Of 7 registrations whose promised date has arrived, 7 kept it (100%).

Projects1616 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record114registered first-sale deeds matched so far
Regulatory cases3no insolvency

Delivery record

7 of 16 registrations with dates moved or missed their RERA date · months late against the original promise

16 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Kumar Palmcrest A4 BuildingP52100022295PisoliCertificate Signed28 Aug 202328 Aug 2023On date
Kumar Pebble Park Joy 3 - C3P52100026151HadapsarCertificate Signed28 Feb 202628 Feb 2026On date
Kumar PiccadillyP52100029950WakadCertificate Signed31 May 202531 May 2025On date
Kumar Primrose C BuildingP52100030114Pune (Cb)Completed31 Dec 202231 Dec 2022On date
Kumar Pebble Park Khushi 3 - D3P52100031349HadapsarCertificate Signed31 Jul 202531 Jul 2025On date
Kumar Palmcrest A5P52100033817PisoliCompleted31 Dec 202531 Dec 2025On date
Kumar PrismP52100034109MundhawaCertificate Signed31 Dec 202431 Dec 2024On date
Kumar PalmnestP52100045312PisoliCertificate Signed31 Dec 203030 Apr 2031+4 mo
Kumar Pebble Park Joy 1 - C1P52100048543HadapsarCertificate Signed31 Dec 202631 Dec 2026On date
Kumar Pebble Park Joy 2 - C2P52100048597HadapsarCertificate Signed31 Dec 202631 Dec 2026On date
Kumar Primeview E1P52100052845HadapsarCertificate Signed31 Dec 202830 Apr 2029+4 mo
Kumar Primeview E2P52100052915HadapsarCertificate Signed31 Dec 202830 Apr 2029+4 mo
Kumar Primeview E3P52100077087HadapsarCertificate Signed31 Mar 202931 Jul 2029+4 mo
Kumar Primeview G2PR1260002502134HadapsarCertificate Signed31 Dec 203030 Apr 2031+4 mo
Kumar Palmcrest A6P52100081089PisoliCertificate Signed31 Mar 202931 Jul 2029+4 mo
Kumar Primeview G3PR1260002502222HadapsarCertificate Signed31 Dec 203030 Apr 2031+4 mo
Show all 16 registrationsShow fewer

Kumar Properties And Promoters Private Limited, in questions

Does Kumar Properties And Promoters Private Limited finish projects on time?

Of 7 MahaRERA registrations whose promised completion date has arrived, 7 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Kumar Properties And Promoters Private Limited registered with MahaRERA?

16 projects under 16 MahaRERA registrations; 7 completed on MahaRERA.

Does Kumar Properties And Promoters Private Limited have MahaRERA regulatory cases?

3 regulatory cases name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology