Extended 24 mo5 floorsRERA P52100013109
Main building, Saiguru
Deedo IDDP-PUN-NVTB-SAIGURMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked78%7 of 9 · MahaRERA
Completion30 Oct 202031 Oct 2018 · revised
Units & parking in Main building
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 36 m² (387 sq.ft) | 1 | 1 |
| 1BHK | 35.7 m² (384 sq.ft) | 1 | 1 |
| 1BHK | 35.9 m² (387 sq.ft) | 1 | 1 |
| 1BHK | 40.9 m² (440 sq.ft) | 1 | 1 |
| 1BHK | 41 m² (441 sq.ft) | 1 | 1 |
| 1BHK | 45.1 m² (486 sq.ft) | 1 | 1 |
| 1RK | 30.4 m² (327 sq.ft) | 1 | 1 |
| 2 BHK | 40.7 m² (438 sq.ft) | 1 | 0 |
| 2 BHK | 46.7 m² (503 sq.ft) | 1 | 0 |
As registered with MahaRERA
- RERA registration
- P52100013109 · registered 14 Sep 2017
- Promised completion
- 31 Oct 2018
- Revised completion
- 30 Oct 2020
- Sanctioned habitable floors
- 5
- Building
- SAIGURU
- Sanctioned floors (incl. basement, stilt, podium)
- 5
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- DP-PUN-NVTB-SAIGUR
Questions about Main building
When is Main building due for completion?
The MahaRERA registration promises 31 Oct 2018, revised to 30 Oct 2020.
How many floors does Main building have?
5 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Report a problemMethodology