Extended 12 mo9 floorsRERA P52100023073
B, Gulmohar Park
Deedo IDDP-PUN-JFE1-BMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Completion29 Dec 202430 Dec 2023 · revised
Units & parking in B
MahaRERA's project page with unit types hasn't been imported for this registration.
As registered with MahaRERA
- RERA registration
- P52100023073 · registered 22 Nov 2019
- Promised completion
- 30 Dec 2023
- Revised completion
- 29 Dec 2024
- Sanctioned habitable floors
- 9
- Sanctioned floors (incl. basement, stilt, podium)
- 9
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-PUN-JFE1-B
Questions about B
When is B due for completion?
The MahaRERA registration promises 30 Dec 2023, revised to 29 Dec 2024.
How many floors does B have?
9 sanctioned habitable floors, as registered with MahaRERA.
SourcesMahaRERA registration · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology