Skip to content
Residential / Group Housing · 3 buildings · 272 unitsRERA P52100017218 +2

Rahul Arcus

Deedo IDDP-PUN-684J

MahaRERA shows it completed, after its date was pushed back 1 year; no MahaRERA orders on record; 99% of its units are booked.

Baner, Pune 411045 · Property rates in Baner · by Raichand Brijlal Kunkulol · 60% of its projects kept the RERA date

DeliveryCompletedCompletion / occupancy certificate on MahaRERA · after a 1 yr extensionRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales99% booked268 of 272 units · as the promoter reported to MahaRERAPrice₹14,120 /sq ft24.6% above Baner · 65 registered sales

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed, after its date was pushed back 1 year

  • P52100017218Registered 23 Jul 2018, completion promised 31 Dec 2019, revised to 30 Dec 2020.
  • P52100020396Registered 9 Apr 2019, completion promised 30 Mar 2021.
  • P52100022202Registered 5 Sep 2019, completion promised 30 Mar 2022.

1 extension certificate on record.

3 registrations · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

All 290 deeds →
  • Rental · Oct 2026
  • Rental · Oct 2026
  • Rental · Sep 2026
  • Rental · Sep 2026
  • Rental · Sep 2026
  • Rental · Aug 2026
  • Rental · 22 mo · Aug 2026
  • Rental · Jul 2026
  • Rental · Jul 2026
  • Rental · Jul 2026
Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Oct 2026Bldg D - Phase IV · 701Rental—View Rental, Oct 2026
Oct 2026Bldg D - Phase IV · 304Rental—View Rental, Oct 2026
Sep 2026Bldg D - Phase IV · 1002Rental—View Rental, Sep 2026
Sep 2026Bldg B Phase II · 205Rental—View Rental, Sep 2026
Sep 2026Unit 901Rental1,876 sq ftView Rental, Sep 2026
Aug 2026Bldg D - Phase IV · 1502Rental—View Rental, Aug 2026
Aug 2026Bldg B Phase II · 107Rental—View Rental, Aug 2026
Jul 2026Bldg B Phase II · 108Rental—View Rental, Jul 2026
Jul 2026Bldg B Phase II · 807Rental—View Rental, Jul 2026
Jul 2026Bldg B Phase II · B-1402Rental—View Rental, Jul 2026

3 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrations3
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210001721823 Jul 201831 Dec 201930 Dec 2020Raichand Brijlal KunkulolProject page
P521000203969 Apr 201930 Mar 202130 Mar 2021Raichand Brijlal KunkulolProject page
P521000222025 Sep 201930 Mar 202230 Mar 2022Raichand Brijlal KunkulolProject page
Documents95

4 documents held by Deedo, 91 filings listed on MahaRERA's project page

Registration certificate (3)

  • Registration certificateP52100017218 · 23 Jul 2018ViewSource
  • Registration certificateP52100020396 · 18 May 2020ViewSource
  • Registration certificateP52100022202 · 8 Sep 2021ViewSource

Extension certificate

  • Extension certificateP52100017218 · 7 Jul 2020ViewSource

Legal

  • Declaration Form BP52100017218 · Form B Phase III.pdf · uploaded 19 Jun 2018Source
  • Legal Title reportP52100017218 · Title Search.pdf · uploaded 6 Jul 2018Source
  • Declaration Form BP52100020396 · Form B Bldg B.pdf · uploaded 4 Apr 2019Source
  • Legal Title reportP52100020396 · Title Certificate.pdf · uploaded 4 Apr 2019Source
Show all 95 documentsShow fewer documents

Legal

  • Declaration Form BP52100022202 · Form - B Affidavit Cum Declaration.pdf · uploaded 7 Aug 2019Source
  • Legal Title reportP52100022202 · Title Certificate.pdf · uploaded 24 Aug 2019Source

Migrated

  • 1 Details of encumbrancesP52100017218 · Bldg C Declaration regarding Encumbrances.pdf · uploaded 19 Jun 2018Source
  • 1 Declaration in FORM BP52100017218 · Form B Phase III.pdf · uploaded 19 Jun 2018Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100017218 · Bldg C Architect Certificate.pdf · uploaded 19 Jun 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017218 · Engineer Certificate Phase III.pdf · uploaded 19 Jun 2018Source
  • 1 Certificates of CA (Form 3)P52100017218 · C ACertificate Phase III.pdf · uploaded 19 Jun 2018Source
  • 1 Copy of the legal title reportP52100017218 · Title Search.pdf · uploaded 6 Jul 2018Source
  • 1 Copy of Layout Approval (in case of layout)P52100017218 · Lay out.pdf · uploaded 16 Jul 2018Source
  • 1 Building Plan Approval (IOD)P52100017218 · I O D.pdf · uploaded 16 Jul 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100017218 · Commencement.pdf · uploaded 16 Jul 2018Source
  • 1 Proforma of Allotment letterP52100017218 · Agreement of Sale.pdf · uploaded 16 Jul 2018Source
  • 1 Copy of the legal title reportP52100020396 · Title Certificate.pdf · uploaded 4 Apr 2019Source
  • 1 Details of encumbrancesP52100020396 · Encumbrances Bldg B.pdf · uploaded 4 Apr 2019Source
  • 1 Building Plan Approval (IOD)P52100020396 · I O D.pdf · uploaded 4 Apr 2019Source
  • 1 Declaration in FORM BP52100020396 · Form B Bldg B.pdf · uploaded 4 Apr 2019Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100020396 · Bldg B- Architect Certificate.pdf · uploaded 4 Apr 2019Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100020396 · B Bldg Engineer Certificate.pdf · uploaded 4 Apr 2019Source
  • 1 Certificates of CA (Form 3)P52100020396 · Bldg B - C A Certificate.pdf · uploaded 4 Apr 2019Source
  • 1 Proforma of Allotment letterP52100020396 · Bldg -B - AGREEMENT OF SALE.pdf · uploaded 4 Apr 2019Source
  • 1 Copy of Layout Approval (in case of layout)P52100020396 · Copy of layout approval.pdf · uploaded 8 Apr 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100020396 · Commencement.pdf · uploaded 8 Apr 2019Source
  • 2 Proforma of Allotment letterP52100020396 · Agreement Draft Bldg B_17_04_19.pdf · uploaded 17 Apr 2019Source
  • 3 Proforma of Allotment letterP52100020396 · Agreement of Sale - 26-4-2019.pdf · uploaded 26 Apr 2019Source
  • 1 Details of encumbrancesP52100022202 · Encumbrances.pdf · uploaded 7 Aug 2019Source
  • 1 Copy of Layout Approval (in case of layout)P52100022202 · Lay out.pdf · uploaded 7 Aug 2019Source
  • 1 Building Plan Approval (IOD)P52100022202 · IOD.pdf · uploaded 7 Aug 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100022202 · Commencement.pdf · uploaded 7 Aug 2019Source
  • 1 Declaration in FORM BP52100022202 · Form - B Affidavit Cum Declaration.pdf · uploaded 7 Aug 2019Source
  • 1 Certificates of CA (Form 3)P52100022202 · D - C A Certificate.PDF · uploaded 7 Aug 2019Source
  • 1 Proforma of Allotment letterP52100022202 · D - Agreement of Sale.pdf · uploaded 7 Aug 2019Source
  • 1 Copy of the legal title reportP52100022202 · Title Certificate.pdf · uploaded 24 Aug 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5)P52100017218 · Rera Phase III 30-Sep-2019 23-06-17(1).pdf · uploaded 30 Sep 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)P52100020396 · Form 5 FY 19-20 B Bldg.pdf · uploaded 8 Jan 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)P52100022202 · Form 5 FY 19-20 D Bldg.pdf · uploaded 8 Jan 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)P52100017218 · Form 5 FY 19-20 C Bldg.pdf · uploaded 8 Jan 2021Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100017218 · Completion Certificate 1.pdf · uploaded 19 Feb 2021Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100017218 · Completion Certificate 2.pdf · uploaded 19 Feb 2021Source
  • 3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100017218 · Completion Certificate 3.pdf · uploaded 19 Feb 2021Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)P52100020396 · Form 4 Bldg B.pdf · uploaded 1 Jun 2021Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)P52100017218 · Form 4 - Bldg C.pdf · uploaded 1 Jun 2021Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100020396 · Completion.pdf · uploaded 16 Jun 2021Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100020396 · Completion.pdf · uploaded 16 Jun 2021Source
  • 3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100020396 · Completion.pdf · uploaded 16 Jun 2021Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100020396 · Engineer Certificate - B.pdf · uploaded 15 Aug 2021Source
  • 2 Certificates of CA (Form 3)P52100020396 · C A Certificate - B.pdf · uploaded 15 Aug 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100022202 · Engineer Certificate D.pdf · uploaded 15 Aug 2021Source
  • 2 Certificates of CA (Form 3)P52100022202 · C A Certificate - D.pdf · uploaded 15 Aug 2021Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100017218 · Engineer Certificate - C.pdf · uploaded 15 Aug 2021Source
  • 2 Certificates of CA (Form 3)P52100017218 · C A Certificate -C.pdf · uploaded 15 Aug 2021Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)P52100020396 · Form 4-B (1).pdf · uploaded 17 Aug 2021Source
  • 2 Architect’s Certificate on Completion of Project (Form 4)P52100017218 · Form 4-C (1).pdf · uploaded 17 Aug 2021Source
  • 4 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100020396 · Completion Certificate - A-B-C-D.pdf · uploaded 23 Sep 2021Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100022202 · Completion Certificate - A-B-C-D.pdf · uploaded 23 Sep 2021Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100022202 · Certificate Completion.pdf · uploaded 23 Sep 2021Source
  • 3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100022202 · Completion Certificate.pdf · uploaded 23 Sep 2021Source
  • 4 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100022202 · Completion Certificate.pdf · uploaded 23 Sep 2021Source
  • 4 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100017218 · Completion Certificate - A-B-C-D.pdf · uploaded 23 Sep 2021Source
  • 3 Architect’s Certificate on Completion of Project (Form 4)P52100020396 · B - Form 4.pdf · uploaded 24 Sep 2021Source
  • 3 Architect’s Certificate on Completion of Project (Form 4)P52100017218 · C - Form 4.pdf · uploaded 24 Sep 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P52100020396 · Form 5 - Bldg B.PDF · uploaded 29 Sep 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P52100022202 · Form 5 - Bldg D.PDF · uploaded 29 Sep 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P52100017218 · Form 5 - Bldg C.PDF · uploaded 29 Sep 2021Source
  • 4 Architect’s Certificate on Completion of Project (Form 4)P52100022202 · Form 4 - Bldg D.pdf · uploaded 22 Feb 2022Source
  • 5 Architect’s Certificate on Completion of Project (Form 4)P52100020396 · Form 4 - Bldg B.pdf · uploaded 28 Feb 2022Source
  • 5 Architect’s Certificate on Completion of Project (Form 4)P52100017218 · Form 4 - Bldg C.pdf · uploaded 28 Feb 2022Source
  • 5 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100020396 · Bldg B Completion.pdf · uploaded 31 Mar 2023Source
  • 5 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100022202 · Bldg D Completion.pdf · uploaded 31 Mar 2023Source
  • 6 Architect’s Certificate on Completion of Project (Form 4)P52100022202 · Form 4 - Bldg D.pdf · uploaded 31 Mar 2023Source
  • 5 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentP52100017218 · Bldg C Completion.pdf · uploaded 31 Mar 2023Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)P52100020396 · Arcus - Socioety Registration Certificate.pdf · uploaded 4 Mar 2024Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)P52100022202 · Arcus - Socioety Registration Certificate.pdf · uploaded 4 Mar 2024Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)P52100017218 · Arcus - Socioety Registration Certificate.pdf · uploaded 4 Mar 2024Source
  • 2 Status of Formation of Legal Entity (Society/Co Op etc.)P52100020396 · Society Formation.pdf · uploaded 20 Mar 2024Source
  • 2 Status of Formation of Legal Entity (Society/Co Op etc.)P52100022202 · Society Formation.pdf · uploaded 20 Mar 2024Source
  • 2 Status of Formation of Legal Entity (Society/Co Op etc.)P52100017218 · Society Formation.pdf · uploaded 20 Mar 2024Source

Technical

  • DocumentP52100017218 · I O D.pdf · uploaded 16 Jul 2018Source
  • DocumentP52100017218 · Lay out.pdf · uploaded 16 Jul 2018Source
  • DocumentP52100020396 · I O D.pdf · uploaded 4 Apr 2019Source
  • DocumentP52100020396 · Copy of layout approval.pdf · uploaded 8 Apr 2019Source
  • DocumentP52100022202 · IOD.pdf · uploaded 7 Aug 2019Source
  • DocumentP52100022202 · Lay out.pdf · uploaded 7 Aug 2019Source

Technical (Architect)

  • DocumentP52100017218 · Bldg C Architect Certificate.pdf · uploaded 19 Jun 2018Source
  • DocumentP52100020396 · Bldg B- Architect Certificate.pdf · uploaded 4 Apr 2019Source

Technical (Engineer)

  • DocumentP52100020396 · Engineer Certificate - B.pdf · uploaded 15 Aug 2021Source
  • DocumentP52100022202 · Engineer Certificate D.pdf · uploaded 15 Aug 2021Source
  • DocumentP52100017218 · Engineer Certificate - C.pdf · uploaded 15 Aug 2021Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 47 PART

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Phases
3
Unit types
1 room toilet, 2 BHK, 2BHK, 3 BHK, 3BHK272 units in all
Address
47 Part, 18 Mt D P Road From Mumbai Banglore Express Highway, Near Audi ShowroomPIN 411045
Village
Baner, Haveli taluka
Land area for this project
1,336 sq m (14,380 sq ft)
Permissible built-up area
6,564 sq m (70,652 sq ft)
Sanctioned built-up area
5,177 sq m (55,719 sq ft)
Designated bank account
171
Developed in phases
No
Also registered as
Rahul Arcus-Phase III- Bldg C, Rahul Arcus-Bldg B, Rahul Arcus - Bldg D

Survey, CTS, gat or plot numbers

47 PART

Land as published on MahaRERA's project page

47 PART

Boundaries

North
Bldg B
South
Bldg D
East
Proposed Bldg E
West
Open Space

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking272 units

268 of 272 units booked (99%), as the promoter reported to MahaRERA

1 room toilet · 2 units2 BHK · 106 units2BHK · 32 units3 BHK · 99 units3BHK · 33 units
RERABuildingTypeCarpet areaUnitsBooked
P52100020396Bldg B Phase II1 room toilet20.4 sq m · 220 sq ft10
P52100020396Bldg B Phase II1 room toilet26.5 sq m · 285 sq ft10
P52100020396Bldg B Phase II2 BHK85.64 sq m · 922 sq ft1616
P52100020396Bldg B Phase II2 BHK85.98 sq m · 925 sq ft1818
P52100020396Bldg B Phase II2 BHK86.31 sq m · 929 sq ft1515
P52100020396Bldg B Phase II2 BHK86.6 sq m · 932 sq ft1717
P52100020396Bldg B Phase II2 BHK90.46 sq m · 974 sq ft3232
P52100020396Bldg B Phase II2 BHK146.17 sq m · 1,573 sq ft11
Show all 30 unit rowsShow fewer unit rows
RERABuildingTypeCarpet areaUnitsBooked
P52100020396Bldg B Phase II2 BHK147.09 sq m · 1,583 sq ft11
P52100020396Bldg B Phase II2 BHK168.41 sq m · 1,813 sq ft11
P52100020396Bldg B Phase II2 BHK169.47 sq m · 1,824 sq ft11
P52100020396Bldg B Phase II2BHK87.52 sq m · 942 sq ft3232
P52100022202Bldg D - Phase IV2 BHK89.89 sq m · 968 sq ft11
P52100022202Bldg D - Phase IV2 BHK93.56 sq m · 1,007 sq ft11
P52100022202Bldg D - Phase IV3 BHK116.66 sq m · 1,256 sq ft1616
P52100022202Bldg D - Phase IV3 BHK119.21 sq m · 1,283 sq ft1515
P52100022202Bldg D - Phase IV3 BHK119.86 sq m · 1,290 sq ft1515
P52100022202Bldg D - Phase IV3 BHK181.89 sq m · 1,958 sq ft22
P52100022202Bldg D - Phase IV3 BHK198.44 sq m · 2,136 sq ft11
P52100022202Bldg D - Phase IV3BHK116.02 sq m · 1,249 sq ft1717
P52100017218Rahul Arcus-Phase III-Bldg C2 BHK89.89 sq m · 968 sq ft11
P52100017218Rahul Arcus-Phase III-Bldg C2 BHK93.56 sq m · 1,007 sq ft11
P52100017218Rahul Arcus-Phase III-Bldg C3 BHK116.02 sq m · 1,249 sq ft1616
P52100017218Rahul Arcus-Phase III-Bldg C3 BHK116.66 sq m · 1,256 sq ft1515
P52100017218Rahul Arcus-Phase III-Bldg C3 BHK119.21 sq m · 1,283 sq ft1615
P52100017218Rahul Arcus-Phase III-Bldg C3 BHK158.55 sq m · 1,707 sq ft11
P52100017218Rahul Arcus-Phase III-Bldg C3 BHK177.5 sq m · 1,911 sq ft11
P52100017218Rahul Arcus-Phase III-Bldg C3 BHK198.67 sq m · 2,138 sq ft10
P52100017218Rahul Arcus-Phase III-Bldg C3BHK119.86 sq m · 1,290 sq ft1515
P52100017218Rahul Arcus-Phase III-Bldg C3BHK182 sq m · 1,959 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals7

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectPandit Joshi & Associates—P52100022202
ArchitectPandit Joshi & Associates—P52100020396
ArchitectPandit Joshi & Associates—P52100017218
Chartered accountantVinod N Nikam & Co—P52100022202
EngineerMr Sham Rajput—P52100022202
EngineerRuikar & Associates—P52100017218
OtherMr Ishwar Patel—P52100022202

Source: MahaRERA project page. Contact details are not shown.

Rahul Arcus in numbers

Registered deals, summarised

Deedo has 290 registered documents at Rahul Arcus, from Apr 2019 to Oct 2026: 65 sales, 135 leave and licence agreements, 83 mortgages. The median registered sale since Apr 2019 works out to about ₹14,100 per sq ft, at a median of ₹1.01 Cr a deal; 17% of sales were resales.

What is the price per sq ft at Rahul Arcus?
The median registered sale since Apr 2019 works out to about ₹14,100 per sq ft, at a median of ₹1.01 Cr a deal; 17% of sales were resales.
How many properties have been sold at Rahul Arcus?
65 sales are registered at Rahul Arcus, 11 of them resales.
Are properties at Rahul Arcus rented out?
Yes: 135 leave and licence agreements are registered at Rahul Arcus, at a median rent since Apr 2019 of about ₹37,000 a month with a deposit of about ₹1,00,000.
Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Rahul Arcus by Deedo, last updated with deals registered in Oct 2026.

Latest deal · Rental · Oct 2026

₹20–50k / month

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · registered documents (Index II)Data through is when MahaRERA's project page was last read.Report a problemMethodology