Skip to content
Residential / Group Housing · 1 building · 39 unitsRERA P52100034805

Venu Tower

Deedo IDDP-PUN-ZHE5

Completion was pushed back 4 months to Jul 2026, and that date has passed too; no MahaRERA orders on record.

Bhosari, Pune 411039 · Property rates in Bhosari · by Vighnaharta Developers

Delivery8 mo latePromised Mar 2026 · revised Jul 2026 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readPrice₹7,180 /sq ft2.8% above Bhosari · 19 registered sales

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months to Jul 2026, and that date has passed too

  • This projectRegistered 28 Apr 2022, completion promised 31 Mar 2026, revised to 31 Jul 2026, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

All 30 deeds →
Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Jun 2026Venu Tower · 103Primary sale623 sq ftView Primary sale, Jun 2026
May 2026Venu Tower · 203Primary sale623 sq ftView Primary sale, May 2026
Mar 2026Venu Tower · 101Primary sale610 sq ftView Primary sale, Mar 2026
Mar 2026Venu Tower · 201Primary sale610 sq ftView Primary sale, Mar 2026
Mar 2026Venu Tower · 303Primary sale623 sq ftView Primary sale, Mar 2026
Jan 2026Venu Tower · 803Primary sale623 sq ftView Primary sale, Jan 2026
Dec 2025Venu Tower · 102Primary sale610 sq ftView Primary sale, Dec 2025
Dec 2025Venu Tower · 401Primary sale607 sq ftView Primary sale, Dec 2025
Sep 2025Venu Tower · 403Primary sale623 sq ftView Primary sale, Sep 2025
Aug 2025Venu Tower · 503Primary sale623 sq ftView Primary sale, Aug 2025

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page. Construction % is the average of the developer's own declared activity progress to MahaRERA, not an inspection.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100034805
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210003480528 Apr 202231 Mar 202631 Jul 2026Vighnaharta DevelopersProject page
Documents38

19 documents held by Deedo, 19 filings listed on MahaRERA's project page

Form B

Allotment letter (4)

Form 1

Title report

Encumbrance details

Show all 38 documentsShow fewer documents

Layout plan (2)

Commencement certificate

Registration certificate

Form 2

Other (6)

Document library

  • Copy of the legal title reportsanjay Pacharane.pdf · uploaded 6 Apr 2022View
  • Details of encumbrancesNo Encumbramce Declaration.pdf · uploaded 6 Apr 2022View
  • Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 6 Apr 2022View
  • Building Plan Approval / NA Order for plotted development1.pdf · uploaded 6 Apr 2022View
  • Declaration in FORM BSurekha Chavhan-Form B.pdf · uploaded 6 Apr 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA ARCHITECT - FORM 1_.pdf · uploaded 6 Apr 2022View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)RERA ENGGINEER CERT - FORM 2.pdf · uploaded 6 Apr 2022View
  • Proforma of Allotment letterALLOTMENT Letter Vighnaharta Developers.pdf · uploaded 6 Apr 2022View
  • CERSAI detailsCERSAI.pdf · uploaded 7 Apr 2022View
  • Commencement Certificates / NA Order for plotted developmentCommencement PCMC.pdf · uploaded 22 Apr 2022View
  • Declaration about Commencement CertificateDeclaration.pdf · uploaded 22 Apr 2022View
  • Proforma of Allotment letterAgreement To Sale Vighnharta Developers 201.pdf · uploaded 22 Apr 2022View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 1 Mar 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Form II Oct-Dec 2024.pdf · uploaded 1 Mar 2025View

Promoter documents

  • Legal Title reportsanjay Pacharane.pdf · uploaded 6 Apr 2022View
  • Declaration Form BSurekha Chavhan-Form B.pdf · uploaded 6 Apr 2022View

Technical documents

  • Layout ApprovalLayout.pdfView
  • Building Plan Approval1.pdfView

Proforma allotment letter

  • Proforma allotment letterALLOTMENT Letter Vighnaharta Developers.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsSurvey 201/1A/1, 4197

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Lapsed
Unit types
1BHK, 2BHK39 units in all
Address
S.No.201/1A/1, CTS no.4197, Alandi Road, BhosariPIN 411039
Village
Bhosari, Haveli taluka
Land area for this project
1,228 sq m (13,218 sq ft)
Permissible built-up area
2,161 sq m (23,261 sq ft)
Sanctioned built-up area
2,161 sq m (23,261 sq ft)
Recreational open space
1,228 sq m (13,218 sq ft)
Designated bank account
GS Mahanagar Co-operative Bank Limited, Mumbai
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared
Also registered as
Yena-Ya Venu Tovar, येणा-या वेणू टॉवर, Yena-Ya Venu Tower

Survey, CTS, gat or plot numbers

201/1A/14197CTS no.4197S.No.201/1A/1

Land as published on MahaRERA's project page

S.No.201/1A/1, CTS no.4197

Boundaries

North
Survey No 200
South
Birajdar land
East
30ft wide road
West
Pacharane Dham Building

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking39 units · 60 parking spaces

39 units registered

1BHK · 10 units2BHK · 29 units
TypeCarpet areaUnits
1BHK48.7 sq m · 524 sq ft10
2BHK57.87 sq m · 623 sq ft10
2BHK64.97 sq m · 699 sq ft19

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered000048
Open Space000012

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress2 buildings and areas

Work completed, as the promoter reported it to MahaRERA (Form 1)

Venu Tower

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water Supplyto be started0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)to be started0%
  • Storm Water Drainsto be started0%
  • Landscaping & Tree Plantingto be started0%
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage Waterto be started0%
  • Solid Waste Management And Disposalto be started0%
  • Water conservation /Rain water harvestingto be started0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsto be started0%
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open Parkingto be started0%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMr Kiran Bhosale—
Chartered accountantYogeshkumar thanvi—
EngineerMr Ravindra A Karnavat—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Bhosari

All 2,664 projects in Bhosari · Compare Venu Tower with another project

Venu Tower in numbers

Registered deals, summarised

Deedo has 30 registered documents at Venu Tower, from Oct 2020 to Jun 2026: 19 sales, 1 leave and licence agreement, 10 mortgages. The median registered sale since Oct 2020 works out to about ₹7,200 per sq ft, at a median of ₹45 L a deal; 0% of sales were resales.

What is the price per sq ft at Venu Tower?
The median registered sale since Oct 2020 works out to about ₹7,200 per sq ft, at a median of ₹45 L a deal; 0% of sales were resales.
How many properties have been sold at Venu Tower?
19 sales are registered at Venu Tower.
Are properties at Venu Tower rented out?
Yes: 1 leave and licence agreement is registered at Venu Tower.
Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Venu Tower by Deedo, last updated with deals registered in Jun 2026.

Latest deal · Primary sale · Jun 2026

₹25–50 L

Data through3 Nov 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · registered documents (Index II)Data through is when MahaRERA's project page was last read.Report a problemMethodology