Promised date passed6 floorsRERA P52100004067
D, sai avishkar
Deedo IDDP-PUN-D9GD-DMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked38%18 of 48 · MahaRERA
Completion30 Dec 2018as registered
Units & parking in D
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 32.4 m² (349 sq.ft) | 2 | 0 |
| 1 BHK | 32.6 m² (351 sq.ft) | 7 | 3 |
| 1 BHK | 32.8 m² (353 sq.ft) | 4 | 3 |
| 1 BHK | 32.8 m² (353 sq.ft) | 1 | 0 |
| 1 BHK | 32.8 m² (353 sq.ft) | 3 | 0 |
| 1 BHK | 32.8 m² (353 sq.ft) | 5 | 3 |
| 1 BHK | 32.9 m² (354 sq.ft) | 1 | 0 |
| 1 BHK | 33.3 m² (359 sq.ft) | 1 | 0 |
| RESIDENTIAL | 785.3 m² (8,453 sq.ft) | 24 | 9 |
As registered with MahaRERA
- RERA registration
- P52100004067 · registered 7 Aug 2017
- Promised completion
- 30 Dec 2018
- Revised completion
- 30 Dec 2018
- Sanctioned habitable floors
- 6
- Sanctioned floors (incl. basement, stilt, podium)
- 6
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-PUN-D9GD-D
Questions about D
When is D due for completion?
The MahaRERA registration promises 30 Dec 2018.
How many floors does D have?
6 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology