Others · 1 building · 33 unitsRERA P52100028463

Westfield 23

Deedo IDDP-PUN-Y9SV

It is due for completion in Dec 2026, with no extension on record; no MahaRERA orders on record; 33% of its units are booked.

Baner, Pune 411045 · Property rates in Baner · by GRD Westfield Realty LLP

DeliveryDue Dec 2026No extension on recordRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales33% booked11 of 33 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

It is due for completion in Dec 2026, with no extension on record

  • This projectRegistered 2 Mar 2021, completion promised 31 Dec 2026.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100028463
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000284632 Mar 202131 Dec 202631 Dec 2026GRD Westfield Realty LLPProject page
Documents144

1 document held by Deedo, 143 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardGRD Westfield Realty LLP Pan Card.pdf · uploaded 19 Feb 2021Source

Legal

  • Declaration Form BFORM B - Affidavit GRD Westfield Realty LLP.pdf · uploaded 19 Feb 2021Source
  • Legal Title reportSearch Tittle Report 1.pdf · uploaded 23 Feb 2021Source
  • Legal Title reportSearch Tittle Report 2.pdf · uploaded 23 Feb 2021Source
  • Declaration Form BFORM B.pdf · uploaded 25 Apr 2025Source

Migrated

  • 1 PAN CardGRD Westfield Realty LLP Pan Card.pdf · uploaded 19 Feb 2021Source
  • 1 Details of encumbrancesNo Eucumbrances Letter.pdf · uploaded 19 Feb 2021Source
Show all 144 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)Sanction Plan 01.pdf · uploaded 19 Feb 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentSanction Plan 03.pdf · uploaded 19 Feb 2021Source
  • 2 Building Plan Approval / NA Order for plotted developmentSanction Plan 02.pdf · uploaded 19 Feb 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 19 Feb 2021Source
  • 1 Declaration in FORM BFORM B - Affidavit GRD Westfield Realty LLP.pdf · uploaded 19 Feb 2021Source
  • 1 Proforma of Allotment letterGRD Westfield Realty LLP Allotment Letter.pdf · uploaded 20 Feb 2021Source
  • 2 Proforma of Allotment letterDraft agreement.pdf · uploaded 20 Feb 2021Source
  • 1 Copy of the legal title reportSearch Tittle Report 1.pdf · uploaded 23 Feb 2021Source
  • 2 Copy of the legal title reportSearch Tittle Report 2.pdf · uploaded 23 Feb 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)GRD WESTFILED REALTY LLP CA CERTIFICATE.pdf · uploaded 23 Feb 2021Source
  • 3 Building Plan Approval / NA Order for plotted developmentRevised Sanction Plan I.pdf · uploaded 10 May 2022Source
  • 4 Building Plan Approval / NA Order for plotted developmentRevised Sanction Plan II.pdf · uploaded 10 May 2022Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 10 May 2022Source
  • 3 Commencement Certificates / NA Order for plotted developmentRevised Sanction Plan I.pdf · uploaded 10 May 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200239745976_For_Asset_Based_Search_15_06_2022_09_58_26_810.pdf · uploaded 15 Jun 2022Source
  • 1 Declaration about Commencement CertificateWestfield 23 DECLARATION ABOUT COMMENCEMNT CERTIFICATE_compressed.pdf · uploaded 16 Jun 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Westfield 23 Architecture Certificate Of Rera_compressed.pdf · uploaded 16 Jun 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Westfield 23 Quality Assurance Certificate.pdf · uploaded 16 Jun 2022Source
  • 1 Disclosure of sold/ booked inventoryWestfield 23 Discloser for sold and unlsold invetory.pdf · uploaded 16 Jun 2022Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 FY 21-22 (Q4)-WESTFIELD 23.pdf · uploaded 29 Nov 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Signed Form 5_Westfield 23 GRD Westfield Reality LLP.pdf · uploaded 29 Nov 2022Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Q3 (Westfield- 23).pdf · uploaded 16 Feb 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate 23 (Q3).pdf · uploaded 26 Feb 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Westfield 23 Q3.pdf · uploaded 27 Feb 2023Source
  • 2 Disclosure of sold/ booked inventoryPromoter Disclosure 23, Q3.pdf · uploaded 28 Feb 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Q3 (Westfield- 23) Revised.pdf · uploaded 28 Feb 2023Source
  • 2 a Details of encumbrances concerned to Finance1 Details of encumbrances.pdf · uploaded 20 Mar 2023Source
  • 1 b Details of encumbrances concerned to Legal1 Details of encumbrances.pdf · uploaded 20 Mar 2023Source
  • 2 Declaration about Commencement CertificateDeclaration Commencement Certificate - Format D.pdf · uploaded 20 Mar 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Non Applicable of Form 2A.pdf · uploaded 20 Mar 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Quality Assurance Certificate Suhel Patel Dt 17-03-2023.pdf · uploaded 20 Mar 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Non Applicable of Form 5.pdf · uploaded 20 Mar 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Non Applicable of Form 5.pdf · uploaded 20 Mar 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Non Applicable of Form 5.pdf · uploaded 20 Mar 2023Source
  • 1 Proforma of Agreement for saleAgreement for sale.pdf · uploaded 20 Mar 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations.pdf · uploaded 25 Mar 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration for Separate Bank Account - Format A.pdf · uploaded 25 Mar 2023Source
  • 1 Deviation Report with respect to Allotment letterNo Deviation Report - Allotment Letter.pdf · uploaded 25 Mar 2023Source
  • 1 Deviation Report with respect to model copy of AgreementNo Deviation Report - Agreement for sale.pdf · uploaded 25 Mar 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 FY 2021-22.pdf · uploaded 1 Apr 2023Source
  • 5 Building Plan Approval / NA Order for plotted developmentC1W23 Final Revised Sanction Plan Dt 29-03-2023 - 01_11zon.pdf · uploaded 10 Apr 2023Source
  • 6 Building Plan Approval / NA Order for plotted developmentC2W23 Final Revised Sanction Plan Dt 29-03-2023 - 02_11zon.pdf · uploaded 10 Apr 2023Source
  • 7 Building Plan Approval / NA Order for plotted developmentC2W23 Final Revised Sanction Plan Dt 29-03-2023 - 02_11zon.pdf · uploaded 10 Apr 2023Source
  • 4 Commencement Certificates / NA Order for plotted developmentW23 Final Commencement certificate 29-03-2023.pdf · uploaded 10 Apr 2023Source
  • 8 Building Plan Approval / NA Order for plotted developmentPlan Pg 1 of 2.pdf · uploaded 3 May 2023Source
  • 9 Building Plan Approval / NA Order for plotted developmentPlan Pg 2 of 2.pdf · uploaded 3 May 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Westfield 23 Architect Certificate - Form 1.pdf · uploaded 3 May 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Westfield 23 engineer certificate form 2 31-Mar-2023.pdf · uploaded 3 May 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Westfield 23 engineer certificate form 2 31-Mar-2023.pdf · uploaded 18 May 2023Source
  • 3 Declaration about Commencement CertificateDeclaration About Commencement Certificate - Westfield 23.pdf · uploaded 20 May 2023Source
  • 3 Disclosure of sold/ booked inventoryPromoter Declaration - W23 Q4.pdf · uploaded 20 May 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Q4 (Westfield- 23).pdf · uploaded 22 May 2023Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Engineer certificate Form 2A FY 2022-23.pdf · uploaded 15 Jun 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Engi Cer 2A W23.pdf · uploaded 16 Jun 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Form 1 Final.pdf · uploaded 11 Jul 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate Form 1 Q1.pdf · uploaded 2 Aug 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate - Form 2 W23.pdf · uploaded 2 Aug 2023Source
  • 4 Disclosure of sold/ booked inventoryPromoter Disclosure Q1 W23.pdf · uploaded 2 Aug 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Q1 (Westfield- 23).pdf · uploaded 2 Aug 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Westfield 23 RERA quarterly update Architect Certificate - Form 1 30-09-2023.pdf · uploaded 9 Nov 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers certificate - Form 2 Westfield 23 Dt 30-09-2023.pdf · uploaded 9 Nov 2023Source
  • 5 Disclosure of sold/ booked inventoryWestfield 23 Dicloser List Sold and unsold Dt 30-09-2023.pdf · uploaded 9 Nov 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3 -Q2 -Westfield 23.pdf · uploaded 20 Nov 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3 -Q2 -Westfield 23.pdf · uploaded 23 Nov 2023Source
  • 2 CERSAI detailsWestfield 23 CERSAI Search Report.pdf · uploaded 1 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Annual Audit (W 23) FY 2022-23.PDF · uploaded 14 Feb 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Westfield 23 Form 2 Engineer Certificate Q3.pdf · uploaded 6 Mar 2024Source
  • 6 Disclosure of sold/ booked inventoryPromoters Disclosure unit wise Westfield 23 Q3.pdf · uploaded 6 Mar 2024Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form3- FY 23-24 Q3 Westfield 23.pdf · uploaded 6 Mar 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form -1 Architech Certificate Westfield 23 Q3 FY 2023-24.pdf · uploaded 7 Mar 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 23-24 Q4 WF -23.pdf · uploaded 27 May 2024Source
  • 7 Disclosure of sold/ booked inventoryPromoter Disclosure FY 23-24 Q4 Wf23.pdf · uploaded 27 May 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY 23-24 Q4 WF 23.pdf · uploaded 5 Jul 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 FY 2024-25 Q1 W-23.pdf · uploaded 26 Jul 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 FY 2024-25 Q1 W-23.pdf · uploaded 26 Jul 2024Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2024-25 Q1 W- 23.pdf · uploaded 26 Jul 2024Source
  • 8 Disclosure of sold/ booked inventoryPromoter Disclosure FY 2024-25 Q1.pdf · uploaded 31 Jul 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 23-24 Q4 Westfield.pdf · uploaded 11 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 23-24 Q4 Westfield.pdf · uploaded 11 Oct 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 WF 23.pdf · uploaded 24 Dec 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Westfield 23 - Engg Cerificate.pdf · uploaded 24 Dec 2024Source
  • 1 Disclosure of sold/ booked inventoryWF 23 Sold.pdf · uploaded 24 Dec 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 24 Dec 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)W23_Form 1.pdf · uploaded 25 Dec 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)WF 23 FORM 5.pdf · uploaded 27 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect's Certificate Westfield 23.pdf · uploaded 20 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q3 2024-25 WF 23.pdf · uploaded 20 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Q3 2024-25 WF 23.pdf · uploaded 20 Feb 2025Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 25 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 25 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FY 2024-25 Q-4 - Westfield 23 - GRD Westfield Realty LLP.pdf · uploaded 25 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 25 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold-Booked Inventory Word.pdf · uploaded 25 Apr 2025Source
  • Form 1WF 23 - Form 1 JULY TO SEP.pdf · uploaded 12 Oct 2025Source
  • Form 2WF 23 - Form 2 JULY TO SEP.pdf · uploaded 12 Oct 2025Source
  • Form 3WF 23 - Form 3 JULY TO SEP.pdf · uploaded 12 Oct 2025Source
  • Disclosure of Sold and Booked InventoryWESTFIELD-23 DISCLOSURE OF SOLD JULY TO SEP.pdf · uploaded 12 Oct 2025Source
  • Form 1WF 23 For 1 APRL - JUNE.pdf · uploaded 12 Oct 2025Source
  • Form 2WF 23 Form 2 APRIL- JUNE.pdf · uploaded 12 Oct 2025Source
  • Form 3WF 23 ForM 3 APRIL- JUNE.pdf · uploaded 12 Oct 2025Source
  • Disclosure of Sold and Booked InventoryWESTFIELD-23 DISCLOSURE OF SOLD APRIL TO JUNE.pdf · uploaded 12 Oct 2025Source
  • Withdrawal Update Form 1WF 23 For 1 APRL - JUNE.pdf · uploaded 12 Oct 2025Source
  • Withdrawal Update Form 1WF 23 - Form 1 JULY TO SEP.pdf · uploaded 12 Oct 2025Source
  • Withdrawal Update Form 2WF 23 Form 2 APRIL- JUNE.pdf · uploaded 12 Oct 2025Source
  • Withdrawal Update Form 2WF 23 - Form 2 JULY TO SEP.pdf · uploaded 12 Oct 2025Source
  • Withdrawal Update Form 3WF 23 ForM 3 APRIL- JUNE.pdf · uploaded 12 Oct 2025Source
  • Withdrawal Update Form 3WF 23 - Form 3 JULY TO SEP.pdf · uploaded 12 Oct 2025Source
  • Withdrawal Update Form 1Q3 Form 1 Wsetfield 23 2026.pdf · uploaded 31 Jan 2026Source
  • Withdrawal Update Form 2Q3 Form 2 Wsetfield 23 2026.pdf · uploaded 31 Jan 2026Source
  • Withdrawal Update Form 3Q3 Form 3 Wsetfield 23 2026.pdf · uploaded 31 Jan 2026Source
  • Withdrawal Update Form 1Westfield 23 - Form 1 FY25-26 Q4.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 1Form 1 - Westfield 23.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 2Westfield 23 - Form 2 FY25-26 Q4.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 2Form 2 - Westfield 23.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 3Form 3 - Westfield 23.pdf · uploaded 27 Jul 2026Source
  • Withdrawal Update Form 3F 3 - WESTFIELD - 23..pdf · uploaded 27 Jul 2026Source
  • Form 2A (FY 2025-2026)Form 2A.pdf · uploaded 4 Aug 2026Source
  • Form 5 (FY 2024-2025)Form 5 - Westfield 23 2024-25 (1).pdf · uploaded 5 Aug 2026Source

Technical

  • DocumentSanction Plan 01.pdf · uploaded 19 Feb 2021Source
  • DocumentSanction Plan 03.pdf · uploaded 19 Feb 2021Source
  • DocumentSanction Plan 02.pdf · uploaded 19 Feb 2021Source
  • DocumentRevised Sanction Plan I.pdf · uploaded 10 May 2022Source
  • DocumentRevised Sanction Plan II.pdf · uploaded 10 May 2022Source
  • DocumentC1W23 Final Revised Sanction Plan Dt 29-03-2023 - 01_11zon.pdf · uploaded 10 Apr 2023Source
  • DocumentC2W23 Final Revised Sanction Plan Dt 29-03-2023 - 02_11zon.pdf · uploaded 10 Apr 2023Source
  • DocumentC2W23 Final Revised Sanction Plan Dt 29-03-2023 - 02_11zon.pdf · uploaded 10 Apr 2023Source
  • DocumentPlan Pg 1 of 2.pdf · uploaded 3 May 2023Source
  • DocumentPlan Pg 2 of 2.pdf · uploaded 3 May 2023Source

Technical (Architect)

  • DocumentW23_Form 1.pdf · uploaded 25 Dec 2024Source
  • DocumentArchitect's Certificate Westfield 23.pdf · uploaded 20 Feb 2025Source
  • DocumentFORM 1.pdf · uploaded 25 Apr 2025Source
  • DocumentForm 1 - Westfield 23.pdf · uploaded 27 Jul 2026Source

Technical (Engineer)

  • DocumentWestfield 23 - Engg Cerificate.pdf · uploaded 24 Dec 2024Source
  • DocumentForm 2 Q3 2024-25 WF 23.pdf · uploaded 20 Feb 2025Source
  • DocumentFORM 2.pdf · uploaded 25 Apr 2025Source
  • DocumentForm 2 - Westfield 23.pdf · uploaded 27 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 23/5/7, 23/5/8

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
Office space33 units in all
Address
23/5/7, 23/5/8, Balewadi High Street, Cummins CampusPIN 411045
Village
Baner, Haveli taluka
Land area for this project
700 sq m (7,535 sq ft)
Permissible built-up area
2,632 sq m (28,334 sq ft)
Sanctioned built-up area
2,632 sq m (28,334 sq ft)
Recreational open space
533 sq m (5,737 sq ft)
Designated bank account
171
Developed in phases
No

Survey, CTS, gat or plot numbers

23/5/723/5/8

Land as published on MahaRERA's project page

23/5/7, 23/5/8

Boundaries

North
Remaining Land of Survey No 23-5
South
12 Meter Road and Utsav Apartment
East
Remaining Land of Survery No 23-5
West
Remaining Land of Survey No 23-6B-3 and 23-6B-4

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking33 units

11 of 33 units booked (33%), as the promoter reported to MahaRERA

Office space · 33 units
TypeCarpet areaUnitsBooked
Office space35.11 sq m · 378 sq ft52
Office space41.09 sq m · 442 sq ft52
Office space41.26 sq m · 444 sq ft51
Office space42.1 sq m · 453 sq ft51
Office space50.42 sq m · 543 sq ft52
Office space51.66 sq m · 556 sq ft61
Office space88.93 sq m · 957 sq ft11
Office space130.29 sq m · 1,402 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals6

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVivek Garode VIVEK GARODE—
Chartered accountantSPAK & Co—
Chartered accountantV S A P & Company—
EngineerAnil Bawaskar—
EngineerKamlesh S Thakare—
EngineerPranav Manoj Khalate—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology