Others · 2 buildings · 42 unitsRERA P52100079260

Sky Marina

Deedo IDDP-PUN-2V5R

Completion was pushed back 4 months, to Oct 2028; no MahaRERA orders on record.

Chikhali, Pune 411062 · Property rates in Chikhali · by Sai Vaastu Buildcon

DeliveryExtended 4 moPromised Jun 2028 · now due Oct 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readPrice₹7,320 /sq ft10.3% above Chikhali · 36 registered sales

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Oct 2028

  • This projectRegistered 25 Feb 2025, completion promised 30 Jun 2028, revised to 30 Oct 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

All 38 deeds →
Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Oct 2026Main building · 804Primary sale858 sq ftView Primary sale, Oct 2026
Oct 2026Main building · 204Primary sale858 sq ftView Primary sale, Oct 2026
Oct 2026Main building · 706Primary sale846 sq ftView Primary sale, Oct 2026
Sep 2026Sky Marina · 904Primary sale858 sq ftView Primary sale, Sep 2026
Sep 2026Sky Marina · 803Primary sale853 sq ftView Primary sale, Sep 2026
Sep 2026Sky Marina · 802Primary sale826 sq ftView Primary sale, Sep 2026
Jul 2026Sky Marina · 502Primary sale826 sq ftView Primary sale, Jul 2026
Jul 2026Sky Marina · 503Primary sale853 sq ftView Primary sale, Jul 2026
Jun 2026Sky Marina · 501Primary sale836 sq ftView Primary sale, Jun 2026
Jun 2026Sky Marina · 708Primary sale496 sq ftView Primary sale, Jun 2026

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100079260
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210007926025 Feb 202530 Jun 202830 Oct 2028Sai Vaastu BuildconProject page
Documents72

1 document held by Deedo, 71 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Card0 Firm Pan Card.pdf · uploaded 31 Jan 2025Source
  • Other – Financeself declaration 3 rera account - converted.pdf · uploaded 12 Feb 2025Source

Legal

  • Other – LegalPartnership Deed - converted.pdf · uploaded 31 Jan 2025Source
  • Legal Title reportSEARCH REPORT - converted.pdf · uploaded 31 Jan 2025Source
  • Declaration Form BForm B of Developer.pdf · uploaded 31 Jan 2025Source

Migrated

  • 1 PAN Card0 Firm Pan Card.pdf · uploaded 31 Jan 2025Source
  • 1 Copy of the legal title reportSEARCH REPORT - converted.pdf · uploaded 31 Jan 2025Source
Show all 72 documentsShow fewer documents

Migrated

  • 1 a Details of encumbrances concerned to FinanceDetails of encumbrances concerned to Finance.pdf · uploaded 31 Jan 2025Source
  • 1 Copy of Layout Approval (in case of layout)Sanctioned Plan Final-1_compressed.pdf · uploaded 31 Jan 2025Source
  • 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 31 Jan 2025Source
  • 1 Declaration in FORM BForm B of Developer.pdf · uploaded 31 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)DREAM SPACE ARCHITECTS CERTIFICATE24012025.pdf · uploaded 31 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 02.pdf · uploaded 31 Jan 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 31 Jan 2025Source
  • 4 Building Plan Approval / NA Order for plotted developmentSanctioned Plan Final-4_compressed.pdf · uploaded 31 Jan 2025Source
  • 3 Building Plan Approval / NA Order for plotted developmentSanctioned Plan Final-3_compressed.pdf · uploaded 31 Jan 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentSanctioned Plan Final-2_compressed.pdf · uploaded 31 Jan 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentSanctioned Plan Final-1_compressed.pdf · uploaded 31 Jan 2025Source
  • 1 Other – LegalPartnership Deed - converted.pdf · uploaded 31 Jan 2025Source
  • 1 Declaration about Commencement CertificateForm D.pdf · uploaded 31 Jan 2025Source
  • 1 CERSAI detailsDeclaration-Nil-CERSAI Report.pdf · uploaded 31 Jan 2025Source
  • 1 Deviation Report with respect to Allotment letterDeviation of Allotment Letter.pdf · uploaded 31 Jan 2025Source
  • 1 b Details of encumbrances concerned to LegalDetails of encumbrances concerned to Finance.pdf · uploaded 31 Jan 2025Source
  • 1 Other – TechnicalDeclaration of One Plot One Registration.pdf · uploaded 31 Jan 2025Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation for AFS.pdf · uploaded 31 Jan 2025Source
  • 1 Proforma of Agreement for saleRERA DRAFT 25 10 2025.pdf · uploaded 31 Jan 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations.pdf · uploaded 31 Jan 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDisclosure for securedunsecured.pdf · uploaded 31 Jan 2025Source
  • 1 Other – Financeself declaration 3 rera account - converted.pdf · uploaded 12 Feb 2025Source
  • 2 a Details of encumbrances concerned to FinanceDetails of encumbrances concerned to Legal.pdf · uploaded 18 Feb 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A.pdf · uploaded 18 Feb 2025Source
  • 2 b Details of encumbrances concerned to LegalDetails of encumbrances concerned to Legal.pdf · uploaded 18 Feb 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B.pdf · uploaded 18 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Final.pdf · uploaded 19 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERIFICATE FORM-103042025.pdf · uploaded 26 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)SARVASIDDHANT STRUCTURAL.pdf · uploaded 26 Apr 2025Source
  • Form 1FORM-1 ARCHITECTS CERTIFICATE 31 MARCH 202518072025.pdf · uploaded 21 Jul 2025Source
  • Form 2FORM-2 ENGINEERS CERTIFICATE 18 APRIL 202518072025.pdf · uploaded 21 Jul 2025Source
  • Form 3FORM-3 CA CERTIFICATE 17 JUNE 2025 (31 MARCH)18072025.pdf · uploaded 21 Jul 2025Source
  • Disclosure of Sold and Booked InventoryCA SHEET-1 LANDOWNER FLAT 9TH FLOOR TAK21072025.pdf · uploaded 21 Jul 2025Source
  • Withdrawal Update Form 1FORM-1 ARCHITECTS CERTIFICATE 30 JUNE 202518072025.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 1ARCHITECTS CERTIFICATE 30 SEP 202527112025.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 1ARCHITECTS CERTIFICATE 30 SEP 202527112025.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 2FORM-2 ENGINEERS CERTIFICATE 12 JULY 202518072025.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 2FORM-2 ENGINEERS CERTIFICATE 30 SEP 2025.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 2FORM-2 ENGINEERS CERTIFICATE 30 SEP 2025.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 3FORM-3 CA CERTIFICATE 15 JULY 202518072025.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 3FORM-3 CA CERTIFICATE 15 OC 202527112025.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 3FORM-3 CA CERTIFICATE 15 OC 202527112025.pdf · uploaded 27 Nov 2025Source
  • Form 5 (FY 2024-2025)AUDITOR REPORT 25 FEB TO 31 MARCH-202527112025.pdf · uploaded 27 Nov 2025Source
  • Withdrawal Update Form 1ARCHITECT CERTIFICATE FORM1 31 DEC 202522012026.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 2FORM-2 ENGINEER CERTIFICATE 22 JAN 202622012026.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 3FORM-3 CA CERTIFICATE 17 JAN 202623012026.pdf · uploaded 23 Jan 2026Source
  • Withdrawal Update Form 1ARHITECT CERTIFICATE 31 MARCH-2609042026.pdf · uploaded 19 Apr 2026Source
  • Withdrawal Update Form 2FORM-2 ENGINEER CERTIFICATE 08 MARCH-2609042026.pdf · uploaded 19 Apr 2026Source
  • Withdrawal Update Form 3FORM-3 CA CERTIFICATE 10 APRIL2026.pdf · uploaded 19 Apr 2026Source

Technical

  • DocumentSanctioned Plan Final-1_compressed.pdf · uploaded 31 Jan 2025Source
  • DocumentSanctioned Plan Final-1_compressed.pdf · uploaded 31 Jan 2025Source
  • DocumentSanctioned Plan Final-2_compressed.pdf · uploaded 31 Jan 2025Source
  • DocumentSanctioned Plan Final-3_compressed.pdf · uploaded 31 Jan 2025Source
  • DocumentSanctioned Plan Final-4_compressed.pdf · uploaded 31 Jan 2025Source
  • Other – TechnicalDeclaration of One Plot One Registration.pdf · uploaded 31 Jan 2025Source
  • DocumentPLAN COPY-1_11zon.pdf · uploaded 5 Jul 2025Source
  • DocumentPLAN COPY-1_11zon.pdf · uploaded 5 Jul 2025Source
  • DocumentPLAN COPY-2.pdf · uploaded 5 Jul 2025Source
  • DocumentPLAN COPY-3_11zon.pdf · uploaded 5 Jul 2025Source
  • DocumentPLAN COPY-4.pdf · uploaded 5 Jul 2025Source

Technical (Architect)

  • DocumentARCHITECT CERIFICATE FORM-103042025.pdf · uploaded 26 Apr 2025Source
  • DocumentARHITECT CERTIFICATE 31 MARCH-2609042026.pdf · uploaded 19 Apr 2026Source

Technical (Engineer)

  • DocumentSARVASIDDHANT STRUCTURAL.pdf · uploaded 26 Apr 2025Source
  • DocumentFORM-2 ENGINEER CERTIFICATE 08 MARCH-2609042026.pdf · uploaded 19 Apr 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Gat No. 63

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
—42 units in all
Address
Gat No. 63, Village Chikhali, Taluka Haveli, District Pune 411062, Dehu Alandi Road, Near Indian Oil Petrol PumpPIN 411062
Village
Chikhali, Haveli taluka
Land area for this project
4,500 sq m (48,438 sq ft)
Permissible built-up area
17,000 sq m (1,82,986 sq ft)
Sanctioned built-up area
4,180 sq m (44,995 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
86
Developed in phases
No
Also registered as
Skay Marina, स्काय मरिना

Survey, CTS, gat or plot numbers

Gat No. 63

Land as published on MahaRERA's project page

Gat No. 63, Village Chikhali, Taluka Haveli, District Pune 411062

Boundaries

North
24 Meters Road
South
Property of Bharat Rajaram Rakade out of Gat No 63
East
Property of Gupta out Gat No 63
West
Property of Satish Rajaram Rokade out of Gat No 63

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking42 units

42 units registered

— · 42 units
TypeCarpet areaUnits
——42

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals6

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMahendra Thakur—
ArchitectM/s Mahendra Thakur & Associates—
Chartered accountantM. S. Kumbhar and Associates KUMBHAR—
Chartered accountantNavnath Lahu Bhakare—
EngineerJaykumar Rameshbhai Patel—
EngineerSarvasiddhant Structural Engineers Pvt Ltd—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Chikhali

All 2,448 projects in Chikhali · Compare Sky Marina with another project

Sky Marina in numbers

Registered deals, summarised

Deedo has 38 registered documents at Sky Marina, from Jun 2025 to Oct 2026: 36 sales, 2 mortgages. The median registered sale since Jun 2025 works out to about ₹7,300 per sq ft, at a median of ₹56 L a deal; 0% of sales were resales.

What is the price per sq ft at Sky Marina?
The median registered sale since Jun 2025 works out to about ₹7,300 per sq ft, at a median of ₹56 L a deal; 0% of sales were resales.
How many properties have been sold at Sky Marina?
36 sales are registered at Sky Marina.
Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Sky Marina by Deedo, last updated with deals registered in Oct 2026.

Latest deal · Primary sale · Oct 2026

₹50–75 L

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · registered documents (Index II)Data through is when MahaRERA's project page was last read.Report a problemMethodology