Extended 12 mo10 floorsRERA P52100021588
A, Ved Aashritha Phase II
Deedo IDDP-PUN-8XM1-AMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked38%6 of 16 · MahaRERA
Completion24 Apr 202425 Apr 2023 · revised
Units & parking in A
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 40.3 m² (434 sq.ft) | 1 | 1 |
| 1 BHK | 45.1 m² (486 sq.ft) | 2 | 1 |
| 2 BHK | 57.6 m² (620 sq.ft) | 1 | 0 |
| 2 BHK | 57.6 m² (620 sq.ft) | 1 | 0 |
| 2 BHK | 57.6 m² (620 sq.ft) | 1 | 0 |
| 2 BHK | 58.3 m² (628 sq.ft) | 1 | 0 |
| 2 BHK | 59.6 m² (641 sq.ft) | 1 | 0 |
| 2 BHK | 59.7 m² (643 sq.ft) | 1 | 0 |
| 2 BHK | 59.8 m² (643 sq.ft) | 1 | 1 |
| 2 BHK | 59.9 m² (645 sq.ft) | 1 | 1 |
| 2 BHK | 63.7 m² (685 sq.ft) | 1 | 1 |
| 2 BHK | 65.4 m² (703 sq.ft) | 1 | 0 |
| 2 BHK | 65.7 m² (707 sq.ft) | 1 | 1 |
| 2 BHK | 67.2 m² (723 sq.ft) | 1 | 0 |
| 2 BHK | 68.6 m² (739 sq.ft) | 1 | 0 |
As registered with MahaRERA
- RERA registration
- P52100021588 · registered 9 Jul 2019
- Promised completion
- 25 Apr 2023
- Revised completion
- 24 Apr 2024
- Sanctioned habitable floors
- 10
- Sanctioned floors (incl. basement, stilt, podium)
- 10
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-PUN-8XM1-A
Questions about A
When is A due for completion?
The MahaRERA registration promises 25 Apr 2023, revised to 24 Apr 2024.
How many floors does A have?
10 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology