Kumar Primeview G2
Deedo IDDP-PUN-3MHYCompletion was pushed back 4 months, to Apr 2031; no MahaRERA orders on record; 0% of its units are booked.
Hadapsar, Pune 411028 · Property rates in Hadapsar · by Kumar Properties And Promoters Private Limited · 100% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2031
- This projectRegistered 21 Jan 2026, completion promised 31 Dec 2030, revised to 30 Apr 2031.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPR1260002502134
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PR1260002502134 | 21 Jan 2026 | 31 Dec 2030 | 30 Apr 2031 | Kumar Properties & Promoters Private Limited | Project page |
Documents24
1 document held by Deedo, 23 filings listed on MahaRERA's project page
Finance
- PAN CardKPPPL-PAN CARD.pdf · uploaded 7 Dec 2025Source
Legal
Show all 24 documentsShow fewer documents
Migrated
- Withdrawal Update Form 1KPPPL Form 1 KPV G2.pdf · uploaded 14 Jul 2026Source
- Withdrawal Update Form 2G2 Primeview Engineers Certificate.pdf · uploaded 14 Jul 2026Source
- Withdrawal Update Form 3KPPPL Form 3 KPV G2.pdf · uploaded 14 Jul 2026Source
- Form 5 (FY 2025-2026)KPPPL - Kumar Primeview G2.pdf · uploaded 7 Oct 2026Source
Technical
- OthersCC VERIFICATION - G2 - G3.pdf · uploaded 22 Dec 2025Source
- DocumentDeclaration cum Undertaking G2 Bldg.pdf · uploaded 24 Dec 2025Source
- DocumentG2-21_compressed.pdf · uploaded 24 Dec 2025Source
- DocumentG2-22_compressed.pdf · uploaded 24 Dec 2025Source
- DocumentG2-23.pdf · uploaded 24 Dec 2025Source
- DocumentG2-24.pdf · uploaded 24 Dec 2025Source
- DocumentG1G2G3 BASEMENT 4 compressed.pdf · uploaded 24 Dec 2025Source
- DocumentG1G2G3 Gr parking 5 compressed.pdf · uploaded 24 Dec 2025Source
- DocumentLayout G2.pdf · uploaded 24 Dec 2025Source
- OthersRERA PARKING G2 BUILDING CERTIFICATE.pdf · uploaded 12 Jan 2026Source
Technical (Architect)
- DocumentForm 1 KPPPL KPV G2.pdf · uploaded 10 Oct 2026Source
Technical (Engineer)
- DocumentG2 Primeview Engineers Certificate.pdf · uploaded 10 Oct 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 55/1/2/3
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —233 units in all
- Address
- Hadapsar, HadapsarPIN 411028
- Village
- Hadapsar, Haveli taluka
- Location
- 18.47781, 73.93136
- Land area for this project
- 7,984 sq m (85,940 sq ft)
- Approved layout area
- 86,600 sq m (9,32,154 sq ft)
- Permissible built-up area
- 20,870 sq m (2,24,638 sq ft)
- Sanctioned built-up area
- 20,870 sq m (2,24,638 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 109
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
55/1/2/3
Boundaries
- North
- By Building No G1
- South
- By Building No G3
- East
- By survey no 56
- West
- By podium out of the said Project
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking233 units
233 units registered
| Type | Carpet area | Units |
|---|---|---|
| — | — | 233 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Samir Valimbe | — |
| Chartered accountant | Supriya Abhijeet Mundada | — |
| Engineer | Abhijeet Shekar | — |