Kumar Prism
Its promised completion date, Dec 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 70% of its units are booked.
Mundhawa, Pune 411036 · Promoter: Kumar Properties And Promoters Private Limited
Its promised completion date, Dec 2024, has passed and MahaRERA does not show it completed
- This projectRegistered 24 Mar 2022, completion promised 31 Dec 2024, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100034109
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100034109 | 24 Mar 2022 | 31 Dec 2024 | 31 Dec 2024 | Kumar Properties And Promoters Private Limited | Project page |
Documents54
1 document held by Deedo, 53 filings listed on MahaRERA's project page
Finance
- PAN CardKPPPL PAN.PDF · uploaded 14 Mar 2022Source
Legal
Show all 54 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted developmentSheet No 2.pdf · uploaded 16 Feb 2022Source
- 2 Building Plan Approval / NA Order for plotted developmentSheet No 3.pdf · uploaded 16 Feb 2022Source
- 3 Building Plan Approval / NA Order for plotted developmentSheet No 4.pdf · uploaded 16 Feb 2022Source
- 4 Building Plan Approval / NA Order for plotted developmentSheet No 5.pdf · uploaded 16 Feb 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 16 Feb 2022Source
- 1 Declaration about Commencement CertificateDeclaration Form D Commencement Certificate.pdf · uploaded 16 Feb 2022Source
- 1 Declaration in FORM BFORM B AFFIDAVIT KPPPL.pdf · uploaded 16 Feb 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM1 44 MUNDHWA RERA CERTIFICATE.pdf · uploaded 16 Feb 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Engineers Certificate Kumar Prism.pdf · uploaded 16 Feb 2022Source
- 1 CERSAI detailsCERSAI Search Report.pdf · uploaded 16 Feb 2022Source
- 2 Copy of the legal title reportRERA FORMAT Search and Title Report KPPPL.pdf · uploaded 26 Feb 2022Source
- 1 Proforma of Allotment letterAGREEMENT COPY-PRISM-Zodge Mundhwa Unit Agreement.pdf · uploaded 7 Mar 2022Source
- 1 PAN CardKPPPL PAN.PDF · uploaded 14 Mar 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CERTIFICATE.pdf · uploaded 14 Mar 2022Source
- 2 Proforma of Allotment letterALLOTMENT LETTER KUMAR PRISM.pdf · uploaded 14 Mar 2022Source
- 2 Copy of Layout Approval (in case of layout)Layout_compressed.pdf · uploaded 26 May 2022Source
- 5 Building Plan Approval / NA Order for plotted developmentBasement Floor Plan_compressed.pdf · uploaded 26 May 2022Source
- 6 Building Plan Approval / NA Order for plotted development1 to 3 Floor Plan_compressed.pdf · uploaded 26 May 2022Source
- 7 Building Plan Approval / NA Order for plotted developmentTerrace Floor Plan_compressed.pdf · uploaded 26 May 2022Source
- 8 Building Plan Approval / NA Order for plotted developmentSection Elevation Plan_compressed.pdf · uploaded 26 May 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 26 May 2022Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentGround Floor Part Completion.pdf · uploaded 28 Nov 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A - Prism - 2022-23.pdf · uploaded 7 Jul 2023Source
- 1 Disclosure of sold/ booked inventoryKumar Prism shops.PDF · uploaded 19 Jul 2023Source
- 2 Disclosure of sold/ booked inventoryKumar Prism Offices.PDF · uploaded 19 Jul 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Kumar Prism.PDF · uploaded 29 Aug 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Prism_Engineer's Certificate.pdf · uploaded 11 Oct 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Prism.PDF · uploaded 13 Oct 2023Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC - PRISM.PDF · uploaded 20 Oct 2023Source
- 1 Other – TechnicalDeclaration - Completion of Project - Prism.pdf · uploaded 28 Nov 2023Source
- 3 Architect’s Certificate on Completion of Project (Form 4)Kumar Prism-RERA Form 4.pdf · uploaded 6 Dec 2023Source
- 2 Other – TechnicalKumar Prism-RERA Form 4.pdf · uploaded 6 Dec 2023Source
Technical
- DocumentSheet No 1.pdf · uploaded 16 Feb 2022Source
- DocumentSheet No 2.pdf · uploaded 16 Feb 2022Source
- DocumentSheet No 3.pdf · uploaded 16 Feb 2022Source
- DocumentSheet No 4.pdf · uploaded 16 Feb 2022Source
- DocumentSheet No 5.pdf · uploaded 16 Feb 2022Source
- DocumentLayout_compressed.pdf · uploaded 26 May 2022Source
- DocumentBasement Floor Plan_compressed.pdf · uploaded 26 May 2022Source
- Document1 to 3 Floor Plan_compressed.pdf · uploaded 26 May 2022Source
- DocumentTerrace Floor Plan_compressed.pdf · uploaded 26 May 2022Source
- DocumentSection Elevation Plan_compressed.pdf · uploaded 26 May 2022Source
- Other – TechnicalDeclaration - Completion of Project - Prism.pdf · uploaded 28 Nov 2023Source
- Other – TechnicalKumar Prism-RERA Form 4.pdf · uploaded 6 Dec 2023Source
Technical (Architect)
- DocumentFORM1 44 MUNDHWA RERA CERTIFICATE.pdf · uploaded 16 Feb 2022Source
Technical (Engineer)
- DocumentPrism_Engineer's Certificate.pdf · uploaded 11 Oct 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals44A/12C
As registered with MahaRERA and published on its project page
- Project type
- Commercial
- Status on MahaRERA
- Certificate Signed
- Unit types
- Shop, Showroom10 units in all
- Address
- 44a/12c, Mundhawa Hadapsar Road, MundhawaPIN 411036
- Village
- Mundhawa, Haveli taluka
- Location
- 18.53303, 73.93300
- Designated bank account
- 109
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Side Margin And Adjoin S No 44 Part
- South
- Side Margin And 24 Mt Road
- East
- Side Margin And Open Space
- West
- Front Margin And Proposed 36 Mt Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking10 units
7 of 10 units booked (70%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 38.7 sq m · 417 sq ft | 1 | 1 |
| Shop | 55.92 sq m · 602 sq ft | 1 | 1 |
| Shop | 58.58 sq m · 631 sq ft | 1 | 1 |
| Shop | 85.04 sq m · 915 sq ft | 1 | 1 |
| Shop | 86.85 sq m · 935 sq ft | 1 | 1 |
| Shop | 105.29 sq m · 1,133 sq ft | 1 | 1 |
| Shop | 114.55 sq m · 1,233 sq ft | 1 | 1 |
| Showroom | 636.49 sq m · 6,851 sq ft | 3 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ar Sameer Valimbe | — |
| Chartered accountant | Supriya Abhijit Mundada | — |
| Engineer | Abhijeet Shekhar | — |
| Engineer | Mr Deepak Ambesange | — |
Source: MahaRERA project page. Contact details are not shown.