Skip to content
Residential / Group Housing · 2 buildings · 120 unitsRERA P52100022808

Namoville

Deedo IDDP-PUN-08F4

It is due for completion in Dec 2028, with no extension on record; no MahaRERA orders on record.

Balewadi, Pune 411045 · Property rates in Balewadi · by Royal Namoville Ventures

DeliveryDue Dec 2028No extension on recordRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readPrice₹7,530 /sq ft31% below Balewadi · 120 registered sales

Buying a flat here?

See every deed registered on it.

It is due for completion in Dec 2028, with no extension on record

  • This projectRegistered 30 Oct 2019, completion promised 31 Dec 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

All 162 deeds →
Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Aug 2026Wing C · 603Primary sale—View Primary sale, Aug 2026
Apr 2026Wing B · 101Primary sale—View Primary sale, Apr 2026
Apr 2026Wing C · 1604Primary sale—View Primary sale, Apr 2026
Apr 2026Wing B · 904Primary sale—View Primary sale, Apr 2026
Apr 2026Wing B · 1604Primary sale—View Primary sale, Apr 2026
Mar 2026Wing C · 304Primary sale—View Primary sale, Mar 2026
Mar 2026Wing B · 201Primary sale—View Primary sale, Mar 2026
Feb 2026Wing C · 303Primary sale—View Primary sale, Feb 2026
Jan 2026Wing B · 1404Primary sale—View Primary sale, Jan 2026
Dec 2025Wing B · 1401Primary sale—View Primary sale, Dec 2025

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100022808
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210002280830 Oct 201931 Dec 202831 Dec 2028Royal Namoville VenturesProject page
Documents295

1 document held by Deedo, 294 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardNamovillePAN.pdf · uploaded 11 Oct 2019Source

Legal

  • Legal Title reportSEARCH REPORT min.pdf · uploaded 11 Oct 2019Source
  • Declaration Form BForm B Royal Namoville Ventures min.pdf · uploaded 11 Oct 2019Source
  • OtherMBVA CERTIFICATE (2).pdf · uploaded 3 Aug 2020Source
  • Declaration Form BDeveloper - Form B Declaration.pdf · uploaded 19 Apr 2024Source
  • Declaration Form BForm B - Namo.pdf · uploaded 3 May 2025Source

Migrated

  • 1 PAN CardNamovillePAN.pdf · uploaded 11 Oct 2019Source
Show all 295 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportSEARCH REPORT min.pdf · uploaded 11 Oct 2019Source
  • 1 Details of encumbrancesEncumbrance Cert.pdf · uploaded 11 Oct 2019Source
  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 11 Oct 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentNAMOVILLECC.pdf · uploaded 11 Oct 2019Source
  • 1 Declaration in FORM BForm B Royal Namoville Ventures min.pdf · uploaded 11 Oct 2019Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate.pdf · uploaded 11 Oct 2019Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate min.pdf · uploaded 11 Oct 2019Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form B Royal Namoville Ventures min.pdf · uploaded 11 Oct 2019Source
  • 1 Proforma of Allotment letterAGREEMENT RERA - Namoville 2019-converted.pdf · uploaded 11 Oct 2019Source
  • 2 Copy of Layout Approval (in case of layout)1-2 min.pdf · uploaded 17 Oct 2019Source
  • 1 Building Plan Approval / NA Order for plotted development1-2 min.pdf · uploaded 17 Oct 2019Source
  • 2 Building Plan Approval / NA Order for plotted development1-7 min.pdf · uploaded 17 Oct 2019Source
  • 3 Building Plan Approval / NA Order for plotted development2-2 min.pdf · uploaded 17 Oct 2019Source
  • 4 Building Plan Approval / NA Order for plotted development2-7 min.pdf · uploaded 17 Oct 2019Source
  • 5 Building Plan Approval / NA Order for plotted development3-7 min.pdf · uploaded 17 Oct 2019Source
  • 6 Building Plan Approval / NA Order for plotted development4-7 min.pdf · uploaded 17 Oct 2019Source
  • 7 Building Plan Approval / NA Order for plotted development5-7 min.pdf · uploaded 17 Oct 2019Source
  • 8 Building Plan Approval / NA Order for plotted development6-7 min.pdf · uploaded 17 Oct 2019Source
  • 9 Building Plan Approval / NA Order for plotted development7-7 min.pdf · uploaded 17 Oct 2019Source
  • 2 Proforma of Allotment letterallotment Letter.pdf · uploaded 17 Oct 2019Source
  • 1 OtherMBVA CERTIFICATE (2).pdf · uploaded 3 Aug 2020Source
  • 3 Copy of Layout Approval (in case of layout)1 Sanction Layout_compressed.pdf · uploaded 10 Jan 2023Source
  • 10 Building Plan Approval / NA Order for plotted development1 Building Plan Layout compressed.pdf · uploaded 10 Jan 2023Source
  • 11 Building Plan Approval / NA Order for plotted development2_compressed.pdf · uploaded 10 Jan 2023Source
  • 12 Building Plan Approval / NA Order for plotted development3_compressed.pdf · uploaded 10 Jan 2023Source
  • 13 Building Plan Approval / NA Order for plotted development4_compressed.pdf · uploaded 10 Jan 2023Source
  • 14 Building Plan Approval / NA Order for plotted development5_compressed.pdf · uploaded 10 Jan 2023Source
  • 15 Building Plan Approval / NA Order for plotted development6_compressed.pdf · uploaded 10 Jan 2023Source
  • 16 Building Plan Approval / NA Order for plotted development7_compressed.pdf · uploaded 10 Jan 2023Source
  • 17 Building Plan Approval / NA Order for plotted development8_compressed.pdf · uploaded 10 Jan 2023Source
  • 18 Building Plan Approval / NA Order for plotted development9_compressed.pdf · uploaded 10 Jan 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentCommencement Certificate_compressed.pdf · uploaded 10 Jan 2023Source
  • 2 Declaration in FORM BDeveloper - Form B Declaration.pdf · uploaded 19 Apr 2024Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold - booked inventory.pdf · uploaded 19 Apr 2024Source
  • 1 CERSAI detailsself declaration regarding non-encumbrances.pdf · uploaded 19 Apr 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)organized form 3_compressed.pdf · uploaded 19 Apr 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 19 Apr 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Namoville form 5 FY 22-23.pdf · uploaded 19 Apr 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 19 Apr 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Architect Certificate.pdf · uploaded 23 Apr 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Engineer Certificate.pdf · uploaded 23 Apr 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)2A ENGINEERS CERTIFICATE.pdf · uploaded 23 Apr 2024Source
  • 1 Declaration in FORM BForm B - Namo.pdf · uploaded 3 May 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)1Form 1 Sept 22.pdf · uploaded 3 May 2025Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)11Form 1 March 25.pdf · uploaded 3 May 2025Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)10Form 1 Dec 24.pdf · uploaded 3 May 2025Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)9Form 1 Sept 24.pdf · uploaded 3 May 2025Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)8Form 1 June 24.pdf · uploaded 3 May 2025Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)7Form 1 March24.pdf · uploaded 3 May 2025Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)6Form 1 Dec 23.pdf · uploaded 3 May 2025Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)5Form 1 Sept 23.pdf · uploaded 3 May 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)4Form 1 June 23.pdf · uploaded 3 May 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)3Form 1 March 23.pdf · uploaded 3 May 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)2Form 1 Dec 22.pdf · uploaded 3 May 2025Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)11June 2022_compressed.pdf · uploaded 3 May 2025Source
  • 21 CA Certificate on Project Cost & Fund withdrawal (Form 3)22March 25_compressed.pdf · uploaded 3 May 2025Source
  • 20 CA Certificate on Project Cost & Fund withdrawal (Form 3)21Dec24_compressed.pdf · uploaded 3 May 2025Source
  • 19 CA Certificate on Project Cost & Fund withdrawal (Form 3)20Sept 24_compressed.pdf · uploaded 3 May 2025Source
  • 18 CA Certificate on Project Cost & Fund withdrawal (Form 3)19June 24_compressed.pdf · uploaded 3 May 2025Source
  • 17 CA Certificate on Project Cost & Fund withdrawal (Form 3)18March 24_compressed.pdf · uploaded 3 May 2025Source
  • 16 CA Certificate on Project Cost & Fund withdrawal (Form 3)17Dec 23_compressed.pdf · uploaded 3 May 2025Source
  • 15 CA Certificate on Project Cost & Fund withdrawal (Form 3)16Sept23_compressed.pdf · uploaded 3 May 2025Source
  • 14 CA Certificate on Project Cost & Fund withdrawal (Form 3)15June23_compressed.pdf · uploaded 3 May 2025Source
  • 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)14Mar 2023_compressed.pdf · uploaded 3 May 2025Source
  • 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)13Dec 2022_compressed.pdf · uploaded 3 May 2025Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)10March22_compressed.pdf · uploaded 3 May 2025Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)9Dec21_compressed.pdf · uploaded 3 May 2025Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)8Sept21_compressed.pdf · uploaded 3 May 2025Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)7June21_compressed.pdf · uploaded 3 May 2025Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)6Mar 21_compressed.pdf · uploaded 3 May 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)5Dec 20_compressed.pdf · uploaded 3 May 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)4Sep 20_compressed.pdf · uploaded 3 May 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)3June 20_compressed.pdf · uploaded 3 May 2025Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)12Sep 2022_compressed.pdf · uploaded 3 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)2March 20 Final_compressed.pdf · uploaded 3 May 2025Source
  • 19 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q4-24-25.pdf · uploaded 3 May 2025Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q3-22-23.pdf · uploaded 3 May 2025Source
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q4-22-23.pdf · uploaded 3 May 2025Source
  • 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q2-23-24.pdf · uploaded 3 May 2025Source
  • 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q3-23-24.pdf · uploaded 3 May 2025Source
  • 15 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q4-23-24.pdf · uploaded 3 May 2025Source
  • 16 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q1-24-25.pdf · uploaded 3 May 2025Source
  • 17 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q2-24-25.pdf · uploaded 3 May 2025Source
  • 18 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q3-24-25.pdf · uploaded 3 May 2025Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q2-21-22.pdf · uploaded 3 May 2025Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q1-22-23.pdf · uploaded 3 May 2025Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q4-21-22.pdf · uploaded 3 May 2025Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q3-21-22.pdf · uploaded 3 May 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q1-21-22.pdf · uploaded 3 May 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q4-20-21.pdf · uploaded 3 May 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q3-20-21.pdf · uploaded 3 May 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q2-20-21.pdf · uploaded 3 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q1-20-21.pdf · uploaded 3 May 2025Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q2-22-23.pdf · uploaded 3 May 2025Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Formation Declaration.pdf · uploaded 3 May 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 (2020-2021).pdf · uploaded 3 May 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2 A 20-21.pdf · uploaded 3 May 2025Source
  • 16 Disclosure of sold/ booked inventory16 March 25.pdf · uploaded 3 May 2025Source
  • 15 Disclosure of sold/ booked inventory15 Dec24.pdf · uploaded 3 May 2025Source
  • 14 Disclosure of sold/ booked inventory14Sept 24.pdf · uploaded 3 May 2025Source
  • 13 Disclosure of sold/ booked inventory13June 24.pdf · uploaded 3 May 2025Source
  • 5 Disclosure of sold/ booked inventory5June 22.pdf · uploaded 3 May 2025Source
  • 12 Disclosure of sold/ booked inventory12March 24.pdf · uploaded 3 May 2025Source
  • 11 Disclosure of sold/ booked inventory11Dec 23.pdf · uploaded 3 May 2025Source
  • 10 Disclosure of sold/ booked inventory10Sept 23.pdf · uploaded 3 May 2025Source
  • 9 Disclosure of sold/ booked inventory9June 23.pdf · uploaded 3 May 2025Source
  • 8 Disclosure of sold/ booked inventory8March 23.pdf · uploaded 3 May 2025Source
  • 7 Disclosure of sold/ booked inventory7Dec 22.pdf · uploaded 3 May 2025Source
  • 6 Disclosure of sold/ booked inventory6Sept 22.pdf · uploaded 3 May 2025Source
  • 4 Disclosure of sold/ booked inventory4March 22.pdf · uploaded 3 May 2025Source
  • 3 Disclosure of sold/ booked inventory3Dec 21.pdf · uploaded 3 May 2025Source
  • 2 Disclosure of sold/ booked inventory2Sept 21.pdf · uploaded 3 May 2025Source
  • 1 Disclosure of sold/ booked inventory1June 21.pdf · uploaded 3 May 2025Source
  • 1 Declaration about Commencement CertificateFormat D CC Declaration.pdf · uploaded 3 May 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 (2021 - 2022).pdf · uploaded 3 May 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2 A 21-22.pdf · uploaded 3 May 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2 A_23_24.pdf · uploaded 3 May 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 (2023 - 2024).pdf · uploaded 3 May 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)Form 5 Declaration 24-25.pdf · uploaded 12 May 2025Source
  • Withdrawal Update Form 1Form 1 June 25.pdf · uploaded 11 May 2026Source
  • Withdrawal Update Form 1Form 1 Sept 25.pdf · uploaded 11 May 2026Source
  • Withdrawal Update Form 1Form 1 251231.pdf · uploaded 11 May 2026Source
  • Withdrawal Update Form 2Form 2 June 25.pdf · uploaded 11 May 2026Source
  • Withdrawal Update Form 2Form 2 Sept 25.pdf · uploaded 11 May 2026Source
  • Withdrawal Update Form 2Form 2 Dec 25.pdf · uploaded 11 May 2026Source
  • Withdrawal Update Form 3Form 3 June 25-compressed.pdf · uploaded 11 May 2026Source
  • Withdrawal Update Form 3Form 3 Sept 25-compressed.pdf · uploaded 11 May 2026Source
  • Withdrawal Update Form 3Form 3 Dec 2025-compressed.pdf · uploaded 11 May 2026Source
  • Form 1Form 1 2019.pdf · uploaded 12 May 2026Source
  • Form 1Form 1.pdf · uploaded 12 May 2026Source
  • Form 11Form 1.pdf · uploaded 12 May 2026Source
  • Form 111Form 1 March 25.pdf · uploaded 12 May 2026Source
  • Form 110Form 1 Dec 24.pdf · uploaded 12 May 2026Source
  • Form 19Form 1 Sept 24.pdf · uploaded 12 May 2026Source
  • Form 18Form 1 June 24.pdf · uploaded 12 May 2026Source
  • Form 11Form 1.pdf · uploaded 12 May 2026Source
  • Form 13Form 1 March 23.pdf · uploaded 12 May 2026Source
  • Form 17Form 1 March24.pdf · uploaded 12 May 2026Source
  • Form 16Form 1 Dec 23.pdf · uploaded 12 May 2026Source
  • Form 15Form 1 Sept 23.pdf · uploaded 12 May 2026Source
  • Form 11Form 1.pdf · uploaded 12 May 2026Source
  • Form 14Form 1 June 23.pdf · uploaded 12 May 2026Source
  • Form 12Form 1 Dec 22.pdf · uploaded 12 May 2026Source
  • Form 11Form 1 Sept 22.pdf · uploaded 12 May 2026Source
  • Form 11Form 1.pdf · uploaded 12 May 2026Source
  • Form 11Form 1.pdf · uploaded 12 May 2026Source
  • Form 11Form 1.pdf · uploaded 12 May 2026Source
  • Form 11Form 1.pdf · uploaded 12 May 2026Source
  • Form 1Form 1.pdf · uploaded 12 May 2026Source
  • Form 1Form 1.pdf · uploaded 12 May 2026Source
  • Form 2Q3-2019-20.pdf · uploaded 12 May 2026Source
  • Form 2Q4-2019-20.pdf · uploaded 12 May 2026Source
  • Form 2Q1-20-21.pdf · uploaded 12 May 2026Source
  • Form 2Q4-24-25.pdf · uploaded 12 May 2026Source
  • Form 2Q3-24-25.pdf · uploaded 12 May 2026Source
  • Form 2Q2-24-25.pdf · uploaded 12 May 2026Source
  • Form 2Q1-24-25.pdf · uploaded 12 May 2026Source
  • Form 2Q4-21-22.pdf · uploaded 12 May 2026Source
  • Form 2Q4-22-23.pdf · uploaded 12 May 2026Source
  • Form 2Q4-23-24.pdf · uploaded 12 May 2026Source
  • Form 2Q3-22-23.pdf · uploaded 12 May 2026Source
  • Form 2Q2-23-24.pdf · uploaded 12 May 2026Source
  • Form 2Q4-20-21.pdf · uploaded 12 May 2026Source
  • Form 2Q1-23-24.pdf · uploaded 12 May 2026Source
  • Form 2Q3-21-22.pdf · uploaded 12 May 2026Source
  • Form 2Q2-22-23.pdf · uploaded 12 May 2026Source
  • Form 2Q1-22-23.pdf · uploaded 12 May 2026Source
  • Form 2Q3-21-22.pdf · uploaded 12 May 2026Source
  • Form 2Q2-21-22.pdf · uploaded 12 May 2026Source
  • Form 2Q1-21-22.pdf · uploaded 12 May 2026Source
  • Form 2Q3-20-21.pdf · uploaded 12 May 2026Source
  • Form 2Q2-20-21.pdf · uploaded 12 May 2026Source
  • Form 31Dec 19 Final_compressed.pdf · uploaded 12 May 2026Source
  • Form 32March 20 Final_compressed.pdf · uploaded 12 May 2026Source
  • Form 33June 20_compressed.pdf · uploaded 12 May 2026Source
  • Form 322March 25_compressed.pdf · uploaded 12 May 2026Source
  • Form 321Dec24_compressed.pdf · uploaded 12 May 2026Source
  • Form 320Sept 24_compressed.pdf · uploaded 12 May 2026Source
  • Form 319June 24_compressed.pdf · uploaded 12 May 2026Source
  • Form 310March22_compressed.pdf · uploaded 12 May 2026Source
  • Form 314Mar 2023_compressed.pdf · uploaded 12 May 2026Source
  • Form 318March 24_compressed.pdf · uploaded 12 May 2026Source
  • Form 317Dec 23_compressed.pdf · uploaded 12 May 2026Source
  • Form 316Sept23_compressed.pdf · uploaded 12 May 2026Source
  • Form 36Mar 21_compressed.pdf · uploaded 12 May 2026Source
  • Form 315June23_compressed.pdf · uploaded 12 May 2026Source
  • Form 313Dec 2022_compressed.pdf · uploaded 12 May 2026Source
  • Form 312Sep 2022_compressed.pdf · uploaded 12 May 2026Source
  • Form 311June 2022_compressed.pdf · uploaded 12 May 2026Source
  • Form 39Dec21_compressed.pdf · uploaded 12 May 2026Source
  • Form 38Sept21_compressed.pdf · uploaded 12 May 2026Source
  • Form 37June21_compressed.pdf · uploaded 12 May 2026Source
  • Form 35Dec 20_compressed.pdf · uploaded 12 May 2026Source
  • Form 34Sep 20_compressed.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Discl.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Discl.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Discl.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked Inventory16 March 25.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked Inventory15 Dec24.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked Inventory14Sept 24.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked Inventory13June 24.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked Inventory4March 22.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked Inventory8March 23.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked Inventory12March 24.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked Inventory11Dec 23.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked Inventory10Sept 23.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Discl.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked Inventory9June 23.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked Inventory7Dec 22.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked Inventory6Sept 22.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked Inventory5June 22.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked Inventory3Dec 21.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked Inventory2Sept 21.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked Inventory1June 21.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Disclosure.pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Disclosure.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 1FORM-1 NAMOVILLE March 26.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 2Form 2 March 26.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 3Form 3 March 26_compressed.pdf · uploaded 12 May 2026Source
  • Form 2A (FY 2019-2020)Form 2A_2019-20.pdf · uploaded 12 May 2026Source
  • Form 2A (FY 2020-2021)Form 2A_2020-21.pdf · uploaded 12 May 2026Source
  • Form 2A (FY 2021-2022)Form 2A_2021-22.pdf · uploaded 12 May 2026Source
  • Form 2A (FY 2022-2023)Form 2A_2022-23.pdf · uploaded 12 May 2026Source
  • Form 2A (FY 2023-2024)Form 2A_2023-24.pdf · uploaded 12 May 2026Source
  • Form 2A (FY 2024-2025)Form 2A_2024-25.pdf · uploaded 12 May 2026Source
  • Form 2A (FY 2025-2026)Form 2A_2025-26.pdf · uploaded 12 May 2026Source
  • Form 5 (FY 2020-2021)Form 5 20-21.pdf · uploaded 12 May 2026Source
  • Form 5 (FY 2021-2022)Form 5 21-22.pdf · uploaded 12 May 2026Source
  • Form 5 (FY 2022-2023)Form 5 22-23.pdf · uploaded 12 May 2026Source
  • Form 5 (FY 2023-2024)Form 5 23-24.pdf · uploaded 12 May 2026Source
  • Form 5 (FY 2024-2025)Form 5 24-25.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 1Form 1 Namo June 26.pdf · uploaded 5 Aug 2026Source
  • Withdrawal Update Form 2FORM 2 Namo.pdf · uploaded 5 Aug 2026Source
  • Withdrawal Update Form 3FORM-3 Namo-compressed.pdf · uploaded 5 Aug 2026Source

Technical

  • DocumentLayout.pdf · uploaded 11 Oct 2019Source
  • Document1-2 min.pdf · uploaded 17 Oct 2019Source
  • Document1-2 min.pdf · uploaded 17 Oct 2019Source
  • Document1-7 min.pdf · uploaded 17 Oct 2019Source
  • Document2-2 min.pdf · uploaded 17 Oct 2019Source
  • Document2-7 min.pdf · uploaded 17 Oct 2019Source
  • Document3-7 min.pdf · uploaded 17 Oct 2019Source
  • Document4-7 min.pdf · uploaded 17 Oct 2019Source
  • Document5-7 min.pdf · uploaded 17 Oct 2019Source
  • Document6-7 min.pdf · uploaded 17 Oct 2019Source
  • Document7-7 min.pdf · uploaded 17 Oct 2019Source
  • Document1 Sanction Layout_compressed.pdf · uploaded 10 Jan 2023Source
  • Document1 Building Plan Layout compressed.pdf · uploaded 10 Jan 2023Source
  • Document2_compressed.pdf · uploaded 10 Jan 2023Source
  • Document3_compressed.pdf · uploaded 10 Jan 2023Source
  • Document4_compressed.pdf · uploaded 10 Jan 2023Source
  • Document5_compressed.pdf · uploaded 10 Jan 2023Source
  • Document6_compressed.pdf · uploaded 10 Jan 2023Source
  • Document7_compressed.pdf · uploaded 10 Jan 2023Source
  • Document8_compressed.pdf · uploaded 10 Jan 2023Source
  • Document9_compressed.pdf · uploaded 10 Jan 2023Source

Technical (Architect)

  • Document1Form 1 Sept 22.pdf · uploaded 3 May 2025Source
  • Document2Form 1 Dec 22.pdf · uploaded 3 May 2025Source
  • Document3Form 1 March 23.pdf · uploaded 3 May 2025Source
  • Document4Form 1 June 23.pdf · uploaded 3 May 2025Source
  • Document5Form 1 Sept 23.pdf · uploaded 3 May 2025Source
  • Document6Form 1 Dec 23.pdf · uploaded 3 May 2025Source
  • Document7Form 1 March24.pdf · uploaded 3 May 2025Source
  • Document8Form 1 June 24.pdf · uploaded 3 May 2025Source
  • Document9Form 1 Sept 24.pdf · uploaded 3 May 2025Source
  • Document10Form 1 Dec 24.pdf · uploaded 3 May 2025Source
  • Document11Form 1 March 25.pdf · uploaded 3 May 2025Source
  • DocumentForm 1 Namo June 26.pdf · uploaded 30 Jul 2026Source

Technical (Engineer)

  • DocumentQ1-20-21.pdf · uploaded 3 May 2025Source
  • DocumentQ2-20-21.pdf · uploaded 3 May 2025Source
  • DocumentQ3-20-21.pdf · uploaded 3 May 2025Source
  • DocumentQ4-20-21.pdf · uploaded 3 May 2025Source
  • DocumentQ1-21-22.pdf · uploaded 3 May 2025Source
  • DocumentQ2-21-22.pdf · uploaded 3 May 2025Source
  • DocumentQ3-21-22.pdf · uploaded 3 May 2025Source
  • DocumentQ4-21-22.pdf · uploaded 3 May 2025Source
  • DocumentQ1-22-23.pdf · uploaded 3 May 2025Source
  • DocumentQ2-22-23.pdf · uploaded 3 May 2025Source
  • DocumentQ3-22-23.pdf · uploaded 3 May 2025Source
  • DocumentQ4-22-23.pdf · uploaded 3 May 2025Source
  • DocumentQ2-23-24.pdf · uploaded 3 May 2025Source
  • DocumentQ3-23-24.pdf · uploaded 3 May 2025Source
  • DocumentQ4-23-24.pdf · uploaded 3 May 2025Source
  • DocumentQ1-24-25.pdf · uploaded 3 May 2025Source
  • DocumentQ2-24-25.pdf · uploaded 3 May 2025Source
  • DocumentQ3-24-25.pdf · uploaded 3 May 2025Source
  • DocumentQ4-24-25.pdf · uploaded 3 May 2025Source
  • DocumentFORM 2 Namo.pdf · uploaded 5 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel S No 32/2 Parts

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 2BHK, 3BHK120 units in all
Address
S No 32/2 Parts, Balewadi Highstreet DP, BalewadiPIN 411045
Village
Balewadi, Haveli taluka
Land area for this project
5,335 sq m (57,425 sq ft)
Permissible built-up area
11,079 sq m (1,19,255 sq ft)
Sanctioned built-up area
10,102 sq m (1,08,739 sq ft)
Recreational open space
391 sq m (4,207 sq ft)
Designated bank account
212
Developed in phases
Yes

Survey, CTS, gat or plot numbers

S No 32/2 Parts

Land as published on MahaRERA's project page

S No 32/2 Parts

Boundaries

North
30 Mtr Wide DP Road
South
Truspace Prima Domus Project
East
Balance area of S No 32 2 part
West
Hiraman Balwadkar Property

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking120 units

77 of 120 units booked (64%), as the promoter reported to MahaRERA

1BHK · 2 units2BHK · 88 units3BHK · 30 units
BuildingTypeCarpet areaUnitsBooked
Wing B1BHK39.52 sq m · 425 sq ft11
Wing B2BHK49.75 sq m · 536 sq ft3018
Wing B2BHK57.52 sq m · 619 sq ft2918
Wing C1BHK39.52 sq m · 425 sq ft11
Wing C2BHK57.52 sq m · 619 sq ft2925
Wing C3BHK77.78 sq m · 837 sq ft3014

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals8

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRaviraj Gosavi—
ArchitectVK a Architecture—
Chartered accountantDSD and Associates—
Chartered accountantK K S S And Associates—
EngineerMahendra Kale—
OtherSahyadri Group of Constructions—
OtherSejal Associates—
Registered real estate agentNiraj Sharma—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Balewadi

All 1,319 projects in Balewadi · Compare Namoville with another project

Namoville in numbers

Registered deals, summarised

Deedo has 162 registered documents at Namoville, from Dec 2019 to Sep 2026: 120 sales, 11 leave and licence agreements, 13 mortgages. The median registered sale since Dec 2019 works out to about ₹7,500 per sq ft, at a median of ₹53 L a deal; 0% of sales were resales.

What is the price per sq ft at Namoville?
The median registered sale since Dec 2019 works out to about ₹7,500 per sq ft, at a median of ₹53 L a deal; 0% of sales were resales.
How many properties have been sold at Namoville?
120 sales are registered at Namoville.
Are properties at Namoville rented out?
Yes: 11 leave and licence agreements are registered at Namoville, at a median rent since Dec 2019 of about ₹27,000 a month with a deposit of about ₹50,000.
Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at Namoville by Deedo, last updated with deals registered in Sep 2026.

Latest deal · Primary sale · Aug 2026

₹75 L–1 Cr

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · registered documents (Index II)Data through is when MahaRERA's project page was last read.Report a problemMethodology