RERA projects in Dongargaon

1 project under 1 MahaRERA registration, registered 2024–2024. 100% have a completion date extended beyond the one promised.

Locality
1RERA projects
1Registrations
1Completion still due0 past their completion date
4 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
29Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20241

Projects in Dongargaon

1 project registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
The DoorwaysMoon Valley Resorts LLPP5210007815825 Nov 202415 Dec 202815 Apr 2029Extended 4 mo0

Other localities in Mawal

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Moon Valley Resorts LLP1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology