14Projects14 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date5 of 5 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Kumar Palmcrest A4 BuildingP52100022295 | Pisoli | 2019 | Not reported | 28 Aug 2023 | — | On date |
| Kumar Pebble Park Joy 3 - C3P52100026151 | Haveli | 2020 | Not reported | 28 Feb 2026 | — | On date |
| Kumar Pebble Park Khushi 3 - D3P52100031349 | Hadapsar | 2021 | Not reported | 31 Jul 2025 | — | On date |
| Kumar Palmcrest A5P52100033817 | Pisoli | 2022 | Not reported | 31 Dec 2025 | — | On date |
| Kumar PrismP52100034109 | Mundhawa | 2022 | Not reported | 31 Dec 2024 | — | On date |
| Kumar PalmnestP52100045312 | Pisoli | 2022 | Not reported | 31 Dec 2030 | — | On date |
| Kumar Pebble Park Joy 1 - C1P52100048543 | Hadapsar | 2023 | Not reported | 31 Dec 2026 | — | On date |
| Kumar Pebble Park Joy 2 - C2P52100048597 | Hadapsar | 2023 | Not reported | 31 Dec 2026 | — | On date |
| Kumar Primeview E1P52100052845 | Hadapsar | 2023 | Not reported | 31 Dec 2028 | — | On date |
| Kumar Primeview E2P52100052915 | Hadapsar | 2023 | Not reported | 31 Dec 2028 | — | On date |
| Kumar Primeview E3P52100077087 | Hadapsar | 2024 | Not reported | 31 Mar 2029 | — | On date |
| Kumar Primeview G2PR1260002502134 | Hadapsar | 2026 | Not reported | 31 Dec 2030 | — | On date |
| Kumar Palmcrest A6P52100081089 | Pisoli | 2026 | Not reported | 31 Mar 2029 | — | On date |
| Kumar Primeview G3PR1260002502222 | Hadapsar | 2026 | Not reported | 31 Dec 2030 | — | On date |
Show all 14 registrationsShow fewer
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Show all 14 registrations
Track record notes
- 5 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 3 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology