Chakreshwar Vihar
Deedo IDDP-PUN-GBAYCompletion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 1% of its units are booked.
Chakan (Ct), Pune 410501 · by Yashodeep Tradecon
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2029
- This projectRegistered 20 Jan 2025, completion promised 31 Dec 2028, revised to 30 Apr 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100078916
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100078916 | 20 Jan 2025 | 31 Dec 2028 | 30 Apr 2029 | Yashodeep Tradecon | Project page |
Documents74
1 document held by Deedo, 73 filings listed on MahaRERA's project page
Finance
Legal
Show all 74 documentsShow fewer documents
Migrated
- 1 a Details of encumbrances concerned to FinanceEncumbrance Letter - Finance.pdf · uploaded 9 Oct 2024Source
- 1 Copy of Layout Approval (in case of layout)Layout - 1.pdf · uploaded 9 Oct 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentChakreshwar Vihar Commencement Certificate.pdf · uploaded 9 Oct 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentLayout - 1.pdf · uploaded 9 Oct 2024Source
- 1 Declaration about Commencement CertificateDeclaration about Commencement.pdf · uploaded 9 Oct 2024Source
- 1 CERSAI detailsNo CERSAI Legal .pdf · uploaded 9 Oct 2024Source
- 1 Deviation Report with respect to Allotment letterNo Deviation in Agreement to sell.pdf · uploaded 9 Oct 2024Source
- 1 b Details of encumbrances concerned to LegalEncumbrance Letter - Finance.pdf · uploaded 9 Oct 2024Source
- 1 Deviation Report with respect to model copy of AgreementNo Deviation in Agreement to sell.pdf · uploaded 9 Oct 2024Source
- 1 Proforma of Allotment letterAl_Chakreshwar Vihar_Yashodeep Tradecon_29112024.pdf · uploaded 17 Oct 2024Source
- 1 Declaration in FORM BFrom B Yashodeep Tradecon.pdf · uploaded 17 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate_11zon.pdf · uploaded 17 Oct 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Latest.pdf · uploaded 17 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate_11zon.pdf · uploaded 17 Oct 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A - All RERA Designated account.pdf · uploaded 17 Oct 2024Source
- 1 Proforma of Agreement for saleAFS_Chakreshwar Vihar_Yashodeep Tradecon_14122024.pdf · uploaded 17 Oct 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsYogesh Annexure A.pdf · uploaded 17 Oct 2024Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsVaibhav Annexure A.pdf · uploaded 17 Oct 2024Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B - Declaration from the bank.pdf · uploaded 17 Oct 2024Source
- 1 Disclosure for secured/unsecured finance availed for the projectDiclosure of Secured and Unsecured Loan.pdf · uploaded 17 Oct 2024Source
- 2 a Details of encumbrances concerned to FinanceEncumbrance Letter - Legal.pdf · uploaded 14 Dec 2024Source
- 2 b Details of encumbrances concerned to LegalEncumbrance Letter - Legal.pdf · uploaded 14 Dec 2024Source
- 2 Other – FinanceDeclaration for Proprietorship firm.pdf · uploaded 14 Dec 2024Source
- 2 Other – TechnicalAnnexure A - Order No 50.pdf · uploaded 16 Dec 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentLayout - 2-4.pdf · uploaded 3 Jan 2025Source
- 2 Building Plan Approval / NA Order for plotted developmentLayout - 5-7.pdf · uploaded 3 Jan 2025Source
- 1 Other – FinanceDeclaration for no bank account.pdf · uploaded 3 Jan 2025Source
- 1 Other – TechnicalCC Verification Mail - Chakreshwar Vihar.pdf · uploaded 3 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryCircular 29_11zon (2).pdf · uploaded 13 Mar 2025Source
- DocumentForm 1 - Chakreshwar Vihar as on March 2025.pdf · uploaded 29 Apr 2025Source
- Documentuploaded 29 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Chakreshwar Vihar as on March 2025.pdf · uploaded 9 May 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)1 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf · uploaded 9 May 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Chakreshwar Vihar as on March 2025.pdf · uploaded 9 May 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 9 May 2025Source
- Form 5 (FY 2024-2025)Form 5 - Chakreshwar Vihar for FY 2024-25.pdf · uploaded 23 Dec 2025Source
- Withdrawal Update Form 1Form 1- Chakreshwar Vihar as on June 2025.pdf · uploaded 4 Aug 2026Source
- Withdrawal Update Form 1Chakreshwar_architect certificate_Sep 2025.pdf · uploaded 4 Aug 2026Source
- Withdrawal Update Form 1Chakreshwar_architect certificate_Dec 2025.pdf · uploaded 4 Aug 2026Source
- Withdrawal Update Form 1Form 1 - Chakreshwar Vihar as on March 2025.pdf · uploaded 4 Aug 2026Source
- Withdrawal Update Form 1Form 1 - Chakreshwar Vihar as on March 2025.pdf · uploaded 4 Aug 2026Source
- Withdrawal Update Form 1Form 1 Chakreshwar Vihar june 2026.pdf · uploaded 4 Aug 2026Source
- Withdrawal Update Form 2Form 2 - Chakreshwar Vihar as on June 2025.pdf · uploaded 4 Aug 2026Source
- Withdrawal Update Form 2Chakreshwar_Vihar_Form2_Q2_2025-26_04-08-2026_06-34.pdf · uploaded 4 Aug 2026Source
- Withdrawal Update Form 2Chakreshwar_Vihar_Form2_Q3_2025-26_04-08-2026_06-29.pdf · uploaded 4 Aug 2026Source
- Withdrawal Update Form 2Form 2 - Chakreshwar Vihar as on March 2025.pdf · uploaded 4 Aug 2026Source
- Withdrawal Update Form 2Form 2 - Chakreshwar Vihar as on March 2025.pdf · uploaded 4 Aug 2026Source
- Withdrawal Update Form 2form 2 Chakreshwar Vihar june 2026.pdf · uploaded 4 Aug 2026Source
- Withdrawal Update Form 3Form 3 - Chakreshwar Vihar as on June 2025.pdf · uploaded 4 Aug 2026Source
- Withdrawal Update Form 3Chakreshwar_Vihar_Form3_Q2_2025-26_31-07-2026_09-18_doc1.pdf · uploaded 4 Aug 2026Source
- Withdrawal Update Form 3Chakreshwar_Vihar_Form3_Q3_2025-26_31-07-2026_09-28_doc1.pdf · uploaded 4 Aug 2026Source
- Withdrawal Update Form 3Form 3 - Chakreshwar Vihar as on March 2025.pdf · uploaded 4 Aug 2026Source
- Withdrawal Update Form 3Form 3 - Chakreshwar Vihar as on March 2025.pdf · uploaded 4 Aug 2026Source
- Withdrawal Update Form 3form 3 Chakreshwar Vihar june 2026.pdf · uploaded 4 Aug 2026Source
Technical
- DocumentLayout - 1.pdf · uploaded 9 Oct 2024Source
- DocumentLayout - 1.pdf · uploaded 9 Oct 2024Source
- Other – TechnicalAnnexure A - Order No 50.pdf · uploaded 16 Dec 2024Source
- DocumentLayout - 5-7.pdf · uploaded 3 Jan 2025Source
- DocumentLayout - 2-4.pdf · uploaded 3 Jan 2025Source
- Other – TechnicalCC Verification Mail - Chakreshwar Vihar.pdf · uploaded 3 Jan 2025Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 713/A (P), 713/B
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —141 units in all
- Address
- 713(P), 713/A (P), 713/B, 714(P), 715, 716, 717, 718, 719, 727, Chakreshwar Road, ChakanPIN 410501
- Village
- Chakan (CT), Khed taluka
- Location
- 18.76321, 73.86132
- Land area for this project
- 2,004 sq m (21,575 sq ft)
- Permissible built-up area
- 7,941 sq m (85,480 sq ft)
- Sanctioned built-up area
- 6,941 sq m (74,717 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 190
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
713(P), 713/A (P), 713/B, 714(P), 715, 716,717, 718, 719, 727
Boundaries
- North
- Marathi School To Chakreshwar Road
- South
- Deshmukh Ali To Chakreshwar Road
- East
- Internal City Survey Road
- West
- Saiprasad Residency
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking141 units
141 units registered
| Building | Type | Carpet area | Units |
|---|---|---|---|
| Building A | — | — | 96 |
| Building B | — | — | 45 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Other projects in Chakan (Ct)
- Opal FieldRERA PM1260002602568
- Pradnyesh ShreeRERA PM1260002601406
- Sara Kasturi Building CRERA PR1261012600183
- Bajrang Complex Wing ARERA PR1260002503027
- Aetheria - A wingRERA PR1261012502219
- Empire Business HubRERA PC1260002501299
- Sara Abhiruchi Tower ARERA PR1261012500876
- Chakan Nagarparishad PMAY AhpRERA P52100080338
All 62 projects in Chakan (Ct) · Compare Chakreshwar Vihar with another project