The Mpire

Certificate Signed

Fursungi, Pune 412308 |Promoter: Eagle Developers

12 Oct 2018Registered with MahaRERAFirst of 2 registrations
31 Dec 2028Promised completionLatest across registrations
30 Apr 2029Revised completion1 of 2 registrations pushed back, by up to 4 months
2Buildings2 phases
221Units registered70 booked (32%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
RERA registrations
2
Phases
2
Buildings
2
Unit types
1 BHK, 1BHK, 1 BHK Landowner, 1BHK landowner, 1BHK Landowner, 2 BHK, Office Space Ground, Podium Floor, Shop Ground Floor, 2BHK221 units in all
Address
236, 5a/1, 5b/1, 5b/2, , Next To Fursungi Last Bus Stop Near Walnut School, Fursungi VillagePIN 412308
Designated bank account
220
Developed in phases
No

Also registered as

The Mpire Building A

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Mar 2022

P52100018184

The latest completion date on record passed 4 years and 7 months ago.

Registered
12 Oct 2018
Promised
30 Mar 2022

Completion pushed back 4 months

P52100081103
Registered
2 Mar 2026
Promised
31 Dec 2028
Revised
30 Apr 2029

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210001818412 Oct 201830 Mar 202230 Mar 2022Eagle DevelopersProject page
P521000811032 Mar 202631 Dec 202830 Apr 2029Eagle DevelopersProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Purandar883
Shivneri17138

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

70 of 221 units booked (32%), as the promoter reported to MahaRERA

1 BHK · 24 units1BHK · 81 units1 BHK Landowner · 3 units1BHK landowner · 1 unit1BHK Landowner · 9 units2 BHK · 24 unitsOffice Space Ground · 5 unitsPodium Floor · 5 unitsShop Ground Floor · 13 units2BHK · 56 units
RERABuildingTypeCarpet areaUnitsBooked
P52100081103Purandar1 BHK36.92 sq m · 397 sq ft30
P52100081103Purandar1 BHK37.14 sq m · 400 sq ft10
P52100081103Purandar1 BHK37.24 sq m · 401 sq ft10
P52100081103Purandar1 BHK37.38 sq m · 402 sq ft50
P52100081103Purandar1BHK37.1 sq m · 399 sq ft100
P52100081103Purandar1BHK37.23 sq m · 401 sq ft30
P52100081103Purandar1 BHK Landowner37.38 sq m · 402 sq ft30
P52100081103Purandar1BHK landowner37.26 sq m · 401 sq ft10
Show all 50 unit rowsShow fewer unit rows
RERABuildingTypeCarpet areaUnitsBooked
P52100081103Purandar1BHK Landowner36.92 sq m · 397 sq ft30
P52100081103Purandar1BHK Landowner37.07 sq m · 399 sq ft20
P52100081103Purandar1BHK Landowner37.23 sq m · 401 sq ft20
P52100081103Purandar1BHK Landowner37.28 sq m · 401 sq ft10
P52100081103Purandar1BHK Landowner37.32 sq m · 402 sq ft10
P52100081103Purandar2 BHK54.41 sq m · 586 sq ft40
P52100081103Purandar2 BHK54.42 sq m · 586 sq ft40
P52100081103Purandar2 BHK54.72 sq m · 589 sq ft40
P52100081103Purandar2 BHK54.74 sq m · 589 sq ft40
P52100081103Purandar2 BHK55.14 sq m · 594 sq ft20
P52100081103Purandar2 BHK55.15 sq m · 594 sq ft20
P52100081103Purandar2 BHK55.45 sq m · 597 sq ft20
P52100081103Purandar2 BHK55.47 sq m · 597 sq ft20
P52100081103PurandarOffice Space Ground22.19 sq m · 239 sq ft10
P52100081103PurandarOffice Space Ground22.26 sq m · 240 sq ft10
P52100081103PurandarOffice Space Ground27.97 sq m · 301 sq ft10
P52100081103PurandarOffice Space Ground28.19 sq m · 303 sq ft10
P52100081103PurandarOffice Space Ground28.88 sq m · 311 sq ft10
P52100081103PurandarPodium Floor44.62 sq m · 480 sq ft10
P52100081103PurandarPodium Floor44.93 sq m · 484 sq ft20
P52100081103PurandarPodium Floor65.04 sq m · 700 sq ft10
P52100081103PurandarPodium Floor65.14 sq m · 701 sq ft10
P52100081103PurandarShop Ground Floor5.67 sq m · 61 sq ft20
P52100081103PurandarShop Ground Floor6.75 sq m · 73 sq ft10
P52100081103PurandarShop Ground Floor11.93 sq m · 128 sq ft10
P52100081103PurandarShop Ground Floor12.07 sq m · 130 sq ft10
P52100081103PurandarShop Ground Floor12.09 sq m · 130 sq ft10
P52100081103PurandarShop Ground Floor21.51 sq m · 232 sq ft10
P52100081103PurandarShop Ground Floor21.7 sq m · 234 sq ft20
P52100081103PurandarShop Ground Floor21.87 sq m · 235 sq ft10
P52100081103PurandarShop Ground Floor21.93 sq m · 236 sq ft10
P52100081103PurandarShop Ground Floor27.13 sq m · 292 sq ft10
P52100081103PurandarShop Ground Floor27.55 sq m · 297 sq ft10
P52100018184Shivneri1 BHK30.95 sq m · 333 sq ft144
P52100018184Shivneri1BHK30.45 sq m · 328 sq ft149
P52100018184Shivneri1BHK30.58 sq m · 329 sq ft1310
P52100018184Shivneri1BHK30.6 sq m · 329 sq ft145
P52100018184Shivneri1BHK30.8 sq m · 332 sq ft2717
P52100018184Shivneri2BHK47.2 sq m · 508 sq ft2010
P52100018184Shivneri2BHK47.45 sq m · 511 sq ft2010
P52100018184Shivneri2BHK47.75 sq m · 514 sq ft82
P52100018184Shivneri2BHK47.99 sq m · 517 sq ft83

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 112 filings listed on MahaRERA's project page

Registration certificate (2)

  • Registration certificateP52100018184 · 9 Sep 2021ViewSource
  • Registration certificateP52100081103 · 2 Mar 2026ViewSource

Finance

  • PAN CardP52100018184 · PAN card.pdf · uploaded 12 Sep 2018Source
  • PAN CardP52100081103 · 01_Eagle PAN card.pdf · uploaded 27 Jan 2025Source

Legal

  • Legal Title reportP52100018184 · SEARCH REPORT 1.pdf · uploaded 12 Sep 2018Source
  • Declaration Form BP52100018184 · FORM B 1.pdf · uploaded 2 Oct 2018Source
  • Legal Title reportP52100081103 · 1 Copy of the legal title report.pdf · uploaded 27 Jan 2025Source
  • Declaration Form BP52100081103 · 16_FORM B BY PROMOTER.pdf · uploaded 29 Jan 2025Source
Show all 114 documentsShow fewer documents

Legal

  • Declaration Form BP52100081103 · FORM B BY LANDOWNER.pdf · uploaded 25 Jul 2025Source
  • Other – LegalP52100081103 · Declaration (1).pdf · uploaded 13 Sep 2025Source

Migrated

  • 1 PAN CardP52100018184 · PAN card.pdf · uploaded 12 Sep 2018Source
  • 1 Copy of the legal title reportP52100018184 · SEARCH REPORT 1.pdf · uploaded 12 Sep 2018Source
  • 1 Copy of Layout Approval (in case of layout)P52100018184 · PLAN 1.pdf · uploaded 12 Sep 2018Source
  • 1 Building Plan Approval (IOD)P52100018184 · PLAN 1.pdf · uploaded 12 Sep 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100018184 · COMENCEMENT CERTIFICATE.pdf · uploaded 12 Sep 2018Source
  • 1 Details of encumbrancesP52100018184 · ENCUMBRANCE.pdf · uploaded 2 Oct 2018Source
  • 1 Declaration in FORM BP52100018184 · FORM B 1.pdf · uploaded 2 Oct 2018Source
  • 1 Proforma of Allotment letterP52100018184 · DECLARATION SUBSEQUENT.pdf · uploaded 2 Oct 2018Source
  • 1 Certificates of CA (Form 3)P52100018184 · CA CERTIFICATE.pdf · uploaded 3 Oct 2018Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100018184 · Architect Certificate for RERA upto sept 2019.pdf · uploaded 1 Jan 2020Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100018184 · Engineers Certificate for RERA upto sept 2019.pdf · uploaded 1 Jan 2020Source
  • 2 Certificates of CA (Form 3)P52100018184 · CA CERTIFICATE_.pdf · uploaded 1 Jan 2020Source
  • 3 Certificates of CA (Form 3)P52100018184 · CA CERTIFICATE_.pdf · uploaded 3 Jan 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)P52100018184 · FORM 5.pdf · uploaded 31 Jan 2020Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100018184 · ARCHITECT CERTIFICATE_.pdf · uploaded 20 Feb 2020Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100018184 · ENGINEER CERTIFICATE.pdf · uploaded 20 Feb 2020Source
  • 4 Certificates of CA (Form 3)P52100018184 · CA CERTIFICATE_.pdf · uploaded 20 Feb 2020Source
  • 2 Copy of Layout Approval (in case of layout)P52100018184 · PMC SANCTION MASTER LAYOUT_compressed.pdf · uploaded 6 Mar 2020Source
  • 2 Building Plan Approval (IOD)P52100018184 · PMC CC (IOD)_compressed.pdf · uploaded 6 Mar 2020Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100018184 · ARCHITECT CERTIFICATE.pdf · uploaded 20 Aug 2021Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100018184 · ENGINEER CERTIFICATE.pdf · uploaded 20 Aug 2021Source
  • 5 Certificates of CA (Form 3)P52100018184 · CA CERTIFICATE_.pdf · uploaded 20 Aug 2021Source
  • 1 Disclosure of sold/ booked inventoryP52100018184 · Disclosure of sold booked inventory.pdf · uploaded 23 Aug 2021Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100018184 · O C.pdf · uploaded 27 Jan 2022Source
  • 4 Architect’s Certificate on Completion of Project (Form 4)P52100018184 · FORM 4 NEW.pdf · uploaded 8 Apr 2022Source
  • 1 PAN CardP52100081103 · 01_Eagle PAN card.pdf · uploaded 27 Jan 2025Source
  • 1 Copy of the legal title reportP52100081103 · 1 Copy of the legal title report.pdf · uploaded 27 Jan 2025Source
  • 2 a Details of encumbrances concerned to FinanceP52100081103 · 04_DECLARATION OF NO LEGAL ENCUMBRANCES.pdf · uploaded 27 Jan 2025Source
  • 1 Copy of Layout Approval (in case of layout)P52100081103 · UDMC 2025 Sanction Plan set (4)-1_compressed.pdf · uploaded 27 Jan 2025Source
  • 2 Copy of Layout Approval (in case of layout)P52100081103 · UDMC 2025 Sanction Plan set (4)-10.pdf · uploaded 27 Jan 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100081103 · CC order UDMC 2025.pdf · uploaded 27 Jan 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentP52100081103 · UDMC 2025 Sanction Plan set (4)-11.pdf · uploaded 27 Jan 2025Source
  • 3 Building Plan Approval / NA Order for plotted developmentP52100081103 · UDMC 2025 Sanction Plan set (4)-12.pdf · uploaded 27 Jan 2025Source
  • 4 Building Plan Approval / NA Order for plotted developmentP52100081103 · REV-01_RERA SALE PLAN_FIRST SECOND PLAN_18122025 Upload on layout.pdf · uploaded 27 Jan 2025Source
  • 5 Building Plan Approval / NA Order for plotted developmentP52100081103 · REV-01_RERA SALE PLAN_GROUND PODIUM PLAN_18122025.pdf · uploaded 27 Jan 2025Source
  • 2 b Details of encumbrances concerned to LegalP52100081103 · 04_DECLARATION OF NO LEGAL ENCUMBRANCES.pdf · uploaded 27 Jan 2025Source
  • 1 Proforma of Agreement for saleP52100081103 · 1 Proforma of Agreement for sale.pdf · uploaded 27 Jan 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsP52100081103 · 28_ANNEXURE A DISCLOSURE OF INTEREST IN OTHER REAL ESTATE ORGANIZATION.pdf · uploaded 27 Jan 2025Source
  • 1 Declaration in FORM BP52100081103 · 16_FORM B BY PROMOTER.pdf · uploaded 29 Jan 2025Source
  • 1 Deviation Report with respect to Allotment letterP52100081103 · 45_DECLARATION FOR REPORT ON DEVATION IN RESPECT OF ALLOTMENT.pdf · uploaded 29 Jan 2025Source
  • 1 Deviation Report with respect to model copy of AgreementP52100081103 · 46_DECLARATION FOR REPORT ON DEVATION IN RESPECT OF AGGREMENT FOR SALE.pdf · uploaded 29 Jan 2025Source
  • 1 CERSAI detailsP52100081103 · Declaration on CERSAI Report.pdf · uploaded 24 Jul 2025Source
  • 2 Declaration in FORM BP52100081103 · FORM B BY LANDOWNER.pdf · uploaded 25 Jul 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100081103 · ARCHITECT CERTIFICATE-BLDG-A Jan 30, 2025.pdf · uploaded 25 Jul 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100081103 · Engeeners Certificate.pdf · uploaded 28 Jul 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectP52100081103 · Disclosure for SECURED UNSECURED FINANCE -Project-A.pdf · uploaded 28 Jul 2025Source
  • 1 Other – LegalP52100081103 · Declaration (1).pdf · uploaded 13 Sep 2025Source
  • 8 Other – TechnicalP52100081103 · UDMC 2025 Sanction Plan set-12.pdf · uploaded 13 Sep 2025Source
  • 9 Other – TechnicalP52100081103 · 100 Power of attorney Ms Eagle Developers 10012017.pdf · uploaded 13 Sep 2025Source
  • 7 Other – TechnicalP52100081103 · UDMC 2025 Sanction Plan set-11.pdf · uploaded 13 Sep 2025Source
  • 6 Other – TechnicalP52100081103 · UDMC 2025 Sanction Plan set-4.pdf · uploaded 13 Sep 2025Source
  • 5 Other – TechnicalP52100081103 · UDMC 2025 Sanction Plan set-3.pdf · uploaded 13 Sep 2025Source
  • 4 Other – TechnicalP52100081103 · Second sheet of plan.pdf · uploaded 13 Sep 2025Source
  • 3 Other – TechnicalP52100081103 · UDMC 2025 Sanction Plan set-1_compressed.pdf · uploaded 13 Sep 2025Source
  • 2 Other – TechnicalP52100081103 · Annexure A_Declaration cum undertaking.pdf · uploaded 13 Sep 2025Source
  • 11 Other – TechnicalP52100081103 · Format D_Declaration on CC.pdf · uploaded 22 Nov 2025Source
  • 10 Other – TechnicalP52100081103 · Gmail - Fwd_ The Mpire Verification of Commencement certificate from UDMC.pdf · uploaded 22 Nov 2025Source
  • 1 a Details of encumbrances concerned to FinanceP52100081103 · Declaration on No Financial Encu.pdf · uploaded 2 Jan 2026Source
  • 1 b Details of encumbrances concerned to LegalP52100081103 · Declaration on No Financial Encu.pdf · uploaded 2 Jan 2026Source
  • 1 Proforma of Allotment letterP52100081103 · Allotment Letter -Annexure-1_compressed.pdf · uploaded 3 Jan 2026Source
  • 1 Building Plan Approval / NA Order for plotted developmentP52100081103 · REV-01_RERA SALE PLAN_TYPICAL 3RD 5TH4TH 6TH PLAN_18122025.pdf · uploaded 3 Jan 2026Source
  • 1 Declaration about Commencement CertificateP52100081103 · Form D.pdf · uploaded 6 Jan 2026Source
  • 1 Other – TechnicalP52100081103 · Final_Annexure A_Signed.pdf · uploaded 7 Jan 2026Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)P52100081103 · Format A.pdf · uploaded 3 Feb 2026Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)P52100081103 · Format B - Landowner.pdf · uploaded 3 Feb 2026Source
  • 2 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)P52100081103 · Format B - Promotor .pdf · uploaded 3 Feb 2026Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100081103 · Form 3 Updated as on 20-02-2026.pdf · uploaded 20 Feb 2026Source
  • Form 1P52100081103 · Form 1.pdf · uploaded 29 Sep 2026Source
  • Form 2P52100081103 · Form 2.pdf · uploaded 29 Sep 2026Source
  • Form 3P52100081103 · Form 3.pdf · uploaded 29 Sep 2026Source
  • Disclosure of Sold and Booked InventoryP52100081103 · DISCLOSURE OF SOLD BOOKED INVENTORY BLD A March 26.pdf · uploaded 29 Sep 2026Source
  • Form 1P52100081103 · Form 1.pdf · uploaded 29 Sep 2026Source
  • Form 2P52100081103 · Form 2.pdf · uploaded 29 Sep 2026Source
  • Form 3P52100081103 · Form 3.pdf · uploaded 29 Sep 2026Source
  • Disclosure of Sold and Booked InventoryP52100081103 · DISCLOSURE OF SOLD BOOKED INVENTORY BLD A March 26.pdf · uploaded 29 Sep 2026Source
  • Withdrawal Update Form 1P52100081103 · Form 1.pdf · uploaded 12 Oct 2026Source
  • Withdrawal Update Form 2P52100081103 · Form 2.pdf · uploaded 12 Oct 2026Source
  • Withdrawal Update Form 3P52100081103 · Form 3.pdf · uploaded 12 Oct 2026Source

Technical

  • DocumentP52100018184 · PLAN 1.pdf · uploaded 12 Sep 2018Source
  • DocumentP52100018184 · PLAN 1.pdf · uploaded 12 Sep 2018Source
  • DocumentP52100018184 · PMC CC (IOD)_compressed.pdf · uploaded 6 Mar 2020Source
  • DocumentP52100018184 · PMC SANCTION MASTER LAYOUT_compressed.pdf · uploaded 6 Mar 2020Source
  • DocumentP52100081103 · UDMC 2025 Sanction Plan set (4)-1_compressed.pdf · uploaded 27 Jan 2025Source
  • DocumentP52100081103 · UDMC 2025 Sanction Plan set (4)-10.pdf · uploaded 27 Jan 2025Source
  • DocumentP52100081103 · UDMC 2025 Sanction Plan set (4)-11.pdf · uploaded 27 Jan 2025Source
  • DocumentP52100081103 · UDMC 2025 Sanction Plan set (4)-12.pdf · uploaded 27 Jan 2025Source
  • DocumentP52100081103 · REV-01_RERA SALE PLAN_FIRST SECOND PLAN_18122025 Upload on layout.pdf · uploaded 27 Jan 2025Source
  • DocumentP52100081103 · REV-01_RERA SALE PLAN_GROUND PODIUM PLAN_18122025.pdf · uploaded 27 Jan 2025Source
  • Other – TechnicalP52100081103 · Annexure A_Declaration cum undertaking.pdf · uploaded 13 Sep 2025Source
  • Other – TechnicalP52100081103 · UDMC 2025 Sanction Plan set-1_compressed.pdf · uploaded 13 Sep 2025Source
  • Other – TechnicalP52100081103 · Second sheet of plan.pdf · uploaded 13 Sep 2025Source
  • Other – TechnicalP52100081103 · UDMC 2025 Sanction Plan set-3.pdf · uploaded 13 Sep 2025Source
  • Other – TechnicalP52100081103 · UDMC 2025 Sanction Plan set-4.pdf · uploaded 13 Sep 2025Source
  • Other – TechnicalP52100081103 · UDMC 2025 Sanction Plan set-11.pdf · uploaded 13 Sep 2025Source
  • Other – TechnicalP52100081103 · UDMC 2025 Sanction Plan set-12.pdf · uploaded 13 Sep 2025Source
  • Other – TechnicalP52100081103 · 100 Power of attorney Ms Eagle Developers 10012017.pdf · uploaded 13 Sep 2025Source
  • Other – TechnicalP52100081103 · Gmail - Fwd_ The Mpire Verification of Commencement certificate from UDMC.pdf · uploaded 22 Nov 2025Source
  • Other – TechnicalP52100081103 · Format D_Declaration on CC.pdf · uploaded 22 Nov 2025Source
  • DocumentP52100081103 · REV-01_RERA SALE PLAN_TYPICAL 3RD 5TH4TH 6TH PLAN_18122025.pdf · uploaded 3 Jan 2026Source
  • Other – TechnicalP52100081103 · Final_Annexure A_Signed.pdf · uploaded 7 Jan 2026Source

Technical (Architect)

  • DocumentP52100018184 · ARCHITECT CERTIFICATE.pdf · uploaded 20 Aug 2021Source
  • DocumentP52100081103 · Form 1.pdf · uploaded 12 Oct 2026Source

Technical (Engineer)

  • DocumentP52100018184 · ENGINEER CERTIFICATE.pdf · uploaded 20 Aug 2021Source
  • DocumentP52100081103 · Form 2.pdf · uploaded 12 Oct 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Fursungi, Haveli taluka

Survey, CTS, gat or plot numbers

2365A/15B/15B/25B/2 New Survey No. 236/5A/2/1Hiss No.5A/1

Boundaries

North
Property Of Ram Chandra Pandharinath Pawar
South
Eagle Developers Building A
East
Area Given Agn Venture For Development
West
Survey No 234 235

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectRahul Soma Londhe—P52100018184
ArchitectRao Architects—P52100081103
Chartered accountantHeena B Momaya—P52100081103
EngineerAgre India Engineering Consultancy—P52100081103
OtherJitendra Pawar—P52100081103

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology