Skip to content
Extended 18 mo1 floorRERA P52100018678

Vithai Complex, Vithai Developers

Deedo IDDP-PUN-3KKQ-VC

MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.

Median saleNot on recordneeds 3 or more sales
Completion29 May 202230 Nov 2020 · revised
Units & parking in Vithai Complex
TypeCarpet areaUnitsBooked
1BHK41.2 m² (444 sq.ft)4Not on record
1BHK44.3 m² (477 sq.ft)4Not on record
1BHK47.5 m² (511 sq.ft)4Not on record

Parking: Closed/Covered 0 · Open Space 0 (as declared to MahaRERA)

Construction progress (declared)

Work completed, as the promoter reported it to MahaRERA (Form 1). Not verified on site.

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
As registered with MahaRERA
RERA registration
P52100018678 · registered 27 Nov 2018
Promised completion
30 Nov 2020
Revised completion
29 May 2022
Sanctioned habitable floors
1
Deedo ID
DP-PUN-3KKQ-VC
Questions about Vithai Complex

When is Vithai Complex due for completion?

The MahaRERA registration promises 30 Nov 2020, revised to 29 May 2022.

How many floors does Vithai Complex have?

1 sanctioned habitable floor, as registered with MahaRERA.

Data through12 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology