Amruta Vihar
Deedo IDDP-PUN-N6ZSCompletion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 45% of its units are booked.
Dhayari, Pune 411041 · Property rates in Dhayari · by Amruta Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2028
- This projectRegistered 9 May 2023, completion promised 31 Dec 2027, revised to 30 Apr 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100050831
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100050831 | 9 May 2023 | 31 Dec 2027 | 30 Apr 2028 | Amruta Developers | Project page |
Documents125
1 document held by Deedo, 124 filings listed on MahaRERA's project page
Finance
- PAN CardFIRM PAN.pdf · uploaded 3 Dec 2022Source
Legal
Show all 125 documentsShow fewer documents
Migrated
- 2 Copy of Layout Approval (in case of layout)PLAN3.pdf · uploaded 6 Dec 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERT.pdf · uploaded 6 Dec 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 6 Dec 2022Source
- 3 Copy of Layout Approval (in case of layout)PLAN.pdf · uploaded 29 Dec 2022Source
- 1 Copy of the legal title reportLEGALTITLE_REPORT.pdf · uploaded 31 Dec 2022Source
- 1 a Details of encumbrances concerned to FinanceDeclaration2 LEGAL ENCUMB.pdf · uploaded 31 Dec 2022Source
- 1 b Details of encumbrances concerned to LegalDeclaration2 LEGAL ENCUMB.pdf · uploaded 31 Dec 2022Source
- 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 31 Dec 2022Source
- 2 a Details of encumbrances concerned to FinanceDECLARATION ENCUMBRANCES.pdf · uploaded 2 Jan 2023Source
- 2 b Details of encumbrances concerned to LegalDECLARATION ENCUMBRANCES.pdf · uploaded 2 Jan 2023Source
- 1 CERSAI detailsDECLARATION ENCUMBRANCES.pdf · uploaded 2 Jan 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFORMAT A - BANK.pdf · uploaded 2 Jan 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsFORM A DALVI.pdf · uploaded 9 Jan 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsFORM A DALVI2.pdf · uploaded 9 Jan 2023Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsFORM A DEVI.pdf · uploaded 9 Jan 2023Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsFORM A LAIGUDE.pdf · uploaded 9 Jan 2023Source
- 5 Disclosure of Interest in Other Real Estate OrganizationsFORM A PAWAR.pdf · uploaded 9 Jan 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 13 Jan 2023Source
- 1 Deviation Report with respect to Allotment letterNO DEVIATION IN ALLOTMENT.pdf · uploaded 13 Jan 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentPLAN 2.pdf · uploaded 21 Jan 2023Source
- 2 Building Plan Approval / NA Order for plotted developmentPLAN 4.pdf · uploaded 21 Jan 2023Source
- 3 Building Plan Approval / NA Order for plotted developmentPLAN 5.pdf · uploaded 21 Jan 2023Source
- 1 Declaration about Commencement CertificateFORM D.pdf · uploaded 23 Jan 2023Source
- 4 Building Plan Approval / NA Order for plotted developmentCC-2098-22_dated_10-11-2022-05_compressed__1_ (1).pdf · uploaded 19 Feb 2023Source
- 5 Building Plan Approval / NA Order for plotted developmentCC-2098-22_dated_10-11-2022-03_compressed.pdf · uploaded 19 Feb 2023Source
- 1 Declaration in FORM BForm_B_-_Promoter.pdf · uploaded 19 Feb 2023Source
- 2 Declaration in FORM BForm_B_-_Co_Promoter.pdf · uploaded 19 Feb 2023Source
- 3 Declaration in FORM BForm_B_2nd_Co_Promoter.pdf · uploaded 19 Feb 2023Source
- 1 Proforma of Agreement for saleFinal Agreement.pdf · uploaded 11 Mar 2023Source
- 1 Deviation Report with respect to model copy of AgreementNO_DEVIATION_IN_AGREEMENT.pdf · uploaded 11 Mar 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form_no-01_Archtech_Certificate.pdf · uploaded 18 Sep 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eiginners_Certificate__Form_-02.pdf · uploaded 18 Sep 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_Certificate_Form-03.pdf · uploaded 18 Sep 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5.pdf · uploaded 18 Sep 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM_-01.pdf · uploaded 13 Feb 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-02.pdf · uploaded 13 Feb 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-03_compressed.pdf · uploaded 13 Feb 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate.pdf · uploaded 29 May 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 29 May 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form-2A.pdf · uploaded 29 May 2024Source
- 1 Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory.pdf · uploaded 29 May 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 29 May 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Audit Report.pdf · uploaded 29 May 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 Architech Certificate.pdf · uploaded 7 Aug 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineers certificate Form-02.pdf · uploaded 7 Aug 2024Source
- 2 Disclosure of sold/ booked inventoryDisclosure Of Sold Booked Inventory (1).pdf · uploaded 7 Aug 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)form-03 CA Certificate - converted (1).pdf · uploaded 7 Aug 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 Architech Certificate.pdf · uploaded 22 Nov 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Cert.pdf · uploaded 22 Nov 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-02 Engineer Certificate.pdf · uploaded 22 Nov 2024Source
- 2 Disclosure of sold/ booked inventoryDisclosure Of Sold Booked Inventroy.pdf · uploaded 22 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 Architech Certificate.pdf · uploaded 17 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-03 CA Certificate_compressed.pdf · uploaded 17 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-02 Engineer Certificater.pdf · uploaded 17 Feb 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure of Sold Booked Inventory-1.pdf · uploaded 17 Feb 2025Source
- Form 1Form-01.pdf · uploaded 18 Jul 2025Source
- Form 2Form- 2 March 25.pdf · uploaded 18 Jul 2025Source
- Form 3Form-03 .pdf · uploaded 18 Jul 2025Source
- Disclosure of Sold and Booked InventoryDisclosuer Of Sold Inventrory - March 25.pdf · uploaded 18 Jul 2025Source
- Form 1AR certificate.pdf · uploaded 6 Aug 2025Source
- Form 2ER certificate.pdf · uploaded 6 Aug 2025Source
- Form 3CA certificate.pdf · uploaded 6 Aug 2025Source
- Disclosure of Sold and Booked InventoryDisclosure - June 25.pdf · uploaded 6 Aug 2025Source
- Form 1Architect June 24.pdf · uploaded 29 Sep 2025Source
- Form 2Engineer June 24.pdf · uploaded 29 Sep 2025Source
- Form 3CA Certificate June 24.pdf · uploaded 29 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure June 24.pdf · uploaded 29 Sep 2025Source
- Form 1Architect Dec 24.pdf · uploaded 29 Sep 2025Source
- Form 2Engineer Dec 24.pdf · uploaded 29 Sep 2025Source
- Form 3CA Certificate Dec 24.pdf · uploaded 29 Sep 2025Source
- Disclosure of Sold and Booked InventoryDisclosure Dec 24.pdf · uploaded 29 Sep 2025Source
- Form 5 (FY 2023-2024)RERA Audit Report 23-24.pdf · uploaded 29 Sep 2025Source
- Withdrawal Update Form 1form 1 dhayri 132 30-09-2025.pdf · uploaded 5 Nov 2025Source
- Withdrawal Update Form 2From 2.pdf · uploaded 5 Nov 2025Source
- Withdrawal Update Form 3CA - sept 25.pdf · uploaded 5 Nov 2025Source
- Form 1AR - sept 24.pdf · uploaded 6 Nov 2025Source
- Form 2ER - sept 24.pdf · uploaded 6 Nov 2025Source
- Form 3CA Certificate sept 24.pdf · uploaded 6 Nov 2025Source
- Disclosure of Sold and Booked InventoryDisclosure - sept 24.pdf · uploaded 6 Nov 2025Source
- Form 1Architect Mar 24.pdf · uploaded 6 Nov 2025Source
- Form 2Engineer Mar 24.pdf · uploaded 6 Nov 2025Source
- Form 3CA Certificate Mar 24.pdf · uploaded 6 Nov 2025Source
- Disclosure of Sold and Booked InventoryDisclosure Mar 24.pdf · uploaded 6 Nov 2025Source
- Form 2A (FY 2023-2024)Form 2A - March 24.pdf · uploaded 6 Nov 2025Source
- Form 2A (FY 2024-2025)Form 2A - March 25.pdf · uploaded 6 Nov 2025Source
- Withdrawal Update Form 1AR -.pdf · uploaded 31 Jan 2026Source
- Withdrawal Update Form 2ER - .pdf · uploaded 31 Jan 2026Source
- Withdrawal Update Form 3Form 3.pdf · uploaded 31 Jan 2026Source
- Withdrawal Update Form 1AR.pdf · uploaded 24 Apr 2026Source
- Withdrawal Update Form 2ER .pdf · uploaded 24 Apr 2026Source
- Withdrawal Update Form 3Form-03 Final_2.pdf · uploaded 24 Apr 2026Source
- Withdrawal Update Form 1AR - June 26 .pdf · uploaded 23 Jul 2026Source
- Withdrawal Update Form 2ER - June 26 .pdf · uploaded 23 Jul 2026Source
- Withdrawal Update Form 3CA-June-26_.pdf · uploaded 23 Jul 2026Source
- Form 5 (FY 2025-2026)RA Report 25-26 .pdf · uploaded 19 Sep 2026Source
Technical
- DocumentPLAN1.pdf · uploaded 6 Dec 2022Source
- DocumentPLAN3.pdf · uploaded 6 Dec 2022Source
- DocumentPLAN.pdf · uploaded 29 Dec 2022Source
- DocumentPLAN 2.pdf · uploaded 21 Jan 2023Source
- DocumentPLAN 4.pdf · uploaded 21 Jan 2023Source
- DocumentPLAN 5.pdf · uploaded 21 Jan 2023Source
- DocumentCC-2098-22_dated_10-11-2022-05_compressed__1_ (1).pdf · uploaded 19 Feb 2023Source
- DocumentCC-2098-22_dated_10-11-2022-03_compressed.pdf · uploaded 19 Feb 2023Source
- OthersFormat-D-Amruta Developers.pdf · uploaded 16 Nov 2025Source
- OthersLetter to RERA-Amruta Developers.pdf · uploaded 16 Nov 2025Source
- Document1.pdf · uploaded 22 Nov 2025Source
- Document2.pdf · uploaded 22 Nov 2025Source
- Document3.pdf · uploaded 22 Nov 2025Source
- Document4.pdf · uploaded 22 Nov 2025Source
- Document5.pdf · uploaded 22 Nov 2025Source
- DocumentBuilding Plan No 6.pdf · uploaded 21 Dec 2025Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel S No. 132/1/1A (P)
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Office space, Shop117 units in all
- Address
- S No 132/1/1a, Sinhagad Road, Dsk Vishwa Nanded RoadPIN 411041
- Village
- Dhayari (Part), Haveli taluka
- Location
- 18.45032, 73.79864
- Land area for this project
- 3,500 sq m (37,674 sq ft)
- Permissible built-up area
- 10,691 sq m (1,15,076 sq ft)
- Sanctioned built-up area
- 10,691 sq m (1,15,073 sq ft)
- Recreational open space
- 269 sq m (2,893 sq ft)
- Designated bank account
- 220
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S No. 132/1/1A (P)
Boundaries
- North
- Bharat Dalvi Property
- South
- Common Appraoch Road In The S No
- East
- Sagar Suresh Dalvi
- West
- Indrajeet Dalvi And Others
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking117 units
53 of 117 units booked (45%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 42.53 sq m · 458 sq ft | 7 | 7 |
| 1BHK | 42.65 sq m · 459 sq ft | 7 | 2 |
| 1BHK | 44.85 sq m · 483 sq ft | 14 | 4 |
| 2BHK | 59.13 sq m · 636 sq ft | 7 | 4 |
| 2BHK | 59.19 sq m · 637 sq ft | 7 | 4 |
| 2BHK | 59.21 sq m · 637 sq ft | 14 | 6 |
| 2BHK | 70.94 sq m · 764 sq ft | 7 | 6 |
| 2BHK | 71.06 sq m · 765 sq ft | 7 | 6 |
Show all 32 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 76.14 sq m · 820 sq ft | 7 | 3 |
| 2BHK | 76.25 sq m · 821 sq ft | 7 | 4 |
| Office space | 12.57 sq m · 135 sq ft | 2 | 0 |
| Office space | 13.12 sq m · 141 sq ft | 1 | 0 |
| Office space | 13.21 sq m · 142 sq ft | 2 | 0 |
| Office space | 13.32 sq m · 143 sq ft | 1 | 0 |
| Office space | 14.99 sq m · 161 sq ft | 2 | 0 |
| Office space | 16.2 sq m · 174 sq ft | 1 | 0 |
| Office space | 16.38 sq m · 176 sq ft | 1 | 0 |
| Office space | 16.87 sq m · 182 sq ft | 1 | 0 |
| Office space | 16.95 sq m · 182 sq ft | 2 | 0 |
| Office space | 17.01 sq m · 183 sq ft | 2 | 0 |
| Office space | 17.23 sq m · 185 sq ft | 2 | 0 |
| Shop | 9.66 sq m · 104 sq ft | 2 | 1 |
| Shop | 13.46 sq m · 145 sq ft | 1 | 0 |
| Shop | 13.56 sq m · 146 sq ft | 2 | 0 |
| Shop | 13.66 sq m · 147 sq ft | 1 | 0 |
| Shop | 15.38 sq m · 166 sq ft | 2 | 2 |
| Shop | 16.61 sq m · 179 sq ft | 1 | 1 |
| Shop | 16.82 sq m · 181 sq ft | 1 | 1 |
| Shop | 17.08 sq m · 184 sq ft | 1 | 0 |
| Shop | 17.28 sq m · 186 sq ft | 1 | 0 |
| Shop | 17.44 sq m · 188 sq ft | 2 | 1 |
| Shop | 17.69 sq m · 190 sq ft | 2 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals11
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Architects Eye | — |
| Architect | Nitin Ausekar | — |
| Chartered accountant | CA Joshi and Associates | — |
| Chartered accountant | CA MS Joshi and associates | — |
| Chartered accountant | Joshi and Raykar | — |
| Engineer | Ajay Mohan Chalke | — |
| Engineer | Amol Nanaso Kumbhar | — |
| Engineer | Atul Suresh Laigude | — |
Show all 11 professionalsShow fewer professionals
| Role | Name | Registration no. |
|---|---|---|
| Engineer | Shankar Digamber Bade | — |
| Other | Amol Kumbhar | — |
| Other | Shiv Shambho Enterprises | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Dhayari
- Navale PramocrestRERA PR1260002602333
- Akshay VistaraRERA PR1260002602243
- Kumar ProsperRERA PC1260002602074
- Shriram VandanRERA PM1260002601459
- Laxmi ElanzaRERA PR1261012600965
- Rahi LegacyRERA PR1260002600582
- Bramhand OneRERA PR1260002600301
- NHC OneRERA PR1260002600087
All 115 projects in Dhayari · Compare Amruta Vihar with another project