Residential / Group Housing · 13 buildings · 219 unitsRERA P52100027134

Swara Blossom

Deedo IDDP-PUN-4NSZ

Completion was pushed back 4 months, to Oct 2028; no MahaRERA orders on record; 86% of its units are booked.

Chinchwad, Pune 411062 · Property rates in Chinchwad · by Blue Sapphire Vastu Nirmitee Llp

DeliveryExtended 4 moPromised Jun 2028 · now due Oct 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales86% booked188 of 219 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Oct 2028

  • This projectRegistered 19 Nov 2020, completion promised 30 Jun 2028, revised to 30 Oct 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

  • Resale · Mar 2026
Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Mar 2026Wing F · 801Resale476 sq ftView Resale, Mar 2026

13 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100027134
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210002713419 Nov 202030 Jun 202830 Oct 2028Blue Sapphire Vastu Nirmitee LLPProject page
Documents131

37 documents held by Deedo, 94 filings listed on MahaRERA's project page

Building plan (3)

Title report

Commencement certificate

Registration certificate

Form B

Form 2A (3)

Show all 131 documentsShow fewer documents

Form 2A (3)

Other (12)

Encumbrance details

Form 5

Allotment letter (2)

Form 2 (3)

Form 1 (8)

Document library

  • Details of encumbrancesletter 123-converted.pdf · uploaded 8 Jun 2020View
  • Copy of Layout Approval (in case of layout)Layout plan.pdf · uploaded 8 Jun 2020View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate1.pdf · uploaded 8 Jun 2020View
  • Declaration in FORM Bfrom B.pdf · uploaded 8 Jun 2020View
  • Declaration in FORM Bfrom b 1.pdf · uploaded 8 Jun 2020View
  • Proforma of Allotment letterDRAFT AGREEMENT - SWARA BLOSSOM.pdf · uploaded 17 Sep 2020View
  • Building Plan Approval / NA Order for plotted developmentNA order-compressed.pdf · uploaded 17 Sep 2020View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECH CERTIFICATE.pdf · uploaded 12 Nov 2020View
  • Copy of the legal title reportSEARCH REPORT.pdf · uploaded 13 Nov 2020View
  • Commencement Certificates / NA Order for plotted developmentNEW COMMENCEMENT CERTIFICATE.pdf · uploaded 16 Apr 2021View
  • Copy of Layout Approval (in case of layout)HPSC0583.pdf · uploaded 16 Apr 2021View
  • Building Plan Approval / NA Order for plotted developmentHPSC0584.pdf · uploaded 16 Apr 2021View
  • Building Plan Approval / NA Order for plotted developmentHPSC0585.pdf · uploaded 16 Apr 2021View
  • Building Plan Approval / NA Order for plotted developmentHPSC0586.pdf · uploaded 16 Apr 2021View
  • Building Plan Approval / NA Order for plotted developmentHPSC0587.pdf · uploaded 16 Apr 2021View
  • Building Plan Approval / NA Order for plotted developmentHPSC0588.pdf · uploaded 16 Apr 2021View
  • Building Plan Approval / NA Order for plotted developmentHPSC0589.pdf · uploaded 16 Apr 2021View
  • Building Plan Approval / NA Order for plotted developmentHPSC0590.pdf · uploaded 16 Apr 2021View
  • Building Plan Approval / NA Order for plotted developmentHPSC0591.pdf · uploaded 16 Apr 2021View
  • Building Plan Approval / NA Order for plotted developmentHPSC0592.pdf · uploaded 16 Apr 2021View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Signed Form 5_compressed.pdf · uploaded 9 Mar 2022View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 5 Scan.pdf · uploaded 25 Jan 2023View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) .pdf · uploaded 16 Dec 2023View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1- Architect Certificate_11zon.pdf · uploaded 27 Feb 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form - 2 Engineers Certificate .pdf · uploaded 27 Feb 2024View
  • Disclosure of sold/ booked inventoryUpdated Disclosure of Sold unsold Inventory_11zon.pdf · uploaded 27 Feb 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsAnnexure A- Mahesh Yelmar.pdf · uploaded 27 Feb 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsAnnexure A- Tanaji Phand.pdf · uploaded 27 Feb 2024View
  • a Details of encumbrances concerned to Finance1 Details of encumbrances (1).pdf · uploaded 18 Mar 2024View
  • b Details of encumbrances concerned to Legal1 Details of encumbrances (1).pdf · uploaded 18 Mar 2024View
  • Proforma of Agreement for sale1 Proforma of Allotment letter.pdf · uploaded 18 Mar 2024View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5.pdf · uploaded 18 Mar 2024View
  • Deviation Report with respect to Allotment letterDeviation report.pdf · uploaded 18 Mar 2024View
  • Deviation Report with respect to model copy of AgreementDeviation report.pdf · uploaded 18 Mar 2024View
  • CERSAI details1 Details of encumbrances (1).pdf · uploaded 18 Mar 2024View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A- Bank Account declaration.pdf · uploaded 18 Mar 2024View
  • Declaration about Commencement CertificateDeclaration about commencement Certificate.pdf · uploaded 25 Mar 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A 20-21.pdf · uploaded 25 Mar 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A 21-22.pdf · uploaded 25 Mar 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A 22-23.pdf · uploaded 25 Mar 2024View
  • Form 1Form 1 June 25.pdf · uploaded 29 Jul 2025View
  • Form 2Form 2 June 25.pdf · uploaded 29 Jul 2025View
  • Disclosure of Sold and Booked InventoryDisclosure Of Sold & Unsold Inventory.pdf · uploaded 29 Jul 2025View
  • Self-declaration of Quarterly ProgressQPR Self Declaration.pdf · uploaded 29 Jul 2025View
  • Form 1Form 1 March 25.pdf · uploaded 29 Jul 2025View
  • Form 2Form 2 March 25.pdf · uploaded 29 Jul 2025View
  • Disclosure of Sold and Booked InventoryDisclosure of Sold & Unsold Inventory.pdf · uploaded 29 Jul 2025View
  • Self-declaration of Quarterly ProgressQPR Self Declaration.pdf · uploaded 29 Jul 2025View
  • Form 1Form 1_Dec 24.pdf · uploaded 29 Jul 2025View
  • Form 2Form 2 Dec 24.pdf · uploaded 29 Jul 2025View
  • Disclosure of Sold and Booked InventoryDisclosure of Sold & Unsold Inventory.pdf · uploaded 29 Jul 2025View
  • Self-declaration of Quarterly ProgressQPR Self Declaration.pdf · uploaded 29 Jul 2025View
  • Form 1Form 1 Sept 24.pdf · uploaded 29 Jul 2025View
  • Form 2Form 2 Sept 24.pdf · uploaded 29 Jul 2025View
  • Disclosure of Sold and Booked InventoryDisclosure of Sold & Unsold Inventory.pdf · uploaded 29 Jul 2025View
  • Self-declaration of Quarterly ProgressQPR Self Declaration.pdf · uploaded 29 Jul 2025View
  • Form 1Form 1 June 24.pdf · uploaded 29 Jul 2025View
  • Form 2Form 2 June 24.pdf · uploaded 29 Jul 2025View
  • Disclosure of Sold and Booked InventoryDisclosure of Sold & Unsold Inventory.pdf · uploaded 29 Jul 2025View
  • Self-declaration of Quarterly ProgressQPR Self Declaration.pdf · uploaded 29 Jul 2025View
  • Form 5 (FY 2023-2024)FORM 5 FY_23-24.pdf · uploaded 31 Jul 2025View
  • Form 5 (FY 2024-2025)FORM 5 FY_24-25.pdf · uploaded 31 Jul 2025Source
  • Form 2A (FY 2023-2024)Form 2A 23-24.pdf · uploaded 31 Jul 2025View
  • Form 2A (FY 2024-2025)Form 2A 24-25.pdf · uploaded 31 Jul 2025View
  • Form 1Architect Certificate Q2.pdf · uploaded 12 Jan 2026View
  • Form 2Engineer Certificate F2 Q2.pdf · uploaded 12 Jan 2026View
  • Disclosure of Sold and Booked InventoryFY 2025-26 Q2 (1).pdf · uploaded 12 Jan 2026View
  • Self-declaration of Quarterly ProgressDeclaration by promoter_Q2.pdf · uploaded 12 Jan 2026View
  • Form 1Architect Certificate Q3.pdf · uploaded 12 Jan 2026View
  • Form 2Engineer Certificate F2 Q3.pdf · uploaded 12 Jan 2026View
  • Disclosure of Sold and Booked InventoryFY 2025-26 Q3_compressed.pdf · uploaded 12 Jan 2026View
  • Self-declaration of Quarterly ProgressDeclaration By Promoter_Q3.pdf · uploaded 12 Jan 2026View
  • Form 1Architect Certificate.pdf · uploaded 24 Apr 2026View
  • Form 2Engineer Certificate.pdf · uploaded 24 Apr 2026View
  • Disclosure of Sold and Booked InventoryDisclosure of sold with Sign.pdf · uploaded 24 Apr 2026View
  • Form 1Architect Certificate (2).pdf · uploaded 18 Jul 2026View
  • Form 2Engineer Certificate (2).pdf · uploaded 18 Jul 2026View
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory.pdf · uploaded 18 Jul 2026View

Promoter documents

  • Declaration Form Bfrom B.pdf · uploaded 8 Jun 2020View
  • Declaration Form Bfrom b 1.pdf · uploaded 8 Jun 2020View
  • Legal Title reportSEARCH REPORT.pdf · uploaded 13 Nov 2020View

Technical documents

  • Layout ApprovalLayout plan.pdfView
  • Layout ApprovalHPSC0583.pdfView
  • Building Plan ApprovalNA order-compressed.pdfView
  • Building Plan ApprovalHPSC0584.pdfView
  • Building Plan ApprovalHPSC0585.pdfView
  • Building Plan ApprovalHPSC0586.pdfView
  • Building Plan ApprovalHPSC0587.pdfView
  • Building Plan ApprovalHPSC0588.pdfView
  • Building Plan ApprovalHPSC0589.pdfView
  • Building Plan ApprovalHPSC0590.pdfView
  • Building Plan ApprovalHPSC0591.pdfView
  • Building Plan ApprovalHPSC0592.pdfView

Proforma allotment letter

  • Proforma allotment letterDRAFT AGREEMENT - SWARA BLOSSOM.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 989, 990 · PMRDA

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Active
Address
989, 990, Chikhali Goan, Haveli TalukaPIN 411062
Land area for this project
6,536 sq m (70,350 sq ft)
Permissible built-up area
22,467 sq m (2,41,833 sq ft)
Sanctioned built-up area
5,467 sq m (58,846 sq ft)
Planning authority
PMRDA
Designated bank account
Icici Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Survey, CTS, gat or plot numbers

989990

Land as published on MahaRERA's project page

989, 990

Boundaries

North
Gat No 988
South
Gat No 992
East
Gat No 991
West
By Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking324 parking spaces

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Wing AClosed/Covered000054
Wing AOpen Space00000
Wing BClosed/Covered000054
Wing BOpen Space00000
Wing CClosed/Covered000054
Wing COpen Space00000
Wing DClosed/Covered000054
Wing DOpen Space00000
Show all 12 parking rowsShow fewer parking rows
BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Wing EClosed/Covered000054
Wing EOpen Space00000
Wing FClosed/Covered000054
Wing FOpen Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress7 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

Wing A

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Wing B

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Wing C

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure7%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Show all 7 buildings and common areasShow fewer buildings and common areas

Wing D

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure20%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Wing E

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
  • Sanitary Fittings within the flats / premises10%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Wing F

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
  • Sanitary Fittings within the flats / premises20%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water Supply0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)0%
  • Storm Water Drains0%
  • Landscaping & Tree Planting0%
  • Street Lighting0%
Show all 15 activitiesShow fewer activities
  • Community Buildings0%
  • Treatment And Disposal Of Sewage And Sullage Water0%
  • Solid Waste Management And Disposal0%
  • Water conservation /Rain water harvesting0%
  • Energy managemcnt0%
  • Fire protection and fire safety requirements0%
  • Electrical meter room, sub-station, receiving station0%
  • Aggregate area of recreational Open Space0%
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectUsha Rangarajan—
Chartered accountantAghav Wavhal & Associates—
Chartered accountantSachin Gogave & Co LLP—
EngineerAjay Bhilare—
EngineerVaijnath Jadhav—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Chinchwad

All 13 projects in Chinchwad · Compare Swara Blossom with another project

Swara Blossom in numbers

Registered deals, summarised

Deedo has 1 registered document at Swara Blossom, from Mar 2026 to Mar 2026: 1 sale.

How many properties have been sold at Swara Blossom?
1 sale is registered at Swara Blossom, 1 of them a resale.
Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Swara Blossom by Deedo, last updated with deals registered in Mar 2026.

Latest deal · Resale · Mar 2026

₹25–50 L