registration, registered 2025–2025. 100% have a completion date extended beyond the one promised.

Locality
1RERA projects
1Registrations
1Completion still due0 past their completion date
4 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20251

Projects in Karandoli

1 project registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Mehul Bhupendra Shah And Sadhna Bhupendra Shahmehul bhupendra shahPP126000250145613 Nov 202531 Aug 203231 Dec 2032Extended 4 mo0

Other localities in Mawal

Most active promoters

By projects registered here, as named on MahaRERA.

  1. mehul bhupendra shah1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology