Skip to content
Residential / Group Housing · 1 building · 233 unitsRERA PR1260002502134

Kumar Primeview G2

Deedo IDDP-PUN-3MHY

Completion was pushed back 4 months, to Apr 2031; no MahaRERA orders on record; 0% of its units are booked.

Hadapsar, Pune 411028 · Property rates in Hadapsar · by Kumar Properties And Promoters Private Limited · 100% of its projects kept the RERA date

DeliveryExtended 4 moPromised Dec 2030 · now due Apr 2031RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 233 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2031

  • This projectRegistered 21 Jan 2026, completion promised 31 Dec 2030, revised to 30 Apr 2031.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPR1260002502134
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PR126000250213421 Jan 202631 Dec 203030 Apr 2031Kumar Properties & Promoters Private LimitedProject page
Documents24

1 document held by Deedo, 23 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardKPPPL-PAN CARD.pdf · uploaded 7 Dec 2025Source

Legal

  • Declaration Form BTilte Report Kumar Primeview Bldg No G2.pdf · uploaded 24 Dec 2025Source
  • Declaration Form BAffidavit cum Declaration-From B Bldg No G2.PDF · uploaded 24 Dec 2025Source
  • Declaration Form BSatbara.pdf · uploaded 24 Dec 2025Source

Migrated

  • Withdrawal Update Form 1KPPPL KPV G2 Form 1.PDF · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 2G2 PrimeView Engineering Certificate.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 3KPPPL KPV G2 Form 3.pdf · uploaded 24 Apr 2026Source
Show all 24 documentsShow fewer documents

Migrated

  • Withdrawal Update Form 1KPPPL Form 1 KPV G2.pdf · uploaded 14 Jul 2026Source
  • Withdrawal Update Form 2G2 Primeview Engineers Certificate.pdf · uploaded 14 Jul 2026Source
  • Withdrawal Update Form 3KPPPL Form 3 KPV G2.pdf · uploaded 14 Jul 2026Source
  • Form 5 (FY 2025-2026)KPPPL - Kumar Primeview G2.pdf · uploaded 7 Oct 2026Source

Technical

  • OthersCC VERIFICATION - G2 - G3.pdf · uploaded 22 Dec 2025Source
  • DocumentDeclaration cum Undertaking G2 Bldg.pdf · uploaded 24 Dec 2025Source
  • DocumentG2-21_compressed.pdf · uploaded 24 Dec 2025Source
  • DocumentG2-22_compressed.pdf · uploaded 24 Dec 2025Source
  • DocumentG2-23.pdf · uploaded 24 Dec 2025Source
  • DocumentG2-24.pdf · uploaded 24 Dec 2025Source
  • DocumentG1G2G3 BASEMENT 4 compressed.pdf · uploaded 24 Dec 2025Source
  • DocumentG1G2G3 Gr parking 5 compressed.pdf · uploaded 24 Dec 2025Source
  • DocumentLayout G2.pdf · uploaded 24 Dec 2025Source
  • OthersRERA PARKING G2 BUILDING CERTIFICATE.pdf · uploaded 12 Jan 2026Source

Technical (Architect)

  • DocumentForm 1 KPPPL KPV G2.pdf · uploaded 10 Oct 2026Source

Technical (Engineer)

  • DocumentG2 Primeview Engineers Certificate.pdf · uploaded 10 Oct 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 55/1/2/3

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
—233 units in all
Address
Hadapsar, HadapsarPIN 411028
Village
Hadapsar, Haveli taluka
Land area for this project
7,984 sq m (85,940 sq ft)
Approved layout area
86,600 sq m (9,32,154 sq ft)
Permissible built-up area
20,870 sq m (2,24,638 sq ft)
Sanctioned built-up area
20,870 sq m (2,24,638 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
109
Developed in phases
No

Survey, CTS, gat or plot numbers

55/1/2/3

Land as published on MahaRERA's project page

55/1/2/3

Boundaries

North
By Building No G1
South
By Building No G3
East
By survey no 56
West
By podium out of the said Project

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking233 units

233 units registered

— · 233 units
TypeCarpet areaUnits
——233

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSamir Valimbe—
Chartered accountantSupriya Abhijeet Mundada—
EngineerAbhijeet Shekar—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology