Deedo IDDP-PUN-CABYMahaRERA shows it completed, after its date was pushed back 3 years and 3 months; no MahaRERA orders on record; 100% of its units are booked.
Baner, Pune 411045 · Property rates in Baner · by Achalare Realtors Private Limited · 50% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
MahaRERA shows it completed, after its date was pushed back 3 years and 3 months
- This projectRegistered 19 Mar 2018, completion promised 31 Dec 2019, revised to 31 Mar 2023.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
- Primary sale · Mar 2026
- Rental · 36 mo · Aug 2026
- Rental · Jul 2026
- Correction · May 2026No amount
- Correction · Apr 2026No amount
- Rental · Jan 2026
- Rental · 17 mo · Aug 2025
- Rental · Dec 2024
- Rental · 60 mo · Jul 2024
- Rental · Mar 2024
| Month | Flat | Kind | Area | Price | Record |
|---|---|---|---|---|---|
| Mar 2026 | Not on record | Primary sale | 1,427 sq ft | View Primary sale, Mar 2026 | |
| Aug 2026 | Unit 501 | Rental | — | View Rental, Aug 2026 | |
| Jul 2026 | Unit 302 | Rental | — | View Rental, Jul 2026 | |
| May 2026 | Not on record | Correction | 644 sq ft | View Correction, May 2026 | |
| Apr 2026 | Not on record | Correction | 662 sq ft | View Correction, Apr 2026 | |
| Jan 2026 | Unit 302 | Rental | — | View Rental, Jan 2026 | |
| Aug 2025 | Unit 101 | Rental | — | View Rental, Aug 2025 | |
| Dec 2024 | Unit 302 | Rental | — | View Rental, Dec 2024 | |
| Jul 2024 | Unit 602 | Rental | — | View Rental, Jul 2024 | |
| Mar 2024 | Unit 302 | Rental | — | View Rental, Mar 2024 |
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100015730
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100015730 | 19 Mar 2018 | 31 Dec 2019 | 31 Mar 2023 | Achalare Realtors Private Limited | Project page |
Documents61
3 documents held by Deedo, 58 filings listed on MahaRERA's project page
Other
- OtherDate not statedView
Legal
Show all 61 documentsShow fewer documents
Migrated
- 1 Details of encumbrances6 Encumbrance.pdf · uploaded 14 Mar 2018Source
- 1 Declaration in FORM BForm B Affidavit Realtors.pdf · uploaded 14 Mar 2018Source
- 1 Proforma of Allotment letterFINAL Allotment and Agreement.pdf · uploaded 14 Mar 2018Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificates.pdf · uploaded 15 Mar 2018Source
- 2 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 15 Mar 2018Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 15 Mar 2018Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 15 Mar 2018Source
- 1 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 15 Mar 2018Source
- 1 Certificates of CA (Form 5)Amber-ilovepdf-compressed.pdf · uploaded 30 Sep 2018Source
- 2 Certificates of CA (Form 5)ARPL Form 5 - Amber.pdf · uploaded 11 Jul 2019Source
- 3 Certificates of CA (Form 5)Amber - CA Cerificate Form 5.pdf · uploaded 8 Aug 2020Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentamber completion.pdf · uploaded 30 Nov 2020Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentAmber Completion Certificate Part II.pdf · uploaded 30 Nov 2020Source
- 1 Status of ConveyanceDeed Declaration Amber index.pdf · uploaded 30 Nov 2020Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Amber 18-19.pdf · uploaded 16 Feb 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Amber 19-20.pdf · uploaded 16 Feb 2021Source
- 1 Disclosure of sold/ booked inventoryDisclosure of sold booked inventory Amber.pdf · uploaded 26 May 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)ARPL (Amber) - CA Certificate (Form 5)-compressed.pdf · uploaded 20 Sep 2021Source
- 2 Disclosure of sold/ booked inventoryRERA Disclosure letter - Amber.pdf · uploaded 23 Sep 2021Source
- 1 Declaration about Commencement CertificateCommencement Declaration format D.pdf · uploaded 25 Nov 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Amber 2A Form 1 Oct 20 Dec 20.pdf · uploaded 25 Nov 2021Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Amber 2A Form 2 Jan 21 March 21.pdf · uploaded 25 Nov 2021Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Amber 2A Form 3 April 21 June 21.pdf · uploaded 25 Nov 2021Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Amber 2A Form 4 July 21 Sept 21.pdf · uploaded 25 Nov 2021Source
- 5 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Amber 2A Form 4 July 21 Sept 21.pdf · uploaded 7 Dec 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Amber 2A Form 2 Jan 21 March 21.pdf · uploaded 7 Dec 2021Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Amber 2A Form 3 April 21 June 21.pdf · uploaded 7 Dec 2021Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Amber.pdf · uploaded 3 Jan 2022Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Quality Assurance certificate Amber.pdf · uploaded 20 Aug 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)AMBER.pdf · uploaded 21 Jan 2023Source
- 2 Certificates of CA (Form 3)Amber CA Certificate -1compressed.pdf · uploaded 23 Jan 2023Source
- 3 Certificates of CA (Form 3)CA Certificate - Amber -2.pdf · uploaded 23 Jan 2023Source
- 4 Certificates of CA (Form 3)CA Certificate Amber -3compressed.pdf · uploaded 23 Jan 2023Source
- 5 Certificates of CA (Form 3)CA Certificate - Amber -4.pdf · uploaded 23 Jan 2023Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 amber.pdf · uploaded 4 Feb 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A Amber.pdf · uploaded 14 Feb 2023Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Amber.pdf · uploaded 23 Feb 2023Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Amber.pdf · uploaded 23 Feb 2023Source
- 3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion Certificate dtd 30 01 2023 revised.pdf · uploaded 23 Feb 2023Source
- 3 Disclosure of sold/ booked inventoryamber dscloser dt 18 03 2023.pdf · uploaded 20 Mar 2023View
- 2 Architect’s Certificate on Completion of Project (Form 4)form 4 amber.pdf · uploaded 1 Apr 2023Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Amber Form 2A 22 23.pdf · uploaded 19 May 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)2 Engineers Certificate on Quality Assurance.pdf · uploaded 21 Jun 2023Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)AMBER.pdf · uploaded 29 Jun 2023Source
- 6 Certificates of CA (Form 3)Form 3 Amber_compressed.pdf · uploaded 13 Jul 2023Source
- 7 Certificates of CA (Form 3)amber form 3 dt 15 5 23.pdf · uploaded 13 Jul 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)CA certificate Amber 30 09 2023.pdf · uploaded 11 Dec 2023Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)2A Amber.pdf · uploaded 26 Apr 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)2 Engineers Certificate on Quality Assurance form 2A FY 2023-2024.pdf · uploaded 7 May 2024Source
Technical
Technical (Architect)
- DocumentForm 1 Amber.pdf · uploaded 23 Feb 2023Source
Technical (Engineer)
- DocumentAMBER.pdf · uploaded 29 Jun 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel S.no. 17/1/2
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK12 units in all
- Address
- S.no. 17/1/2, 18 M DP Road, BanerPIN 411045
- Village
- Baner, Haveli taluka
- Location
- 18.55060, 73.77884
- Land area for this project
- 554 sq m (5,964 sq ft)
- Permissible built-up area
- 712 sq m (7,662 sq ft)
- Sanctioned built-up area
- 622 sq m (6,694 sq ft)
- Designated bank account
- 28
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S.no. 17/1/2
Boundaries
- North
- Adjacent Plot S no 17 Part
- South
- Adjacent 18 M wide Road
- East
- Adjacent Plot S no 17 Part
- West
- Adjacent 9 M wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking12 units
12 of 12 units booked (100%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 42.21 sq m · 454 sq ft | 6 | 6 |
| 2BHK | 69.85 sq m · 752 sq ft | 6 | 6 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals11
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Nitin Joshi | — |
| Chartered accountant | Dnyaneshwar Gopale | — |
| Chartered accountant | Npsr & Associates Chartered Accountants | — |
| Engineer | GA Bhilare Consultants Pvt Ltd | — |
| Other | Anjali Glass & Aluminium Works | — |
| Other | Efficient Enterprises | — |
| Other | G A Bhilare Consultant Pvt Ltd | — |
| Other | Ram Sahay Verma | — |
Show all 11 professionalsShow fewer professionals
| Role | Name | Registration no. |
|---|---|---|
| Other | Shantilal Patel | — |
| Other | Shashank Balawantrao Dasharath | — |
| Other | Yogesh Enterprises | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Baner
- Sai Residency Cooperative Housing Society LimitedRERA PR1260002602726
- Merlin VertexRERA PC1261012602688
- Bliss NestRERA PR1260002602296
- GaurinandanRERA PR1260002602194
- One Space₹9,840 a sq ft
- Anantashree₹8,070 a sq ft
- FernnvaleRERA PM1260002601647
- Avika ResidencesRERA PR1260002601571
All 3,195 projects in Baner · Compare Amber with another project
Amber in numbers
Registered deals, summarised
Deedo has 20 registered documents at Amber, from Aug 2018 to Aug 2026: 1 sale, 14 leave and licence agreements, 3 mortgages.
- How many properties have been sold at Amber?
- 1 sale is registered at Amber.
- Are properties at Amber rented out?
- Yes: 14 leave and licence agreements are registered at Amber, at a median rent since Aug 2018 of about ₹20,000 a month with a deposit of about ₹40,000.
- Where does this data come from?
- The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Amber by Deedo, last updated with deals registered in Aug 2026.