Pinewood Phase II
Deedo IDDP-PUN-VNYBCompletion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 41% of its units are booked.
Baner, Pune 411045 · Property rates in Baner · by Sainath Buildcon
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2028
- This projectRegistered 29 Feb 2024, completion promised 31 Dec 2027, revised to 30 Apr 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
- Mortgage · Aug 2024No amount
| Month | Flat | Kind | Area | Price | Record |
|---|---|---|---|---|---|
| Aug 2024 | Main building · 1202 | Mortgage | — | View Mortgage, Aug 2024 |
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100055098
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100055098 | 29 Feb 2024 | 31 Dec 2027 | 30 Apr 2028 | Sainath Buildcon | Project page |
Documents126
1 document held by Deedo, 125 filings listed on MahaRERA's project page
Finance
- PAN Cardpan.pdf · uploaded 21 Nov 2023Source
Legal
- Declaration Form BDeclaration of Form B.pdf · uploaded 30 Nov 2023Source
- Other – LegalPinewoodNOC.pdf · uploaded 29 Dec 2023Source
- Other – Legalsale deed 9R rohan builder.pdf · uploaded 18 Jan 2024Source
- Other – Legalखरेदी खत 57-3 15R.pdf · uploaded 18 Jan 2024Source
- Other – LegalDeclaration Final.pdf · uploaded 6 Feb 2024Source
- Other – Legalbaner scan 15r.pdf · uploaded 6 Feb 2024Source
Show all 126 documentsShow fewer documents
Legal
Migrated
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1.pdf · uploaded 28 Oct 2023Source
- 1 PAN Cardpan.pdf · uploaded 21 Nov 2023Source
- 1 Copy of Layout Approval (in case of layout)LayoutPlan.pdf · uploaded 30 Nov 2023Source
- 1 Building Plan Approval / NA Order for plotted development1outof6.pdf · uploaded 30 Nov 2023Source
- 2 Building Plan Approval / NA Order for plotted development2outof6.pdf · uploaded 30 Nov 2023Source
- 3 Building Plan Approval / NA Order for plotted development3outof6.pdf · uploaded 30 Nov 2023Source
- 4 Building Plan Approval / NA Order for plotted development4outof6.pdf · uploaded 30 Nov 2023Source
- 5 Building Plan Approval / NA Order for plotted development5outof6.pdf · uploaded 30 Nov 2023Source
- 6 Building Plan Approval / NA Order for plotted development6outof6.pdf · uploaded 30 Nov 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 30 Nov 2023Source
- 1 Declaration about Commencement CertificateDeclaration about Commencement.pdf · uploaded 30 Nov 2023Source
- 1 Declaration in FORM BDeclaration of Form B.pdf · uploaded 30 Nov 2023Source
- 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 22 Dec 2023Source
- 1 Deviation Report with respect to Allotment letterNo Deviation Allotment.pdf · uploaded 29 Dec 2023Source
- 1 Other – LegalPinewoodNOC.pdf · uploaded 29 Dec 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 - Final - 170124.pdf · uploaded 17 Jan 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsRNRDIN.pdf · uploaded 17 Jan 2024Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsSRTDIN.pdf · uploaded 17 Jan 2024Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsARRDIN.pdf · uploaded 17 Jan 2024Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsHRPDIN.pdf · uploaded 17 Jan 2024Source
- 5 Disclosure of Interest in Other Real Estate OrganizationsVVKDIN.pdf · uploaded 17 Jan 2024Source
- 6 Disclosure of Interest in Other Real Estate OrganizationsPSTDIN01.pdf · uploaded 17 Jan 2024Source
- 7 Disclosure of Interest in Other Real Estate OrganizationsAUTDIN.pdf · uploaded 17 Jan 2024Source
- 1 a Details of encumbrances concerned to FinanceFinancial Encumbrance 18 Jan 24 · 05·44·40.pdf · uploaded 18 Jan 2024Source
- 2 a Details of encumbrances concerned to FinanceLegalEncumbrance.pdf · uploaded 18 Jan 2024Source
- 1 b Details of encumbrances concerned to LegalFinancial Encumbrance 18 Jan 24 · 05·44·40.pdf · uploaded 18 Jan 2024Source
- 2 b Details of encumbrances concerned to LegalLegalEncumbrance.pdf · uploaded 18 Jan 2024Source
- 1 CERSAI detailsCERSAIDeclaration.pdf · uploaded 18 Jan 2024Source
- 2 CERSAI detailsFinancial Encumbrance 18 Jan 24 · 05·44·40.pdf · uploaded 18 Jan 2024Source
- 8 Disclosure of Interest in Other Real Estate OrganizationsRHPDIN.pdf · uploaded 18 Jan 2024Source
- 1 Proforma of Agreement for saleAgrmeent_For_Sale (3).pdf · uploaded 18 Jan 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Declaration.pdf · uploaded 18 Jan 2024Source
- 2 Other – Legalsale deed 9R rohan builder.pdf · uploaded 18 Jan 2024Source
- 3 Other – Legalखरेदी खत 57-3 15R.pdf · uploaded 18 Jan 2024Source
- 7 Building Plan Approval / NA Order for plotted development1outof6.pdf · uploaded 31 Jan 2024Source
- 1 Other – Technical1outof6.pdf · uploaded 31 Jan 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Pinewood Phase II FORM 3 Chartered Accountant Certificate 31012024.pdf · uploaded 1 Feb 2024Source
- 1 Deviation Report with respect to model copy of AgreementDeviation in agreement for sale.pdf · uploaded 1 Feb 2024Source
- 2 Proforma of Agreement for saleAgrmeent For Sale.pdf · uploaded 6 Feb 2024Source
- 4 Other – LegalDeclaration Final.pdf · uploaded 6 Feb 2024Source
- 5 Other – Legalbaner scan 15r.pdf · uploaded 6 Feb 2024Source
- 6 Other – LegalFlow of said land final.pdf · uploaded 6 Feb 2024Source
- 1 Copy of the legal title reportfinal search upload 13022024.pdf · uploaded 13 Feb 2024Source
- 3 Proforma of Agreement for sale2 Proforma of Agreement for sale uploaded initially.pdf · uploaded 13 Feb 2024Source
- 2 Deviation Report with respect to model copy of AgreementDeviation Report AFS.pdf · uploaded 13 Feb 2024Source
- 7 Other – Legalconsent letter org landowners.pdf · uploaded 13 Feb 2024Source
- 8 Building Plan Approval / NA Order for plotted developmentBldg pLan.pdf · uploaded 14 Feb 2024Source
- 8 Other – Legal5R entire sale deed.pdf · uploaded 21 Feb 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 2.pdf · uploaded 3 Feb 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate.pdf · uploaded 3 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_compressed.pdf · uploaded 3 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 3 Feb 2025Source
- 1 Disclosure of sold/ booked inventorySold Unsold.pdf · uploaded 3 Feb 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)No Progress Q1.pdf · uploaded 4 Feb 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)No progress Q2.pdf · uploaded 4 Feb 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)No Progress Q1.pdf · uploaded 4 Feb 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)No Progress Q1.pdf · uploaded 4 Feb 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)No progress Q2.pdf · uploaded 4 Feb 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)No progress Q2.pdf · uploaded 4 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architects Certificate.pdf · uploaded 11 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q4 FY 2024-25 Pinewood Phase II FORM 3 Chartered Accountant Certificate 31032025.pdf · uploaded 11 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Engineer Certificate.pdf · uploaded 11 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryInventory decleration.pdf · uploaded 11 Apr 2025Source
- Form 1Form 1 Architects Certificate.pdf · uploaded 19 Jul 2025Source
- Form 1Form 1 Architects Certificate 2.pdf · uploaded 19 Jul 2025Source
- Form 2FORM 2 Engineer Certificate.pdf · uploaded 19 Jul 2025Source
- Form 2FORM 2 Engineer Certificate.pdf · uploaded 19 Jul 2025Source
- Form 3Q4 FY 2024-25 Pinewood Phase II FORM 3 Chartered Accountant Certificate 31032025.pdf · uploaded 19 Jul 2025Source
- Form 3Q1 FY 2025-26 Pinewood Phase II FORM 3 Chartered Accountant Certificate 30062025 (2).pdf · uploaded 19 Jul 2025Source
- Disclosure of Sold and Booked InventoryInventory decleration.pdf · uploaded 19 Jul 2025Source
- Disclosure of Sold and Booked InventorySold Unsold.pdf · uploaded 19 Jul 2025Source
- Form 1Form 1 Architects Certificate 2.pdf · uploaded 19 Nov 2025Source
- Form 2FORM 2 Engineer Certificate as on 30th September 2025.pdf · uploaded 19 Nov 2025Source
- Form 3Q2 FY 2025-26 Pinewood Phase II FORM 3 Chartered Accountant Certificate 30092025.pdf · uploaded 19 Nov 2025Source
- Disclosure of Sold and Booked InventorySold Unsold.pdf · uploaded 19 Nov 2025Source
- Form 1Q3 Form 1 Architects Certificate.pdf · uploaded 22 Jan 2026Source
- Form 2Q3 FORM 2 Engineer Certificate.pdf · uploaded 22 Jan 2026Source
- Form 3Q3 FY 2025-26 Pinewood Phase II FORM 3 Chartered Accountant Certificate 31122025 (1).pdf · uploaded 22 Jan 2026Source
- Disclosure of Sold and Booked InventoryQ3 Disclosure of Sold Unsold Inventory.pdf · uploaded 22 Jan 2026Source
- Withdrawal Update Form 1Form 1 Architects Certificate Q4 FY 2025-26.pdf · uploaded 9 May 2026Source
- Withdrawal Update Form 2FORM 2 Engineer Certificate Q4 FY 2025-26.pdf · uploaded 9 May 2026Source
- Withdrawal Update Form 3Q4 FY 2025-26 Pinewood Phase II FORM 3 Chartered Accountant Certificate 31032026 U.pdf · uploaded 9 May 2026Source
Technical
- DocumentLayoutPlan.pdf · uploaded 30 Nov 2023Source
- Document1outof6.pdf · uploaded 30 Nov 2023Source
- Document2outof6.pdf · uploaded 30 Nov 2023Source
- Document3outof6.pdf · uploaded 30 Nov 2023Source
- Document4outof6.pdf · uploaded 30 Nov 2023Source
- Document5outof6.pdf · uploaded 30 Nov 2023Source
- Document6outof6.pdf · uploaded 30 Nov 2023Source
- Document1outof6.pdf · uploaded 31 Jan 2024Source
- Other – Technical1outof6.pdf · uploaded 31 Jan 2024Source
- DocumentBldg pLan.pdf · uploaded 14 Feb 2024Source
- Document2-11.pdf · uploaded 19 May 2026Source
- Document3-11.pdf · uploaded 19 May 2026Source
- Document4-11.pdf · uploaded 19 May 2026Source
- Document5-11.pdf · uploaded 19 May 2026Source
- Document6-11.pdf · uploaded 19 May 2026Source
- Document7-11.pdf · uploaded 19 May 2026Source
- Document8-11.pdf · uploaded 19 May 2026Source
- Document9-11.pdf · uploaded 19 May 2026Source
- Document10-11.pdf · uploaded 19 May 2026Source
- Document11-11.pdf · uploaded 19 May 2026Source
- Document1-11.pdf · uploaded 20 May 2026Source
Technical (Architect)
- DocumentForm 2.pdf · uploaded 3 Feb 2025Source
- DocumentForm 1 Architect Certificate.pdf · uploaded 3 Feb 2025Source
- DocumentNo Progress Q1.pdf · uploaded 4 Feb 2025Source
- DocumentNo progress Q2.pdf · uploaded 4 Feb 2025Source
- DocumentForm 1 Architects Certificate.pdf · uploaded 11 Apr 2025Source
- DocumentForm 1 Architects Certificate Q4 FY 2025-26.pdf · uploaded 9 May 2026Source
Technical (Engineer)
- DocumentNo Progress Q1.pdf · uploaded 4 Feb 2025Source
- DocumentNo progress Q2.pdf · uploaded 4 Feb 2025Source
- DocumentNo progress Q2.pdf · uploaded 4 Feb 2025Source
- DocumentFORM 2 Engineer Certificate.pdf · uploaded 11 Apr 2025Source
- DocumentFORM 2 Engineer Certificate Q4 FY 2025-26.pdf · uploaded 9 May 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 57/3 +58/2
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 3BHK, 1BHK, 2BHK56 units in all
- Address
- 57/3 +58/2, Baner, BanerPIN 411045
- Village
- Baner, Haveli taluka
- Land area for this project
- 6,900 sq m (74,271 sq ft)
- Permissible built-up area
- 10,403 sq m (1,11,979 sq ft)
- Sanctioned built-up area
- 10,403 sq m (1,11,979 sq ft)
- Recreational open space
- 690 sq m (7,430 sq ft)
- Designated bank account
- 85
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
57/3 +58/2
Boundaries
- North
- S No 59 of village Baner
- South
- Rohan Leher S No57part
- East
- SNo60 Alakriti Society
- West
- S No 57part
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking56 units
23 of 56 units booked (41%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Wing C | 3BHK | 114.92 sq m · 1,237 sq ft | 3 | 1 |
| Wing C | 3BHK | 126.16 sq m · 1,358 sq ft | 23 | 14 |
| Wing D | 1BHK | 32.6 sq m · 351 sq ft | 3 | 0 |
| Wing D | 2BHK | 81.57 sq m · 878 sq ft | 12 | 2 |
| Wing D | 2BHK | 86.21 sq m · 928 sq ft | 15 | 6 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Mangesh Bhandekar | — |
| Chartered accountant | Phule Wagh & Associates LLP | — |
| Engineer | Umesh Madhukar Inamdar | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Baner
- Sai Residency Cooperative Housing Society LimitedRERA PR1260002602726
- Merlin VertexRERA PC1261012602688
- Bliss NestRERA PR1260002602296
- GaurinandanRERA PR1260002602194
- One Space₹9,840 a sq ft
- Anantashree₹8,070 a sq ft
- FernnvaleRERA PM1260002601647
- Avika ResidencesRERA PR1260002601571
All 3,195 projects in Baner · Compare Pinewood Phase II with another project
Pinewood Phase II in numbers
Registered deals, summarised
Deedo has 1 registered document at Pinewood Phase II, from Aug 2024 to Aug 2024: 1 mortgage.
- Where does this data come from?
- The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Pinewood Phase II by Deedo, last updated with deals registered in Aug 2024.
Latest deal · Mortgage · Aug 2024
Exact price & Index II