Chlorophyll
Deedo IDDP-PUN-CXXRIts promised completion date, Dec 2020, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 17% of its units are booked.
Baner, Pune 411045 · Property rates in Baner · by Capstone Landmarks Pvt Ltd
Buying a flat here?
See every deed registered on it.
Its promised completion date, Dec 2020, has passed and MahaRERA does not show it completed
- This projectRegistered 4 Aug 2017, completion promised 29 Dec 2020, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
- Primary sale · Dec 2022
- Rental · 36 mo · Nov 2026
- Rental · Oct 2026
- Rental · 3 mo · Aug 2026
- Rental · 33 mo · Apr 2026
- Rental · Mar 2026
- Rental · 22 mo · Feb 2026
- Rental · 24 mo · Feb 2026
- Mortgage · Dec 2025No amount
- Rental · Dec 2025
| Month | Flat | Kind | Area | Price | Record |
|---|---|---|---|---|---|
| Dec 2022 | Chlorophyll · 1402 | Primary sale | 1,596 sq ft | View Primary sale, Dec 2022 | |
| Nov 2026 | Chlorophyll · 1402 | Rental | — | View Rental, Nov 2026 | |
| Oct 2026 | Chlorophyll · 604 | Rental | — | View Rental, Oct 2026 | |
| Aug 2026 | Chlorophyll · 1402 | Rental | — | View Rental, Aug 2026 | |
| Apr 2026 | Chlorophyll · 1302 | Rental | — | View Rental, Apr 2026 | |
| Mar 2026 | Chlorophyll · 501 | Rental | — | View Rental, Mar 2026 | |
| Feb 2026 | Chlorophyll · 403 | Rental | — | View Rental, Feb 2026 | |
| Feb 2026 | Chlorophyll · 801 | Rental | — | View Rental, Feb 2026 | |
| Dec 2025 | Chlorophyll · 1002 | Mortgage | — | View Mortgage, Dec 2025 | |
| Dec 2025 | Chlorophyll · 803 | Rental | — | View Rental, Dec 2025 |
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100002770
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100002770 | 4 Aug 2017 | 29 Dec 2020 | 29 Dec 2020 | Capstone Landmarks Pvt Ltd | Project page |
Documents48
2 documents held by Deedo, 46 filings listed on MahaRERA's project page
Show all 48 documentsShow fewer documents
Migrated
- 2 PAN CardPAN card SVG.pdf · uploaded 28 Jul 2017Source
- 1 Details of encumbrancesIndex-II - Martgage deed 2.pdf · uploaded 28 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)sanction_plan_page_1.pdf · uploaded 28 Jul 2017Source
- 1 Building Plan Approval (IOD)sanction_plan_page_1.pdf · uploaded 28 Jul 2017Source
- 2 Building Plan Approval (IOD)sanction_plan_page_2.pdf · uploaded 28 Jul 2017Source
- 3 Building Plan Approval (IOD)sanction_plan_page_3.pdf · uploaded 28 Jul 2017Source
- 4 Building Plan Approval (IOD)sanction_plane_page_4.pdf · uploaded 28 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentcommencement certificate 420615.pdf · uploaded 28 Jul 2017Source
- 1 Declaration in FORM BForm B.pdf · uploaded 28 Jul 2017Source
- 1 Copy of the legal title reportCombined_Title_report Compressed.pdf · uploaded 29 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)rev arch certificate(form-1)-compressed.pdf · uploaded 29 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2-compressed.pdf · uploaded 29 Jul 2017Source
- 1 Certificates of CA (Form 3)Form 3-compressed.pdf · uploaded 29 Jul 2017Source
- 1 Proforma of Allotment letteragreement to Sale-Allotement Letter.pdf · uploaded 29 Jul 2017Source
- 2 Copy of the legal title reportTitle Report - 3 supplymentary 2 -com.pdf · uploaded 30 May 2018Source
- 2 Copy of Layout Approval (in case of layout)Sanction plan 1-6.pdf · uploaded 30 May 2018Source
- 5 Building Plan Approval (IOD)Sanction plan 1-6.pdf · uploaded 30 May 2018Source
- 6 Building Plan Approval (IOD)sanction plan 2-6 2.pdf · uploaded 30 May 2018Source
- 7 Building Plan Approval (IOD)sanction plan 3-6 2.pdf · uploaded 30 May 2018Source
- 8 Building Plan Approval (IOD)sanction plan 4-6.pdf · uploaded 30 May 2018Source
- 9 Building Plan Approval (IOD)sanction plan 5-6 2.pdf · uploaded 30 May 2018Source
- 10 Building Plan Approval (IOD)sanction plan 6-6 2.pdf · uploaded 30 May 2018Source
- 2 Commencement Certificates / NA Order for plotted developmentcommencement certificate march2018 main.pdf · uploaded 30 May 2018Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.PDF · uploaded 30 May 2018Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Engg cert.PDF · uploaded 30 May 2018Source
- 2 Certificates of CA (Form 3)Form 3.pdf · uploaded 30 May 2018Source
Technical
- Documentsanction_plan_page_1.pdf · uploaded 28 Jul 2017Source
- Documentsanction_plan_page_2.pdf · uploaded 28 Jul 2017Source
- Documentsanction_plan_page_1.pdf · uploaded 28 Jul 2017Source
- Documentsanction_plan_page_3.pdf · uploaded 28 Jul 2017Source
- Documentsanction_plane_page_4.pdf · uploaded 28 Jul 2017Source
- DocumentSanction plan 1-6.pdf · uploaded 30 May 2018Source
- Documentsanction plan 2-6 2.pdf · uploaded 30 May 2018Source
- Documentsanction plan 3-6 2.pdf · uploaded 30 May 2018Source
- Documentsanction plan 4-6.pdf · uploaded 30 May 2018Source
- Documentsanction plan 5-6 2.pdf · uploaded 30 May 2018Source
- Documentsanction plan 6-6 2.pdf · uploaded 30 May 2018Source
- DocumentSanction plan 1-6.pdf · uploaded 30 May 2018Source
Technical (Architect)
- DocumentForm 1.PDF · uploaded 30 May 2018Source
Technical (Engineer)
- DocumentForm 2 Engg cert.PDF · uploaded 30 May 2018Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 34/3
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 2 BHK, 3 BHK, 4 BHK52 units in all
- Address
- 34/3, Pancardclub Road, BanerPIN 411045
- Village
- Baner, Haveli taluka
- Location
- 18.55623, 73.77348
- Land area for this project
- 3,142 sq m (33,823 sq ft)
- Permissible built-up area
- 4,377 sq m (47,118 sq ft)
- Sanctioned built-up area
- 4,364 sq m (46,978 sq ft)
- Recreational open space
- 263 sq m (2,827 sq ft)
- Designated bank account
- 87
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
34/3
Boundaries
- North
- Internal Road
- South
- Internal road
- East
- Mr Chavan
- West
- 18m wide DP Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking52 units
9 of 52 units booked (17%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2 BHK | 57.44 sq m · 618 sq ft | 6 | 1 |
| 2 BHK | 57.46 sq m · 618 sq ft | 7 | 1 |
| 2 BHK | 58.19 sq m · 626 sq ft | 7 | 0 |
| 2 BHK | 58.21 sq m · 627 sq ft | 5 | 2 |
| 3 BHK | 89.81 sq m · 967 sq ft | 6 | 0 |
| 3 BHK | 89.98 sq m · 969 sq ft | 6 | 2 |
| 3 BHK | 90.2 sq m · 971 sq ft | 6 | 0 |
| 3 BHK | 90.35 sq m · 973 sq ft | 7 | 3 |
| 4 BHK | 148.25 sq m · 1,596 sq ft | 1 | 0 |
| 4 BHK | 190.11 sq m · 2,046 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Pramod Joshi | — |
| Architect | VKa Architecture | — |
| Engineer | MR Sachin Doshi | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Baner
- Sai Residency Cooperative Housing Society LimitedRERA PR1260002602726
- Merlin VertexRERA PC1261012602688
- Bliss NestRERA PR1260002602296
- GaurinandanRERA PR1260002602194
- One Space₹9,840 a sq ft
- Anantashree₹8,070 a sq ft
- FernnvaleRERA PM1260002601647
- Avika ResidencesRERA PR1260002601571
All 3,195 projects in Baner · Compare Chlorophyll with another project
Chlorophyll in numbers
Registered deals, summarised
Deedo has 78 registered documents at Chlorophyll, from May 2019 to Nov 2026: 1 sale, 48 leave and licence agreements, 28 mortgages.
- How many properties have been sold at Chlorophyll?
- 1 sale is registered at Chlorophyll.
- Are properties at Chlorophyll rented out?
- Yes: 48 leave and licence agreements are registered at Chlorophyll, at a median rent since May 2019 of about ₹32,000 a month with a deposit of about ₹85,000.
- Where does this data come from?
- The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Chlorophyll by Deedo, last updated with deals registered in Nov 2026.
Latest deal · Primary sale · Dec 2022
₹2–3.5 Cr