Tejelevia Building C
Deedo IDDP-PUN-NWBFCompletion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 83% of its units are booked.
Baner, Pune 411045 · Property rates in Baner · by Tejraj Realtors Llp
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2029
- This projectRegistered 5 Apr 2023, completion promised 24 Dec 2028, revised to 24 Apr 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
- Rental · Feb 2025
- Rental · Feb 2023
- Rental · 22 mo · Mar 2021
| Month | Flat | Kind | Area | Price | Record |
|---|---|---|---|---|---|
| Feb 2025 | Tejelevia Building C · 8 | Rental | — | View Rental, Feb 2025 | |
| Feb 2023 | Tejelevia Building C · 8 | Rental | — | View Rental, Feb 2023 | |
| Mar 2021 | Tejelevia Building C · 8 | Rental | — | View Rental, Mar 2021 |
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100050379
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100050379 | 5 Apr 2023 | 24 Dec 2028 | 24 Apr 2029 | Tejraj Realtors LLP | Project page |
Documents155
1 document held by Deedo, 154 filings listed on MahaRERA's project page
Finance
- PAN CardUPDATE PAN CARD.pdf · uploaded 10 Mar 2023Source
Legal
Show all 155 documentsShow fewer documents
Migrated
- 1 b Details of encumbrances concerned to LegalSELF DECLARATION REGARDING LITIGATIONS ENCUMBRANCE.pdf · uploaded 10 Mar 2023Source
- 1 CERSAI detailsCERSAI UNDERTAKING.pdf · uploaded 10 Mar 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)fORM 3.pdf · uploaded 10 Mar 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDISCLOSURE OF INTREST IN OTHER REAL ESTATE ORGANIZATION.pdf · uploaded 10 Mar 2023Source
- 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 10 Mar 2023Source
- 1 Deviation Report with respect to Allotment letterDeviation - allotment letter.pdf · uploaded 10 Mar 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviation -Agreement.pdf · uploaded 10 Mar 2023Source
- 1 Copy of Layout Approval (in case of layout)Layout approval.pdf · uploaded 13 Mar 2023Source
- 1 Building Plan Approval / NA Order for plotted development1-sheet no 1-8_compressed.pdf · uploaded 13 Mar 2023Source
- 2 Building Plan Approval / NA Order for plotted development4 OUT OF 8.pdf · uploaded 13 Mar 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentLayout-CC-2861-21.pdf · uploaded 13 Mar 2023Source
- 1 Declaration about Commencement Certificate11-03-2023001.pdf · uploaded 13 Mar 2023Source
- 1 Declaration in FORM BForm B Developer.pdf · uploaded 13 Mar 2023Source
- 1 Proforma of Agreement for saleNew Agrement -C Building.pdf · uploaded 13 Mar 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameformat a001.pdf · uploaded 13 Mar 2023Source
- 2 a Details of encumbrances concerned to FinanceDECLARATION.pdf · uploaded 16 Mar 2023Source
- 2 b Details of encumbrances concerned to LegalDECLARATION.pdf · uploaded 16 Mar 2023Source
- 1 Other – LegalPlot area details.pdf · uploaded 18 Mar 2023Source
- 1 Other – TechnicalPlot area details.pdf · uploaded 24 Mar 2023Source
- 2 Copy of Layout Approval (in case of layout)4 Copy of Layout Approval (in case of layout).pdf · uploaded 12 Apr 2023Source
- 3 Building Plan Approval / NA Order for plotted development8 Building Plan Approval (IOD).pdf · uploaded 12 Apr 2023Source
- 2 Commencement Certificates / NA Order for plotted developmentLayout-CC.pdf · uploaded 12 Apr 2023Source
- 2 Declaration about Commencement Certificateformat D-Tej elevia-C-Building.pdf · uploaded 12 Apr 2023Source
- 3 a Details of encumbrances concerned to FinanceIndex II - Aditya Birla - Encrumbrance.pdf · uploaded 12 Oct 2023Source
- 3 b Details of encumbrances concerned to LegalIndex II - Aditya Birla - Encrumbrance.pdf · uploaded 12 Oct 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - June 23.pdf · uploaded 22 Feb 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Sept 23.pdf · uploaded 22 Feb 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Dec 23.pdf · uploaded 23 Feb 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - June 23.pdf · uploaded 23 Feb 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Sept 23.pdf · uploaded 23 Feb 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Dec 23.pdf · uploaded 23 Feb 2024Source
- 1 Disclosure of sold/ booked inventoryDisclosure - Sold Unsold June 23.pdf · uploaded 23 Feb 2024Source
- 2 Disclosure of sold/ booked inventoryDisclosure - Sold Unsold Sept 23.pdf · uploaded 23 Feb 2024Source
- 3 Disclosure of sold/ booked inventoryDisclosure - Sold Unsold Dec 23.pdf · uploaded 23 Feb 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - June 23.pdf · uploaded 23 Feb 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Sept 23.pdf · uploaded 23 Feb 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Dec 23.pdf · uploaded 23 Feb 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 31 mar 24.pdf · uploaded 20 Apr 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Tej Elevia C Building_0001.pdf · uploaded 20 Apr 2024Source
- 4 Disclosure of sold/ booked inventorysold unsold 31 mar 24.pdf · uploaded 20 Apr 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - June 23.pdf · uploaded 28 Jun 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Sept 23.pdf · uploaded 28 Jun 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Dec 23.pdf · uploaded 28 Jun 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 28 Jun 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 June 23.pdf · uploaded 28 Jun 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Sept 23.pdf · uploaded 28 Jun 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Dec 23.pdf · uploaded 28 Jun 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 28 Jun 2024Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sold Unsold Dec 23.pdf · uploaded 28 Jun 2024Source
- 5 Disclosure of sold/ booked inventorySold Unsold June 23.pdf · uploaded 28 Jun 2024Source
- 6 Disclosure of sold/ booked inventorySold Unsold Sept 23.pdf · uploaded 28 Jun 2024Source
- 7 Disclosure of sold/ booked inventory4 Disclosure of sold_ booked inventory.pdf · uploaded 28 Jun 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 June 23.pdf · uploaded 28 Jun 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Sept 23.pdf · uploaded 28 Jun 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Dec 23.pdf · uploaded 28 Jun 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Mar 24 C.pdf · uploaded 29 Jun 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A.pdf · uploaded 4 Jul 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)8 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 21 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5_Tej Elevia C WING_2023-24_compressed.pdf · uploaded 21 Oct 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 tej elevia building C_Sept 24.pdf · uploaded 12 Nov 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Tej Elevia C_ Sept 24.pdf · uploaded 13 Nov 2024Source
- 1 a Details of encumbrances concerned to FinanceEncumbrance Certificate_Tejelevia C.pdf · uploaded 30 Nov 2024Source
- 1 b Details of encumbrances concerned to LegalEncumbrance Certificate_Tejelevia C.pdf · uploaded 30 Nov 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- CA certificate_Sept 2024_TELBC_compressed.pdf · uploaded 2 Dec 2024Source
- 2 Disclosure of sold/ booked inventoryTej Elevia C Sold and Unsold_Sept 2024.pdf · uploaded 2 Dec 2024Source
- 2 a Details of encumbrances concerned to FinanceEncumbrance Certificate_Tejelevia C.pdf · uploaded 14 Dec 2024Source
- 2 b Details of encumbrances concerned to LegalEncumbrance Certificate_Tejelevia C.pdf · uploaded 14 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1-Tej Elevia_C.pdf · uploaded 17 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_TejElevia C_Dec 24.pdf · uploaded 17 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Tej Elevia C_Dec 24.pdf · uploaded 17 Jan 2025Source
- 1 Disclosure of sold/ booked inventorySold and Unsold_Tejelevia C_Dec 24.pdf · uploaded 17 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Tej Elevia C_March 25.pdf · uploaded 21 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_Tej Elevia C_March 25.pdf · uploaded 21 Apr 2025Source
- 1 Disclosure of sold/ booked inventorySold Unsold_Elevia C_March 25.pdf · uploaded 21 Apr 2025Source
- Form 1Form 1_Tej Elevia C_March 25.pdf · uploaded 18 Jul 2025Source
- Form 1Form 1_Tej Elevia_C_Dec 24.pdf · uploaded 18 Jul 2025Source
- Form 1Form 1-Tej Elevia C_ Sept 24.pdf · uploaded 18 Jul 2025Source
- Form 1Form 1_Tej Elevia C_June 24.pdf · uploaded 18 Jul 2025Source
- Form 1Form 1_Tej Elevia C_ March 24.pdf · uploaded 18 Jul 2025Source
- Form 1Form 1_Tej Elevia C_Dec 23.pdf · uploaded 18 Jul 2025Source
- Form 1Form 1_Tej Elevia C Bldg - Sept 23.pdf · uploaded 18 Jul 2025Source
- Form 1Form 1 - TEJ ELEVIA C - June 23.pdf · uploaded 18 Jul 2025Source
- Form 2Form 2_Tej Elevia C_Mrach 2025.pdf · uploaded 18 Jul 2025Source
- Form 2Form 2_Tej Elevia C_Dec 24.pdf · uploaded 18 Jul 2025Source
- Form 2Form 2 -Tej elevia C_Sept 24.pdf · uploaded 18 Jul 2025Source
- Form 2Form 2_Tej Elevia C_June 24.pdf · uploaded 18 Jul 2025Source
- Form 2Form 2_Tej Elevia C_March 24.pdf · uploaded 18 Jul 2025Source
- Form 2Form 2_Tej Elevia C_ Dec 23.pdf · uploaded 18 Jul 2025Source
- Form 2Form 2_Tej Elevia C Bldg - Sept 23.pdf · uploaded 18 Jul 2025Source
- Form 2Form 2 - Tej Elevia C- June 23.pdf · uploaded 18 Jul 2025Source
- Form 3Form 3_Tej Elevia C_March 25.pdf · uploaded 18 Jul 2025Source
- Form 3Form 3_TejElevia C_Dec 24.pdf · uploaded 18 Jul 2025Source
- Form 3Form 3- CA certificate_Sept 2024.pdf · uploaded 18 Jul 2025Source
- Form 3Form 3 _Tej Elevia C_ June 24.pdf · uploaded 18 Jul 2025Source
- Form 3Form 3_Tej Elevia C_March 24.pdf · uploaded 18 Jul 2025Source
- Form 3Form 3 _Tej Elevia C_Dec 23.pdf · uploaded 18 Jul 2025Source
- Form 3Form 3_Tej Elevia C Bldg_Sept 23.pdf · uploaded 18 Jul 2025Source
- Form 3Form 3 Tej Elevia C Building_June23_signed.pdf · uploaded 18 Jul 2025Source
- Disclosure of Sold and Booked InventorySold Unsold_Elevia C_March 25.pdf · uploaded 18 Jul 2025Source
- Disclosure of Sold and Booked InventorySold and Unsold_Tejelevia C_Dec 24.pdf · uploaded 18 Jul 2025Source
- Disclosure of Sold and Booked InventorySold and Unsold_Tej Elevia C_Sept 2024.pdf · uploaded 18 Jul 2025Source
- Disclosure of Sold and Booked InventorySold and Unsold_Tej Elevia C_June 24.pdf · uploaded 18 Jul 2025Source
- Disclosure of Sold and Booked InventorySold and Unsold_Tej Elevia C_March 24.pdf · uploaded 18 Jul 2025Source
- Disclosure of Sold and Booked InventorySold Unsold_Tej Elevia C_Dec 23.pdf · uploaded 18 Jul 2025Source
- Disclosure of Sold and Booked InventorySold Unsold_Tej Elevia C_Sept 23.pdf · uploaded 18 Jul 2025Source
- Disclosure of Sold and Booked InventorySold Unsold_Tej Elevia C_June 23.pdf · uploaded 18 Jul 2025Source
- Withdrawal Update Form 1Form 1_TejElevia C_June 25.pdf · uploaded 21 Jul 2025Source
- Withdrawal Update Form 2Form 2_Tej Elevia C_June 25.PDF · uploaded 21 Jul 2025Source
- Withdrawal Update Form 3Form 3_TRLLP C Building_June 25.pdf · uploaded 21 Jul 2025Source
- Withdrawal Update Form 1Form 1_Tej Elevia Building C_Sept 25.pdf · uploaded 22 Oct 2025Source
- Withdrawal Update Form 2Form 2_Tej Elevia Building C_Sept 25.pdf · uploaded 22 Oct 2025Source
- Withdrawal Update Form 3Form 3_TejElevia C_Sept 25.pdf · uploaded 22 Oct 2025Source
- Form 2A (FY 2023-2024)Form 2A_Tej Elevia Building C_2023-24.pdf · uploaded 5 Nov 2025Source
- Form 2A (FY 2024-2025)Form 2A Tej Elevia C Building_2024-25.pdf · uploaded 5 Nov 2025Source
- Form 5 (FY 2023-2024)Form 5_Tej Elevia_C WING_2023-24.pdf · uploaded 14 Nov 2025Source
- Form 5 (FY 2024-2025)Form 5_Tej Elevia C_2024-25.pdf · uploaded 14 Nov 2025Source
- Withdrawal Update Form 1Form 1 C Dec 25.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 2Tej Elevia Bldg C - Form 2 Dec 25.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 3Tej Elevia Bldg C - Form 3 Dec 25.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 1Form 1 C Dec 25.pdf · uploaded 21 Jan 2026Source
- Withdrawal Update Form 2Tej Elevia Bldg C - Form 2 Dec 25.pdf · uploaded 21 Jan 2026Source
- Withdrawal Update Form 3Tej Elevia Bldg C - Form 3 Dec 25.pdf · uploaded 21 Jan 2026Source
- Withdrawal Update Form 1Form-1 Tej Elevia C (1).pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 2Form 2 Elevia C bld.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 3Form 3 Tej Elevia C_compressed.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 1form1 tejelevia c building.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 1form1 tejelevia c building.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 2FORM 2_Elevia C June 26.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 2FORM 2_Elevia C June 26.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 3Form-3 C building_001.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 3Form-3 C building_001.pdf · uploaded 20 Jul 2026Source
- Form 2A (FY 2025-2026)Tej Elevia Tower C Form-2A.pdf · uploaded 28 Jul 2026Source
- Form 5 (FY 2025-2026)3_Form -5 - Tej Elevia C.pdf · uploaded 10 Oct 2026Source
Technical
- DocumentLayout approval.pdf · uploaded 13 Mar 2023Source
- Document1-sheet no 1-8_compressed.pdf · uploaded 13 Mar 2023Source
- Document4 OUT OF 8.pdf · uploaded 13 Mar 2023Source
- Other – TechnicalPlot area details.pdf · uploaded 24 Mar 2023Source
- Document4 Copy of Layout Approval (in case of layout).pdf · uploaded 12 Apr 2023Source
- Document8 Building Plan Approval (IOD).pdf · uploaded 12 Apr 2023Source
Technical (Architect)
Technical (Engineer)
- Document8 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 21 Oct 2024Source
- DocumentForm 2 tej elevia building C_Sept 24.pdf · uploaded 12 Nov 2024Source
- DocumentForm 2 Tej Elevia C_Dec 24.pdf · uploaded 17 Jan 2025Source
- DocumentFORM 2_Elevia C June 26.pdf · uploaded 8 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 72 4 73 74 75 2 1 Plot No 31 32
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2BHK116 units in all
- Address
- 72 4 73 74 75 2 1 Plot No 31 32, Baner, BanerPIN 411045
- Village
- Pune (M Corp.), Pune City taluka
- Location
- 18.56046, 73.78370
- Land area for this project
- 1,561 sq m (16,803 sq ft)
- Permissible built-up area
- 15,068 sq m (1,62,190 sq ft)
- Sanctioned built-up area
- 10,803 sq m (1,16,283 sq ft)
- Recreational open space
- 159 sq m (1,710 sq ft)
- Designated bank account
- 85
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
72 4 73 74 75 2 1 Plot No 31 32
Boundaries
- North
- S No 73 Pvt Plot No 1
- South
- 24 Mtr Road
- East
- S No 74 and 75 Part
- West
- S No 72 Part 4
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking116 units
96 of 116 units booked (83%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 26.75 sq m · 288 sq ft | 6 | 4 |
| 2BHK | 51.01 sq m · 549 sq ft | 52 | 44 |
| 2BHK | 56.47 sq m · 608 sq ft | 6 | 4 |
| 2BHK | 57.48 sq m · 619 sq ft | 52 | 44 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals7
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Deepali S Agarwal | — |
| Chartered accountant | P B Shah | — |
| Chartered accountant | Ritesh Chandrakant Gujar | — |
| Engineer | Ganesh Pillay | — |
| Engineer | Rajendra Bhasme | — |
| Engineer | Suresh Fulari | — |
| Engineer | Yuvraj Kamble | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Baner
- Sai Residency Cooperative Housing Society LimitedRERA PR1260002602726
- Merlin VertexRERA PC1261012602688
- Bliss NestRERA PR1260002602296
- GaurinandanRERA PR1260002602194
- One Space₹9,840 a sq ft
- Anantashree₹8,070 a sq ft
- Fernnvale₹10,120 a sq ft
- Avika ResidencesRERA PR1260002601571
All 3,195 projects in Baner · Compare Tejelevia Building C with another project
Tejelevia Building C in numbers
Registered deals, summarised
Deedo has 3 registered documents at Tejelevia Building C, from Mar 2021 to Feb 2025: 3 leave and licence agreements.
- Are properties at Tejelevia Building C rented out?
- Yes: 3 leave and licence agreements are registered at Tejelevia Building C, at a median rent since Mar 2021 of about ₹20,000 a month with a deposit of about ₹50,000.
- Where does this data come from?
- The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Tejelevia Building C by Deedo, last updated with deals registered in Feb 2025.
Latest deal · Rental · Feb 2025
₹20–50k / month