Skip to content
Others · 2 buildingsRERA P52100029972

TruSpace Prima Angulus

Deedo IDDP-PUN-P9HG

MahaRERA shows it completed; no MahaRERA orders on record.

Balewadi, Pune 411045 · Property rates in Balewadi · by Atharva Enterprises · 100% of its projects kept the RERA date

DeliveryCompletedCompletion / occupancy certificate on MahaRERARegulatoryNo ordersNot in any MahaRERA list or order Deedo has readPrice₹9,260 /sq ft15.2% below Balewadi · 318 registered sales

Buying a flat here?

See every deed registered on it.

MahaRERA shows it completed

  • This projectRegistered 18 Jul 2021, completion promised 31 Dec 2024.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

All 682 deeds →
Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Oct 2026TruSpace Prima Angulus · 1302Resale686 sq ftView Resale, Oct 2026
Aug 2026TruSpace Prima Angulus · 303Resale619 sq ftView Resale, Aug 2026
Aug 2026TruSpace Prima Angulus · 1402Resale686 sq ftView Resale, Aug 2026
Dec 2024TruSpace Prima Angulus · 1105Primary sale730 sq ftView Primary sale, Dec 2024
Nov 2024TruSpace Prima Angulus · 1201Resale672 sq ftView Resale, Nov 2024
Oct 2024TruSpace Prima Angulus · 203Resale619 sq ftView Resale, Oct 2024
Sep 2024TruSpace Prima Angulus · 2Primary sale1,088 sq ftView Primary sale, Sep 2024
Jul 2024TruSpace Prima Angulus · 804Resale721 sq ftView Resale, Jul 2024
Mar 2024TruSpace Prima Angulus · 904Primary sale672 sq ftView Primary sale, Mar 2024
Feb 2024TruSpace Prima Angulus · 1502Primary sale730 sq ftView Primary sale, Feb 2024

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100029972
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210002997218 Jul 202131 Dec 202431 Dec 2024Atharva EnterprisesProject page
Documents153

1 document held by Deedo, 152 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardpan card.pdf · uploaded 9 Apr 2021Source

Legal

  • Declaration Form BDeclaration_Form B.pdf · uploaded 25 Jun 2021Source
  • Legal Title reportTitle Opinion_Rera.pdf · uploaded 12 Jul 2021Source

Migrated

  • 1 PAN Cardpan card.pdf · uploaded 9 Apr 2021Source
  • 1 Details of encumbrancesletter.pdf · uploaded 3 May 2021Source
  • 1 Copy of Layout Approval (in case of layout)Layout Plan_Plot A_compressed_compressed.pdf · uploaded 3 May 2021Source
  • 1 Building Plan Approval / NA Order for plotted development1(15).PDF · uploaded 31 May 2021Source
Show all 153 documentsShow fewer documents

Migrated

  • 2 Building Plan Approval / NA Order for plotted development2(15).PDF · uploaded 31 May 2021Source
  • 3 Building Plan Approval / NA Order for plotted development3(12).PDF · uploaded 31 May 2021Source
  • 4 Building Plan Approval / NA Order for plotted development4(12).PDF · uploaded 31 May 2021Source
  • 5 Building Plan Approval / NA Order for plotted development5(8).PDF · uploaded 31 May 2021Source
  • 6 Building Plan Approval / NA Order for plotted development6(7).PDF · uploaded 31 May 2021Source
  • 7 Building Plan Approval / NA Order for plotted development7(6).PDF · uploaded 31 May 2021Source
  • 8 Building Plan Approval / NA Order for plotted development8(7).PDF · uploaded 31 May 2021Source
  • 9 Building Plan Approval / NA Order for plotted development9(6).PDF · uploaded 31 May 2021Source
  • 10 Building Plan Approval / NA Order for plotted development10(4).PDF · uploaded 31 May 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 31 May 2021Source
  • 1 Declaration in FORM BDeclaration_Form B.pdf · uploaded 25 Jun 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_24-06-2021.pdf · uploaded 25 Jun 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate_17-06-2021.pdf · uploaded 25 Jun 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_25-06-2021.pdf · uploaded 26 Jun 2021Source
  • 1 Declaration about Commencement CertificateDeclaration_Form D.pdf · uploaded 8 Jul 2021Source
  • 1 Proforma of Allotment letterAgreement Draft.pdf · uploaded 8 Jul 2021Source
  • 1 Copy of the legal title reportTitle Opinion_Rera.pdf · uploaded 12 Jul 2021Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Cert Form 1_30-06-2021.pdf · uploaded 27 Aug 2021Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate 18-08-2021.pdf · uploaded 27 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Engineers Certificate For Quality Assurance.pdf · uploaded 27 Aug 2021Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_25-08-2021.pdf · uploaded 27 Aug 2021Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Cert Form 1_30-09-2021.pdf · uploaded 22 Oct 2021Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate_30-09-2021.pdf · uploaded 22 Oct 2021Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_30-09-2021.pdf · uploaded 22 Oct 2021Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_31-12-2021.pdf · uploaded 1 Feb 2022Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate_31-12-2021.pdf · uploaded 1 Feb 2022Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A Certificate_31-12-2021.pdf · uploaded 1 Feb 2022Source
  • 2 Details of encumbrancesDetails of Encumbrances.pdf · uploaded 3 Mar 2022Source
  • 11 Building Plan Approval / NA Order for plotted development1.pdf · uploaded 31 Mar 2022Source
  • 12 Building Plan Approval / NA Order for plotted development2.pdf · uploaded 31 Mar 2022Source
  • 13 Building Plan Approval / NA Order for plotted development3.pdf · uploaded 31 Mar 2022Source
  • 14 Building Plan Approval / NA Order for plotted development4.pdf · uploaded 31 Mar 2022Source
  • 15 Building Plan Approval / NA Order for plotted development5.pdf · uploaded 31 Mar 2022Source
  • 16 Building Plan Approval / NA Order for plotted development6.pdf · uploaded 31 Mar 2022Source
  • 17 Building Plan Approval / NA Order for plotted development7.pdf · uploaded 31 Mar 2022Source
  • 18 Building Plan Approval / NA Order for plotted development8.pdf · uploaded 31 Mar 2022Source
  • 19 Building Plan Approval / NA Order for plotted development9.pdf · uploaded 31 Mar 2022Source
  • 20 Building Plan Approval / NA Order for plotted development10.pdf · uploaded 31 Mar 2022Source
  • 21 Building Plan Approval / NA Order for plotted development11.pdf · uploaded 31 Mar 2022Source
  • 22 Building Plan Approval / NA Order for plotted development12.pdf · uploaded 31 Mar 2022Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 31 Mar 2022Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_26-04-2022.pdf · uploaded 24 May 2022Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate_21-04-2022.pdf · uploaded 24 May 2022Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A Certificate_31-03-2022_compressed.pdf · uploaded 24 May 2022Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_30-06-2022.pdf · uploaded 12 Jul 2022Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate_06-07-2022.pdf · uploaded 12 Jul 2022Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3_30-06-2022_compressed.pdf · uploaded 12 Jul 2022Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_10-10-2022.pdf · uploaded 11 Oct 2022Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate_10-10-2022.pdf · uploaded 11 Oct 2022Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_30-09-2022_compressed (1).pdf · uploaded 11 Oct 2022Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch_cert_24-11-2022.pdf · uploaded 1 Dec 2022Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate_24-11-2022.pdf · uploaded 1 Dec 2022Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3_01-12-2022_compressed (1).pdf · uploaded 1 Dec 2022Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_31-12-2022.pdf · uploaded 13 Jan 2023Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate_TSPAngulus_10-01-2023.pdf · uploaded 13 Jan 2023Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3_12-01-2023.pdf · uploaded 13 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form-5_07-11-2022.pdf · uploaded 27 Mar 2023Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_31-03-2023.pdf · uploaded 17 Apr 2023Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate_06-04-2023.pdf · uploaded 17 Apr 2023Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form- 3_31-03-2023.pdf · uploaded 17 Apr 2023Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_31-05-2023.pdf · uploaded 15 Jun 2023Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_07-06-2023.pdf · uploaded 15 Jun 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A Certificate_10-01-2023.pdf · uploaded 15 Jun 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A Certificate_11-04-2023.pdf · uploaded 15 Jun 2023Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A Certificate_07-06-2023.pdf · uploaded 15 Jun 2023Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form- 3_14-06-2023.pdf · uploaded 15 Jun 2023Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_10-07-2023.pdf · uploaded 17 Jul 2023Source
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_07-07-2023.pdf · uploaded 17 Jul 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A_07-07-2023.pdf · uploaded 17 Jul 2023Source
  • 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form- 3_15-07-2023.pdf · uploaded 17 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form-5.pdf · uploaded 2 Sep 2023Source
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_08-09-2023.pdf · uploaded 12 Sep 2023Source
  • 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_07-09-2023.pdf · uploaded 12 Sep 2023Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A_07-09-2023.pdf · uploaded 12 Sep 2023Source
  • 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form- 3_05-09-2023.pdf · uploaded 12 Sep 2023Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Deed Of Declaration-1-110 (1).pdf · uploaded 13 Sep 2023Source
  • 2 Status of Formation of Legal Entity (Society/Co Op etc.)Deed Of Declaration-111-220 (2).pdf · uploaded 13 Sep 2023Source
  • 1 Status of ConveyanceDeed Of Declaration-1-110 (1).pdf · uploaded 13 Sep 2023Source
  • 2 Status of ConveyanceDeed Of Declaration-111-220 (2).pdf · uploaded 13 Sep 2023Source
  • 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_30-09-2023.pdf · uploaded 17 Oct 2023Source
  • 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate_07-10-2023.pdf · uploaded 17 Oct 2023Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A_07-10-2023.pdf · uploaded 17 Oct 2023Source
  • 14 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form- 3_17-10-2023.pdf · uploaded 17 Oct 2023Source
  • 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1_Architect Certificate_30-11-2023.pdf · uploaded 13 Dec 2023Source
  • 15 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_30-11-2023.pdf · uploaded 13 Dec 2023Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A_30-11-2023.pdf · uploaded 13 Dec 2023Source
  • 15 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_30-11-2023.pdf · uploaded 13 Dec 2023Source
  • 16 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1_Architect Certificate_31-12-2023.pdf · uploaded 10 Jan 2024Source
  • 16 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_31-12-2023.pdf · uploaded 10 Jan 2024Source
  • 5 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A_31-12-2023.pdf · uploaded 10 Jan 2024Source
  • 16 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_31-12-2023.pdf · uploaded 10 Jan 2024Source
  • 17 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1_Arch_Cert_31-01-2024.pdf · uploaded 6 Feb 2024Source
  • 17 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_31-01-2024.pdf · uploaded 6 Feb 2024Source
  • 6 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A_31-01-2024.pdf · uploaded 6 Feb 2024Source
  • 17 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form- 3_31-01-2024_compressed (1).pdf · uploaded 6 Feb 2024Source
  • 18 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate_29-02-2024.pdf · uploaded 15 Apr 2024Source
  • 18 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_29-02-2024.pdf · uploaded 15 Apr 2024Source
  • 19 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_31-03-2024.pdf · uploaded 15 Apr 2024Source
  • 7 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A_29-02-2024.pdf · uploaded 15 Apr 2024Source
  • 8 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A_31-03-2024.pdf · uploaded 15 Apr 2024Source
  • 18 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form- 3_29-02-2024.pdf · uploaded 15 Apr 2024Source
  • 19 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_31-03-2024.pdf · uploaded 15 Apr 2024Source
  • 19 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1_Arch_Cert_31-03-2024.pdf · uploaded 17 Apr 2024Source
  • 20 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1_Arch_Cert_30-06-2024.pdf · uploaded 12 Jul 2024Source
  • 20 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_30-06-2024.pdf · uploaded 12 Jul 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A_30-06-2024.pdf · uploaded 12 Jul 2024Source
  • 20 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_30-06-2024.pdf · uploaded 12 Jul 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form1_TSP Angulus_30-09-2024.pdf · uploaded 14 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_TSP Angulus_30-09-2024.pdf · uploaded 14 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_TSP Angulus_30-09-2024.pdf · uploaded 14 Oct 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A_TSP Angulus _30-09-2024.pdf · uploaded 14 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5_TSP Angulus_31-03-2024.pdf · uploaded 15 Oct 2024Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion Full_29-11-2024.pdf · uploaded 4 Dec 2024Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4_10-12-2024.pdf · uploaded 10 Dec 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_13-01-2025.pdf · uploaded 13 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_TSP Angulus_29-11-2024.pdf · uploaded 13 Jan 2025Source
  • Form 5 (FY 2024-2025)Form 5_TS Angulus_28-09-2025.pdf · uploaded 18 Oct 2025Source

Technical

  • DocumentLayout Plan_Plot A_compressed_compressed.pdf · uploaded 3 May 2021Source
  • Document1(15).PDF · uploaded 31 May 2021Source
  • Document2(15).PDF · uploaded 31 May 2021Source
  • Document3(12).PDF · uploaded 31 May 2021Source
  • Document4(12).PDF · uploaded 31 May 2021Source
  • Document5(8).PDF · uploaded 31 May 2021Source
  • Document6(7).PDF · uploaded 31 May 2021Source
  • Document7(6).PDF · uploaded 31 May 2021Source
  • Document8(7).PDF · uploaded 31 May 2021Source
  • Document9(6).PDF · uploaded 31 May 2021Source
  • Document10(4).PDF · uploaded 31 May 2021Source
  • Document1.pdf · uploaded 31 Mar 2022Source
  • Document2.pdf · uploaded 31 Mar 2022Source
  • Document3.pdf · uploaded 31 Mar 2022Source
  • Document4.pdf · uploaded 31 Mar 2022Source
  • Document5.pdf · uploaded 31 Mar 2022Source
  • Document6.pdf · uploaded 31 Mar 2022Source
  • Document7.pdf · uploaded 31 Mar 2022Source
  • Document8.pdf · uploaded 31 Mar 2022Source
  • Document9.pdf · uploaded 31 Mar 2022Source
  • Document10.pdf · uploaded 31 Mar 2022Source
  • Document11.pdf · uploaded 31 Mar 2022Source
  • Document12.pdf · uploaded 31 Mar 2022Source

Technical (Architect)

  • DocumentForm1_Arch_Cert_30-06-2024.pdf · uploaded 12 Jul 2024Source
  • DocumentForm1_TSP Angulus_30-09-2024.pdf · uploaded 14 Oct 2024Source

Technical (Engineer)

  • DocumentForm 2_30-06-2024.pdf · uploaded 12 Jul 2024Source
  • DocumentForm 2_TSP Angulus_30-09-2024.pdf · uploaded 14 Oct 2024Source
  • DocumentForm 2_TSP Angulus_29-11-2024.pdf · uploaded 13 Jan 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Survey No 32/2 part Plot A

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Address
Survey No 32/2 part Plot A, Off MITCON, BalewadiPIN 411045
Village
Balewadi, Haveli taluka
Land area for this project
2,600 sq m (27,986 sq ft)
Permissible built-up area
12,490 sq m (1,34,439 sq ft)
Sanctioned built-up area
8,490 sq m (91,383 sq ft)
Recreational open space
260 sq m (2,799 sq ft)
Designated bank account
76
Developed in phases
No
Also registered as
Truspes Prayama Angyulas Apartament Kandominiyam, ट्रुस्पेस प्रायमा अँग्यूलस अपार्टमेंट कंडोमिनियम, ट्रुस्पेस प्रायमा अँग्युलस, ट्रुस्पेस प्रायमा अँग्युलस अपार्टमेंट, Truspes Prayama Angyulas Apartament, Truspes Prayama Angyulas Apartment Condominium, Truspes Prayama Angyulas Apartment

Survey, CTS, gat or plot numbers

Survey No 32/2 part Plot A

Land as published on MahaRERA's project page

Survey No 32/2 part Plot A

Boundaries

North
D P Road
South
Amenity Space
East
D P Road
West
S No 32 Hissa No 2

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals20

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAvinash Nawathe—
Chartered accountantNikita A Bajaj—
Chartered accountantSiddhant Abhay Bora—
EngineerAbhijeet Redekar—
EngineerAbhijit Redekar—
OtherAr Avadhoot Kumthekar—
OtherBal Kulkarni—
OtherMr Jayesh Phulphagar—
Show all 20 professionalsShow fewer professionals
RoleNameRegistration no.
OtherShailendra S Zopate—
OtherV. G. Phadnis—
Registered real estate agentAmit Anil Kulkarni—
Registered real estate agentAshish Padam Saini—
Registered real estate agentAwanish kumar—
Registered real estate agentElizabeth Kamei—
Registered real estate agentJM Financial Products Limited—
Registered real estate agentLife Space Property Solutions Pvt Ltd—
Registered real estate agentMDN Properties Private Limited—
Registered real estate agentRahul Malik—
Registered real estate agentSandeep Gangadhar Dange—
Registered real estate agentShubham Babasaheb Deshmukh Proprietor Of Esprit Homes And Properties—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Balewadi

All 1,319 projects in Balewadi · Compare TruSpace Prima Angulus with another project

TruSpace Prima Angulus in numbers

Registered deals, summarised

Deedo has 682 registered documents at TruSpace Prima Angulus, from Feb 2015 to Oct 2026: 318 sales, 84 leave and licence agreements, 170 mortgages. The median registered sale since Feb 2015 works out to about ₹9,300 per sq ft, at a median of ₹65 L a deal; 5% of sales were resales.

What is the price per sq ft at TruSpace Prima Angulus?
The median registered sale since Feb 2015 works out to about ₹9,300 per sq ft, at a median of ₹65 L a deal; 5% of sales were resales.
How many properties have been sold at TruSpace Prima Angulus?
318 sales are registered at TruSpace Prima Angulus, 17 of them resales.
Are properties at TruSpace Prima Angulus rented out?
Yes: 84 leave and licence agreements are registered at TruSpace Prima Angulus, at a median rent since Feb 2015 of about ₹31,000 a month with a deposit of about ₹62,000.
Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at TruSpace Prima Angulus by Deedo, last updated with deals registered in Oct 2026.

Latest deal · Resale · Oct 2026

₹75 L–1 Cr

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · registered documents (Index II)Data through is when MahaRERA's project page was last read.Report a problemMethodology