Kuldeep
Deedo IDDP-PUN-MQ58Completion was pushed back 4 months, to Oct 2028; no MahaRERA orders on record; 82% of its units are booked.
Erandwane, Pune 411004 · by Ranade Bagade Construction Llp
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Oct 2028
- This projectRegistered 23 Jul 2024, completion promised 30 Jun 2028, revised to 30 Oct 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100077075
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100077075 | 23 Jul 2024 | 30 Jun 2028 | 30 Oct 2028 | Ranade Bagade Construction LLP | Project page |
Documents88
1 document held by Deedo, 87 filings listed on MahaRERA's project page
Finance
- PAN Card1 -Pan Card-RBC LLP.pdf · uploaded 17 May 2024Source
Legal
Show all 88 documentsShow fewer documents
Migrated
- 2 a Details of encumbrances concerned to Finance5-Declaration of no Encumbrance - Legal.pdf · uploaded 17 May 2024Source
- 1 b Details of encumbrances concerned to Legal4-Declaration of no Encumbrance - Finance (1).pdf · uploaded 17 May 2024Source
- 2 b Details of encumbrances concerned to Legal5-Declaration of no Encumbrance - Legal.pdf · uploaded 17 May 2024Source
- 1 CERSAI details14-Cersai Report ok.pdf · uploaded 17 May 2024Source
- 1 Disclosure of Interest in Other Real Estate Organizations15-Annexure A Disclosure of Interest in Entities Kapil.pdf · uploaded 17 May 2024Source
- 2 Disclosure of Interest in Other Real Estate Organizations15-Annexure A Disclosure of Interest in Entities- Megha.pdf · uploaded 17 May 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the same18-Declaration About Separate Bank Ac.pdf · uploaded 17 May 2024Source
- 1 Other – TechnicalOrder 50 ANNEXURE A.pdf · uploaded 18 May 2024Source
- 1 Declaration in FORM BForm B-Promoter.pdf · uploaded 24 May 2024Source
- 1 Deviation Report with respect to Allotment letterDeviation-Allotment Letter.pdf · uploaded 24 May 2024Source
- 3 Disclosure of Interest in Other Real Estate Organizations15-Annexure A Disclosure of Interest in Entities LLP.pdf · uploaded 25 May 2024Source
- 1 Other – LegalUpload Agreement _ MoU Copy.pdf · uploaded 25 May 2024Source
- 2 Other – LegalUpload Agreement _ MoU Copy (1).pdf · uploaded 25 May 2024Source
- 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 30 May 2024Source
- 1 Proforma of Agreement for saleProforma of Agreement for sale.pdf · uploaded 30 May 2024Source
- 1 Deviation Report with respect to model copy of AgreementDeviation-ATS.pdf · uploaded 30 May 2024Source
- 1 Copy of Layout Approval (in case of layout)Sanction Plan-Kuldeep - 1.pdf · uploaded 20 Jun 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentSanction Plan-Kuldeep - 1.pdf · uploaded 20 Jun 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentSanction Plan-Kuldeep - 2.pdf · uploaded 20 Jun 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentSanction Plan-Kuldeep - 3.pdf · uploaded 20 Jun 2024Source
- 4 Building Plan Approval / NA Order for plotted developmentSanction Plan-Kuldeep - 4.pdf · uploaded 20 Jun 2024Source
- 5 Building Plan Approval / NA Order for plotted developmentSanction Plan-Kuldeep - 5.pdf · uploaded 20 Jun 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentcommentsment-Kuldeep.pdf · uploaded 20 Jun 2024Source
- 1 Declaration about Commencement CertificateDeclaration About Commencement.pdf · uploaded 20 Jun 2024Source
- 1 Copy of the legal title reportFinal Search Upload.pdf · uploaded 21 Jun 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)May 2024 FORM 3 CA Certificate Kuldeep.pdf · uploaded 21 Jun 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Kuldeep.pdf · uploaded 21 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Kuldeep.pdf · uploaded 21 Oct 2024Source
- 2 Disclosure of sold/ booked inventoryDisclosure of sold booked Inventory - Kuldeep.pdf · uploaded 21 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Form - Kuldeep_.pdf · uploaded 29 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Rera Form 1-Kuldeep.pdf · uploaded 3 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Kuldeep.pdf · uploaded 3 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure of sold booked Inventory - Kuldeep.pdf · uploaded 3 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA form - Kuldeep_compressed.pdf · uploaded 20 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Rera Form 1-Kuldeep.pdf · uploaded 29 Mar 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 -Kuldeep_compressed.pdf · uploaded 29 Mar 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure of sold booked Inventory - Kuldeep.pdf · uploaded 29 Mar 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Form - Kuldeep_compressed.pdf · uploaded 19 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Kuldeep_compressed.pdf · uploaded 19 Apr 2025Source
- Withdrawal Update Form 1Withdrawal Application Form1.pdf · uploaded 22 Jul 2025Source
- Withdrawal Update Form 2Withdrawal Application Form2.pdf · uploaded 22 Jul 2025Source
- Withdrawal Update Form 3Withdrawal Application Form3.pdf · uploaded 22 Jul 2025Source
- Form 5 (FY 2024-2025)Form 5.pdf · uploaded 15 Oct 2025Source
- Form 2A (FY 2024-2025)Form 2A.pdf · uploaded 16 Oct 2025Source
- Withdrawal Update Form 1Withdrawal Application Form1.pdf · uploaded 19 Oct 2025Source
- Withdrawal Update Form 2Withdrawal Application Form2.pdf · uploaded 19 Oct 2025Source
- Withdrawal Update Form 3Withdrawal Application Form3.pdf · uploaded 19 Oct 2025Source
- Withdrawal Update Form 1Withdrawal Application Form 1.pdf · uploaded 21 Jan 2026Source
- Withdrawal Update Form 2Withdrawal Application Form 2.pdf · uploaded 21 Jan 2026Source
- Withdrawal Update Form 3Withdrawal Application Form 3.pdf · uploaded 21 Jan 2026Source
- Withdrawal Update Form 1Withdrawal Application Form1.pdf · uploaded 18 Apr 2026Source
- Withdrawal Update Form 2Withdrawal Application Form2.pdf · uploaded 18 Apr 2026Source
- Withdrawal Update Form 3Withdrawal Application Form3.pdf · uploaded 18 Apr 2026Source
- Form 2A (FY 2025-2026)Form 2A.pdf · uploaded 7 Jul 2026Source
- Withdrawal Update Form 1Withdrawal Application Form1.pdf · uploaded 15 Jul 2026Source
- Withdrawal Update Form 2Withdrawal Application Form2.pdf · uploaded 15 Jul 2026Source
- Withdrawal Update Form 3Withdrawal Application Form3.pdf · uploaded 15 Jul 2026Source
- Form 5 (FY 2025-2026)Form 5 - Kuldeep.pdf · uploaded 16 Sep 2026Source
Technical
- Other – TechnicalOrder 50 ANNEXURE A.pdf · uploaded 18 May 2024Source
- DocumentSanction Plan-Kuldeep - 1.pdf · uploaded 20 Jun 2024Source
- DocumentSanction Plan-Kuldeep - 2.pdf · uploaded 20 Jun 2024Source
- DocumentSanction Plan-Kuldeep - 3.pdf · uploaded 20 Jun 2024Source
- DocumentSanction Plan-Kuldeep - 4.pdf · uploaded 20 Jun 2024Source
- DocumentSanction Plan-Kuldeep - 5.pdf · uploaded 20 Jun 2024Source
- DocumentSanction Plan-Kuldeep - 1.pdf · uploaded 20 Jun 2024Source
- DocumentSanction Plan - 1_compressed.pdf · uploaded 22 Jul 2025Source
- DocumentSanction Plan - 2_compressed.pdf · uploaded 22 Jul 2025Source
- DocumentSanction Plan - 3_compressed.pdf · uploaded 22 Jul 2025Source
- DocumentSanction Plan - 4_compressed.pdf · uploaded 22 Jul 2025Source
- DocumentSanction Plan - 5_compressed.pdf · uploaded 22 Jul 2025Source
- DocumentCommencement Certificate.pdf · uploaded 22 Jul 2025Source
Technical (Architect)
Technical (Engineer)
- DocumentForm 2 - Kuldeep.pdf · uploaded 21 Oct 2024Source
- DocumentForm 2 - Kuldeep.pdf · uploaded 3 Jan 2025Source
- DocumentForm 2 -Kuldeep_compressed.pdf · uploaded 29 Mar 2025Source
- DocumentForm 2 - Kuldeep_compressed.pdf · uploaded 19 Apr 2025Source
- DocumentWithdrawal Application Form2.pdf · uploaded 15 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 3, 4
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- Ex Mem Flat A 101, Ex Mem Flat A 104, Ex Mem Flat A 201, Ex Mem Flat A 202, Ex Mem Flat A 203, Ex Mem Flat A 204, Ex Mem Flat A 302, Ex Mem Flat A 303, Ex Mem Flat A 304, Ex Mem Flat A 402, Ex Mem Flat A 504, Ex Mem Flat A 602, Ex Mem Flat B 102, Ex Mem Flat B 103, Ex Mem Flat B 201, Ex Mem Flat B 202, Ex Mem Flat B 203, Ex Mem Flat B 204, Ex Mem Flat B 301, Ex Mem Flat B 302, Ex Mem Flat B 303, Ex Mem Flat B 304, Ex Mem Flat B 401, Ex Mem Flat B 402, Ex Mem Flat B 404, Sale Flat A 301, Sale Flat A 401, Sale Flat A 403, Sale Flat A 404, Sale Flat A 501, Sale Flat A 502, Sale Flat A 503, Sale Flat A 603, Sale Flat B 101, Sale Flat B 104, Sale Flat B 403, Sale Flat B 501, Sale Flat B 502, Sale Flat B 60139 units in all
- Address
- Plot No. 2, 3, 4, CTS No. 254, Sr. No. 41/5A+5B, Erandwane, Pune - 411004, Off Karveroad, Paud PhataPIN 411004
- Village
- Erandwane
- Land area for this project
- 1,756 sq m (18,900 sq ft)
- Permissible built-up area
- 3,960 sq m (42,621 sq ft)
- Sanctioned built-up area
- 3,753 sq m (40,397 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 190
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
Plot No. 2,3,4, CTS No. 254, Sr. No. 41/5A+5B, Erandwane, Pune - 411004
Boundaries
- North
- Buttepatil Complex
- South
- Internal Road named as Birmal Path
- East
- Plot No 01
- West
- Internal Road of HA Colony
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking39 units
32 of 39 units booked (82%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Ex Mem Flat A 101 | 79.52 sq m · 856 sq ft | 1 | 1 |
| Ex Mem Flat A 104 | 73.59 sq m · 792 sq ft | 1 | 1 |
| Ex Mem Flat A 201 | 85.39 sq m · 919 sq ft | 1 | 1 |
| Ex Mem Flat A 202 | 65.2 sq m · 702 sq ft | 1 | 1 |
| Ex Mem Flat A 203 | 42.34 sq m · 456 sq ft | 1 | 1 |
| Ex Mem Flat A 204 | 87.7 sq m · 944 sq ft | 1 | 1 |
| Ex Mem Flat A 302 | 67.09 sq m · 722 sq ft | 1 | 1 |
| Ex Mem Flat A 303 | 41.01 sq m · 441 sq ft | 1 | 1 |
Show all 39 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Ex Mem Flat A 304 | 83.12 sq m · 895 sq ft | 1 | 1 |
| Ex Mem Flat A 402 | 79.05 sq m · 851 sq ft | 1 | 1 |
| Ex Mem Flat A 504 | 77.44 sq m · 834 sq ft | 1 | 1 |
| Ex Mem Flat A 602 | 74.62 sq m · 803 sq ft | 1 | 1 |
| Ex Mem Flat B 102 | 30.58 sq m · 329 sq ft | 1 | 1 |
| Ex Mem Flat B 103 | 72.77 sq m · 783 sq ft | 1 | 1 |
| Ex Mem Flat B 201 | 84.93 sq m · 914 sq ft | 1 | 1 |
| Ex Mem Flat B 202 | 50.89 sq m · 548 sq ft | 1 | 1 |
| Ex Mem Flat B 203 | 70.6 sq m · 760 sq ft | 1 | 1 |
| Ex Mem Flat B 204 | 86.61 sq m · 932 sq ft | 1 | 1 |
| Ex Mem Flat B 301 | 76.16 sq m · 820 sq ft | 1 | 1 |
| Ex Mem Flat B 302 | 69.81 sq m · 751 sq ft | 1 | 1 |
| Ex Mem Flat B 303 | 81.04 sq m · 872 sq ft | 1 | 1 |
| Ex Mem Flat B 304 | 78.53 sq m · 845 sq ft | 1 | 1 |
| Ex Mem Flat B 401 | 83.25 sq m · 896 sq ft | 1 | 1 |
| Ex Mem Flat B 402 | 74.27 sq m · 799 sq ft | 1 | 1 |
| Ex Mem Flat B 404 | 86.81 sq m · 934 sq ft | 1 | 1 |
| Sale Flat A 301 | 81.63 sq m · 879 sq ft | 1 | 1 |
| Sale Flat A 401 | 87.81 sq m · 945 sq ft | 1 | 0 |
| Sale Flat A 403 | 43.5 sq m · 468 sq ft | 1 | 1 |
| Sale Flat A 404 | 55.09 sq m · 593 sq ft | 1 | 1 |
| Sale Flat A 501 | 83.19 sq m · 895 sq ft | 1 | 1 |
| Sale Flat A 502 | 72.49 sq m · 780 sq ft | 1 | 0 |
| Sale Flat A 503 | 27.85 sq m · 300 sq ft | 1 | 0 |
| Sale Flat A 603 | 60.06 sq m · 646 sq ft | 1 | 0 |
| Sale Flat B 101 | 60.37 sq m · 650 sq ft | 1 | 1 |
| Sale Flat B 104 | 60.06 sq m · 646 sq ft | 1 | 0 |
| Sale Flat B 403 | 25.47 sq m · 274 sq ft | 1 | 0 |
| Sale Flat B 501 | 59.12 sq m · 636 sq ft | 1 | 0 |
| Sale Flat B 502 | 92.09 sq m · 991 sq ft | 1 | 1 |
| Sale Flat B 601 | 60.26 sq m · 649 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Abhiram Mahadik | — |
| Architect | Sandeep Hardikar | — |
| Chartered accountant | Phule Wagh & Associates LLP | — |
| Engineer | Kulbhushan Annadate | — |
| Engineer | Madhav Joshi | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Erandwane
- MuktaRERA P52100079819
- Swojas EmeraldRERA P52100077931
- Soujanya Sahakari Griha Rachana Sanstha MaryaditRERA P52100077869
- SiddharthRERA P52100077732
- ChandrabhagaRERA P52100077614
- Snehabhavan Cooperative Housing Society LimitedRERA P52100077568
- Sweet Home Co-Operative Housing SocietyRERA P52100076987
- The Pleasant Co Op Housing Society LtdRERA P52100076724
All 10 projects in Erandwane · Compare Kuldeep with another project