Vivencia
Deedo IDDP-PUN-MC04Completion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 23% of its units are booked.
Ghorpadi, Pune 411001 · by Kp50 Development Ventures Llp
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2027
- This projectRegistered 28 Apr 2023, completion promised 31 Dec 2026, revised to 30 Apr 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100050726
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100050726 | 28 Apr 2023 | 31 Dec 2026 | 30 Apr 2027 | Kp50 Development Ventures LLP | Project page |
Documents131
1 document held by Deedo, 130 filings listed on MahaRERA's project page
Finance
Legal
Show all 131 documentsShow fewer documents
Migrated
- 1 Declaration in FORM BFORM B Pramoter.pdf · uploaded 4 Mar 2023Source
- 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 4 Mar 2023Source
- 1 Deviation Report with respect to Allotment letterDeviation Report Allotment Letter.pdf · uploaded 4 Mar 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Report Agreement to Sell.pdf · uploaded 4 Mar 2023Source
- 1 Building Plan Approval / NA Order for plotted development1_11zon.pdf · uploaded 14 Mar 2023Source
- 2 Building Plan Approval / NA Order for plotted development2_11zon.pdf · uploaded 14 Mar 2023Source
- 3 Building Plan Approval / NA Order for plotted development3_11zon.pdf · uploaded 14 Mar 2023Source
- 4 Building Plan Approval / NA Order for plotted development4_11zon.pdf · uploaded 14 Mar 2023Source
- 5 Building Plan Approval / NA Order for plotted development5_11zon.pdf · uploaded 14 Mar 2023Source
- 6 Building Plan Approval / NA Order for plotted development6_11zon.pdf · uploaded 14 Mar 2023Source
- 7 Building Plan Approval / NA Order for plotted development7_11zon.pdf · uploaded 14 Mar 2023Source
- 1 Disclosure of Interest in Other Real Estate Organizations1_11zon.pdf · uploaded 14 Mar 2023Source
- 2 Disclosure of Interest in Other Real Estate Organizations2_11zon.pdf · uploaded 14 Mar 2023Source
- 1 a Details of encumbrances concerned to FinanceNo Encumbrance Certificate.pdf · uploaded 15 Mar 2023Source
- 1 b Details of encumbrances concerned to LegalNo Encumbrance Certificate.pdf · uploaded 15 Mar 2023Source
- 1 Declaration about Commencement CertificateDeclaration CC.pdf · uploaded 15 Mar 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration Separate Bank Account.pdf · uploaded 15 Mar 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentMEERANAGAR CC_compressed.pdf · uploaded 18 Mar 2023Source
- 1 CERSAI details06 Undertaking in case of no charge plus cersai.pdf · uploaded 24 Mar 2023Source
- 1 Proforma of Agreement for saleRERA ATS_compressed-rev.pdf · uploaded 31 Mar 2023Source
- 1 Copy of the legal title reportTitel Report 03042023Vivencia.pdf · uploaded 4 Apr 2023Source
- 1 Other – LegalRera Declaration Compressed.pdf · uploaded 21 Apr 2023Source
- 1 Other – FinanceRera Declaration Compressed.pdf · uploaded 21 Apr 2023Source
- 1 Other – TechnicalRera Declaration Compressed.pdf · uploaded 21 Apr 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Certificate (1).pdf · uploaded 22 Apr 2023Source
- 2 Copy of Layout Approval (in case of layout)1 Layout _compressed.pdf · uploaded 5 Jan 2024Source
- 8 Building Plan Approval / NA Order for plotted development2.pdf · uploaded 5 Jan 2024Source
- 9 Building Plan Approval / NA Order for plotted development3.pdf · uploaded 5 Jan 2024Source
- 10 Building Plan Approval / NA Order for plotted development4.pdf · uploaded 5 Jan 2024Source
- 11 Building Plan Approval / NA Order for plotted development5.pdf · uploaded 5 Jan 2024Source
- 12 Building Plan Approval / NA Order for plotted development6.pdf · uploaded 5 Jan 2024Source
- 13 Building Plan Approval / NA Order for plotted development7.pdf · uploaded 5 Jan 2024Source
- 14 Building Plan Approval / NA Order for plotted development8.pdf · uploaded 5 Jan 2024Source
- 15 Building Plan Approval / NA Order for plotted development9.pdf · uploaded 5 Jan 2024Source
- 16 Building Plan Approval / NA Order for plotted development10.pdf · uploaded 5 Jan 2024Source
- 2 Commencement Certificates / NA Order for plotted developmentCC 2185 23.pdf · uploaded 5 Jan 2024Source
- 2 Declaration about Commencement CertificateDeclaration 050124.pdf · uploaded 5 Jan 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q1.pdf · uploaded 4 Feb 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Q2.pdf · uploaded 4 Feb 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1_Q3.pdf · uploaded 4 Feb 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q 1.pdf · uploaded 4 Feb 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q 2.pdf · uploaded 4 Feb 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Q3.pdf · uploaded 4 Feb 2024Source
- 1 Disclosure of sold/ booked inventorySold Unsold Q1Edited.pdf · uploaded 4 Feb 2024Source
- 2 Disclosure of sold/ booked inventorySold Unsold Q2.pdf · uploaded 4 Feb 2024Source
- 3 Disclosure of sold/ booked inventorySold Unsold Format Q3_11zon.pdf · uploaded 4 Feb 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-03 Jun-23_11zon.pdf · uploaded 4 Feb 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-03 Sep-23_11zon.pdf · uploaded 4 Feb 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-03 -Dec-23_11zon.pdf · uploaded 4 Feb 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 FY22-23.pdf · uploaded 4 Mar 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-01.pdf · uploaded 17 Apr 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-02.pdf · uploaded 17 Apr 2024Source
- 4 Disclosure of sold/ booked inventoryDisclosure_compressed.pdf · uploaded 17 Apr 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-03_compressed.pdf · uploaded 17 Apr 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-01.pdf · uploaded 29 Jul 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-02.pdf · uploaded 29 Jul 2024Source
- 5 Disclosure of sold/ booked inventoryInventory Disclosure_compressed.pdf · uploaded 29 Jul 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-03_compressed.pdf · uploaded 29 Jul 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form -3_compressed.pdf · uploaded 22 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2.pdf · uploaded 22 Oct 2024Source
- 2 Disclosure of sold/ booked inventoryDisclosure of Inventory_compressed.pdf · uploaded 22 Oct 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1.pdf · uploaded 24 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 FY 202324.pdf · uploaded 21 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 FY 202324.pdf · uploaded 21 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1.pdf · uploaded 22 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3_compressed.pdf · uploaded 22 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2.pdf · uploaded 22 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryUnit Disclosure_compressed.pdf · uploaded 22 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)KP form 1.pdf · uploaded 19 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)kp form 3_compressed.pdf · uploaded 19 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryKP DISCLOSURE OF INVENTORY.pdf · uploaded 19 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 22 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 22 Jul 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed.pdf · uploaded 22 Jul 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 22 Jul 2025Source
- 1 Disclosure of sold/ booked inventoryInventory Disclosure_compressed.pdf · uploaded 22 Jul 2025Source
- Form 1Vivencia form 1.pdf · uploaded 3 Jan 2026Source
- Form 2Vvencia Form 2.pdf · uploaded 3 Jan 2026Source
- Form 3Vivencia Form 3.pdf · uploaded 3 Jan 2026Source
- Disclosure of Sold and Booked InventoryDisclosure of Investory.pdf · uploaded 3 Jan 2026Source
- Form 1Form 1.pdf · uploaded 19 Jan 2026Source
- Form 2Form 2.pdf · uploaded 19 Jan 2026Source
- Form 3Form 3_compressed.pdf · uploaded 19 Jan 2026Source
- Disclosure of Sold and Booked InventoryDisclosure of Inventory.pdf · uploaded 19 Jan 2026Source
- Form 1Form-1.pdf · uploaded 20 Apr 2026Source
- Form 2Form-2.pdf · uploaded 20 Apr 2026Source
- Form 3Form-3.pdf · uploaded 20 Apr 2026Source
- Disclosure of Sold and Booked InventoryInventory disclosure.pdf · uploaded 20 Apr 2026Source
- Form 1Rera Form-1.pdf · uploaded 16 Jul 2026Source
- Form 2Rera Form-2.pdf · uploaded 16 Jul 2026Source
- Form 3Rera Form-3.pdf · uploaded 16 Jul 2026Source
- Disclosure of Sold and Booked InventoryInventory Disclosure.pdf · uploaded 16 Jul 2026Source
- Form 5 (FY 2025-2026)Form 5.pdf · uploaded 11 Aug 2026Source
- Form 2A (FY 2025-2026)Form-2A.pdf · uploaded 22 Aug 2026Source
Technical
- DocumentLAYOUT.pdf · uploaded 17 Nov 2022Source
- Document1_11zon.pdf · uploaded 14 Mar 2023Source
- Document2_11zon.pdf · uploaded 14 Mar 2023Source
- Document3_11zon.pdf · uploaded 14 Mar 2023Source
- Document4_11zon.pdf · uploaded 14 Mar 2023Source
- Document5_11zon.pdf · uploaded 14 Mar 2023Source
- Document6_11zon.pdf · uploaded 14 Mar 2023Source
- Document7_11zon.pdf · uploaded 14 Mar 2023Source
- Other – TechnicalRera Declaration Compressed.pdf · uploaded 21 Apr 2023Source
- Document1 Layout _compressed.pdf · uploaded 5 Jan 2024Source
- Document2.pdf · uploaded 5 Jan 2024Source
- Document3.pdf · uploaded 5 Jan 2024Source
- Document4.pdf · uploaded 5 Jan 2024Source
- Document5.pdf · uploaded 5 Jan 2024Source
- Document6.pdf · uploaded 5 Jan 2024Source
- Document7.pdf · uploaded 5 Jan 2024Source
- Document8.pdf · uploaded 5 Jan 2024Source
- Document9.pdf · uploaded 5 Jan 2024Source
- Document10.pdf · uploaded 5 Jan 2024Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel Final Plot No 350, Survey No32/A/6
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Address
- Final Plot No 350, Survey No32/A/6, Sangamwadi TPS, Final Plot: 350, Survey No: 32/A/6, LANE NO. 7, SAGAMWADI TPS, KOREGAON PARKPIN 411001
- Village
- Pune (M Corp.), Pune City taluka
- Location
- 18.53431, 73.89957
- Land area for this project
- 3,753 sq m (40,402 sq ft)
- Permissible built-up area
- 15,014 sq m (1,61,607 sq ft)
- Sanctioned built-up area
- 14,841 sq m (1,59,744 sq ft)
- Designated bank account
- 85
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Final Plot No 350, Survey No32/A/6, Sangamwadi TPS
Boundaries
- North
- Fp 339
- South
- Fp 358
- East
- Dp Road
- West
- Fp 351 And 357
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Adva Studio Pvt Ltd | — |
| Architect | Gohad Architects | — |
| Chartered accountant | Hemang Vyasa | — |
| Chartered accountant | Nitesh M Shah | — |
| Engineer | Machindra Sirsath | — |
Source: MahaRERA project page. Contact details are not shown.