Deedo IDDP-PUN-QP8WMahaRERA shows it completed, after its date was pushed back 3 months; no MahaRERA orders on record.
Chikhali, Pune 411062 · Property rates in Chikhali · by S J Builder & Developers
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed, after its date was pushed back 3 months
- This projectRegistered 9 Jun 2022, completion promised 31 Mar 2024, revised to 30 Jun 2024.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
- Resale · Sep 2026
- Title transfer · Sep 2026
- Primary sale · Sep 2026
- Resale · Jul 2026
- Resale · Mar 2026
- Resale · Oct 2025
- Primary sale · Aug 2025
- Resale · Jul 2025
- Resale · Feb 2025
- Resale · Dec 2024
| Month | Flat | Kind | Area | Price | Record |
|---|---|---|---|---|---|
| Sep 2026 | Unit 505 | Resale | 332 sq ft | View Resale, Sep 2026 | |
| Sep 2026 | Unit 904 | Title transfer | 333 sq ft | View Title transfer, Sep 2026 | |
| Sep 2026 | Royal Residency · 208 | Primary sale | 554 sq ft | View Primary sale, Sep 2026 | |
| Jul 2026 | Royal Residency · 909 | Resale | 342 sq ft | View Resale, Jul 2026 | |
| Mar 2026 | Not on record | Resale | 657 sq ft | View Resale, Mar 2026 | |
| Oct 2025 | Unit 706 | Resale | 332 sq ft | View Resale, Oct 2025 | |
| Aug 2025 | Unit 706 | Primary sale | 332 sq ft | View Primary sale, Aug 2025 | |
| Jul 2025 | Unit 111 | Resale | 574 sq ft | View Resale, Jul 2025 | |
| Feb 2025 | Unit 1205 | Resale | 333 sq ft | View Resale, Feb 2025 | |
| Dec 2024 | Unit 604 | Resale | 523 sq ft | View Resale, Dec 2024 |
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100045783
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100045783 | 9 Jun 2022 | 31 Mar 2024 | 30 Jun 2024 | S J Builder & Developers | Project page |
Documents49
3 documents held by Deedo, 46 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Finance
- PAN CardFirm PAN Card.pdf · uploaded 8 Apr 2022Source
Legal
Migrated
- 1 PAN CardFirm PAN Card.pdf · uploaded 8 Apr 2022Source
Show all 49 documentsShow fewer documents
Migrated
- 1 Details of encumbrancesDeclaration.pdf · uploaded 21 Apr 2022Source
- 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 21 Apr 2022Source
- 1 Declaration about Commencement CertificateDeclaration Of Commencment.pdf · uploaded 23 Apr 2022Source
- 1 CERSAI detailsCERSAI_Search_Report_200237461582_For_Debtor_Based_Search_17_05_2022_13_52_39_595.pdf · uploaded 17 May 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed.pdf · uploaded 17 May 2022Source
- 1 Copy of Layout Approval (in case of layout)REVISE PLAN 3.pdf · uploaded 24 May 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentREVISE PLAN 1.pdf · uploaded 24 May 2022Source
- 2 Building Plan Approval / NA Order for plotted developmentREVISE PLAN 2.pdf · uploaded 24 May 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMM CERTIFICATE REVISE.pdf · uploaded 24 May 2022Source
- 2 Proforma of Allotment letterAgreement Copy.pdf · uploaded 24 May 2022Source
- 1 Declaration in FORM BPromotor Form B NEW.pdf · uploaded 29 May 2022Source
- 1 Copy of the legal title reportLEGAL TITAL REPORT.pdf · uploaded 30 May 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 2223.pdf · uploaded 10 Oct 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 DEC 23.pdf · uploaded 23 Jan 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 DEC 23.pdf · uploaded 23 Jan 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 DEC 23_compressed.pdf · uploaded 23 Jan 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 24 Jan 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form - 2.pdf · uploaded 24 Jan 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form - 2.pdf · uploaded 24 Jan 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form - 1.pdf · uploaded 24 Jan 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form - 3_compressed.pdf · uploaded 24 Jan 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form - 3_compressed.pdf · uploaded 24 Jan 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM NO 1 MARCH 24.pdf · uploaded 5 Apr 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MARCH 24.pdf · uploaded 5 Apr 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)CIVIL CER.pdf · uploaded 12 Apr 2024Source
- 1 Disclosure of sold/ booked inventoryBOOK UNIT STATEMENTS.pdf · uploaded 12 Apr 2024View
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 MARCH 24_compressed.pdf · uploaded 13 Apr 2024Source
- 2 Declaration in FORM BFORM B NEW.pdf · uploaded 20 Apr 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MARCH 2024.pdf · uploaded 20 Apr 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MARCH 2024.pdf · uploaded 20 Apr 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)CIVIL CERTIFICATE 23-24.pdf · uploaded 8 Jun 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLITION CERTIFICATE.pdf · uploaded 8 Jun 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 2324.pdf · uploaded 6 Jul 2024Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)SOCIETY CERTIFICATE.pdf · uploaded 6 Jul 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 JUNE 24 NEW.pdf · uploaded 23 Jul 2024Source
- 2 Architect’s Certificate on Completion of Project (Form 4)FORM NO 4 NEW.pdf · uploaded 27 Jul 2024Source
Technical
Technical (Architect)
- DocumentFORM 1 MARCH 2024.pdf · uploaded 20 Apr 2024Source
Technical (Engineer)
- DocumentFORM 2 MARCH 2024.pdf · uploaded 20 Apr 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel GAT NO 75
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK, Office space, Shop32 units in all
- Address
- Gat No 75, Rever Residecy Road, Pimpri ChinchwadPIN 411062
- Village
- Chikhali, Haveli taluka
- Location
- 18.68391, 73.82997
- Land area for this project
- 613 sq m (6,600 sq ft)
- Permissible built-up area
- 2,316 sq m (24,929 sq ft)
- Sanctioned built-up area
- 2,310 sq m (24,868 sq ft)
- Designated bank account
- 88
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
GAT NO 75
Boundaries
- North
- Swastik Home Town Project Gat No 75
- South
- Swastik Home Town Project Gat No 75
- East
- 18 Mtr Dp Road
- West
- Swastik Spira Project Gat No 75
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking32 units
32 of 32 units booked (100%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 61.94 sq m · 667 sq ft | 10 | 10 |
| 2BHK | 63.32 sq m · 682 sq ft | 10 | 10 |
| 2BHK | 67.94 sq m · 731 sq ft | 1 | 1 |
| 2BHK | 70.53 sq m · 759 sq ft | 1 | 1 |
| 2BHK | 71.68 sq m · 772 sq ft | 1 | 1 |
| 2BHK | 73.62 sq m · 792 sq ft | 1 | 1 |
| Office space | 128.46 sq m · 1,383 sq ft | 1 | 1 |
| Shop | 25.64 sq m · 276 sq ft | 1 | 1 |
Show all 14 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 27.72 sq m · 298 sq ft | 1 | 1 |
| Shop | 28.12 sq m · 303 sq ft | 1 | 1 |
| Shop | 28.85 sq m · 311 sq ft | 1 | 1 |
| Shop | 39.51 sq m · 425 sq ft | 1 | 1 |
| Shop | 39.67 sq m · 427 sq ft | 1 | 1 |
| Shop | 59.25 sq m · 638 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals5
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Pramod S Shinde | — |
| Chartered accountant | Sharma Jadhav & Co | — |
| Chartered accountant | S N Jadhav & Co | — |
| Engineer | Ajay Bhilare | — |
| Other | S R Design Hub Mep Consultants | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Chikhali
- The ForestiaRERA PM1260002602656
- Kshitij HomesRERA PR1260002602559
- Paradise VistaRERA PR1260002602535
- Miracle Madhubon ARERA PR1260002602171
- Vrinda ResidencyRERA PR1260002601218
- Landson KeysRERA PM1260002601127
- Santiago Skyarc₹7,220 a sq ft
- Anant₹7,170 a sq ft
All 2,448 projects in Chikhali · Compare Royal Residency with another project
Royal Residency in numbers
Registered deals, summarised
Deedo has 598 registered documents at Royal Residency, from Jan 2015 to Oct 2026: 179 sales, 255 leave and licence agreements, 123 mortgages. The median registered sale since Jan 2015 works out to about ₹7,100 per sq ft, at a median of ₹25 L a deal; 10% of sales were resales.
- What is the price per sq ft at Royal Residency?
- The median registered sale since Jan 2015 works out to about ₹7,100 per sq ft, at a median of ₹25 L a deal; 10% of sales were resales.
- How many properties have been sold at Royal Residency?
- 179 sales are registered at Royal Residency, 18 of them resales.
- Are properties at Royal Residency rented out?
- Yes: 255 leave and licence agreements are registered at Royal Residency, at a median rent since Jan 2015 of about ₹11,000 a month with a deposit of about ₹25,000.
- Where does this data come from?
- The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Royal Residency by Deedo, last updated with deals registered in Oct 2026.
Latest deal · Resale · Sep 2026
₹25–50 L