Skip to content
Others · 1 building · 70 unitsRERA P52100079734

33 Mayfair

Deedo IDDP-PUN-TBJP

Completion was pushed back 4 months, to May 2028; no MahaRERA orders on record; 0% of its units are booked.

Balewadi, Pune 411045 · Property rates in Balewadi · by Blue Pearl Infra

DeliveryExtended 4 moPromised Jan 2028 · now due May 2028RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 70 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to May 2028

  • This projectRegistered 24 Mar 2025, completion promised 29 Jan 2028, revised to 29 May 2028.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

  • Other · Sep 2026No amount
Latest registered deeds in this project
MonthFlatKindAreaPriceRecord
Sep 2026KitchenOther—View Other, Sep 2026

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100079734
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210007973424 Mar 202529 Jan 202829 May 2028Blue Pearl InfraProject page
Documents72

1 document held by Deedo, 71 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardBlue Pearl Infra Pan Card.pdf · uploaded 19 Feb 2025Source
  • Other – FinanceBlue Pearl Infra_RERA Unit Declaration_sr_no_33.pdf · uploaded 28 Feb 2025Source

Legal

  • Declaration Form BBlue Pearl Infra_Rera Affidavit Cum Declaration__493_Dated_4_02_2025.pdf · uploaded 24 Feb 2025Source
  • Other – LegalSale Deed Compressed.pdf · uploaded 8 Mar 2025Source
  • Legal Title reportS No 33-Balewadi RERA_0001_compressed.pdf · uploaded 8 Mar 2025Source

Migrated

  • 1 PAN CardBlue Pearl Infra Pan Card.pdf · uploaded 19 Feb 2025Source
  • 1 Copy of Layout Approval (in case of layout)Plan 1_11zon.pdf · uploaded 19 Feb 2025Source
Show all 72 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentCC_11zon.pdf · uploaded 19 Feb 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan 1_11zon.pdf · uploaded 19 Feb 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentPlan 2_11zon.pdf · uploaded 19 Feb 2025Source
  • 3 Building Plan Approval / NA Order for plotted developmentPlan 3_11zon.pdf · uploaded 19 Feb 2025Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance Finance.pdf · uploaded 20 Feb 2025Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance Legal.pdf · uploaded 20 Feb 2025Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 20 Feb 2025Source
  • 1 CERSAI detailsCersai Declaration.pdf · uploaded 20 Feb 2025Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance Finance.pdf · uploaded 20 Feb 2025Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance Legal.pdf · uploaded 20 Feb 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectSecured Unsecured.pdf · uploaded 20 Feb 2025Source
  • 1 Declaration in FORM BBlue Pearl Infra_Rera Affidavit Cum Declaration__493_Dated_4_02_2025.pdf · uploaded 24 Feb 2025Source
  • 1 Other – FinanceBlue Pearl Infra_RERA Unit Declaration_sr_no_33.pdf · uploaded 28 Feb 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A - All RERA Designated Bank Accounts -Area Sharing.pdf · uploaded 4 Mar 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)IDBI BANK RERA.pdf · uploaded 4 Mar 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A Disclosure of Interest.pdf · uploaded 5 Mar 2025Source
  • 1 Copy of the legal title reportS No 33-Balewadi RERA_0001_compressed.pdf · uploaded 8 Mar 2025Source
  • 1 Proforma of Allotment letterAL_33 Mayfair_Blue Pearl Infra_25022025.pdf · uploaded 8 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)GetUserDocumentFileContent.pdf · uploaded 8 Mar 2025Source
  • 1 Other – LegalSale Deed Compressed.pdf · uploaded 8 Mar 2025Source
  • 1 Deviation Report with respect to Allotment letterDeviation_AL_33 Mayfair_Blue Pearl Infra_05032025.pdf · uploaded 8 Mar 2025Source
  • 1 Other – TechnicalOrder No 50.pdf · uploaded 8 Mar 2025Source
  • 2 Other – Technical1 Other – Technical (4).pdf · uploaded 8 Mar 2025Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation_AFS_33 Mayfair_Blue Pearl Infra_05032025.pdf · uploaded 8 Mar 2025Source
  • 1 Proforma of Agreement for sale1 Deviation Report with respect to model copy of Agreement (2).pdf · uploaded 8 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 12 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Updated Form 1 Infra.pdf · uploaded 18 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - 33 Mayfair as on March 2025.pdf · uploaded 12 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - 33 Mayfair as on March 2025.pdf · uploaded 12 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - 33 Mayfair as on March 2025.pdf · uploaded 15 May 2025Source
  • Withdrawal Update Form 1Form 1 - 33 Mayfair as on June 2025.pdf · uploaded 25 Nov 2025Source
  • Withdrawal Update Form 1Form 1 - 33 Mayfair as on Sept 2025.pdf · uploaded 25 Nov 2025Source
  • Withdrawal Update Form 2Form 2 - 33 Mayfair as on June 2025.pdf · uploaded 25 Nov 2025Source
  • Withdrawal Update Form 2Form 2 - 33 Mayfair as on Sept 2025.pdf · uploaded 25 Nov 2025Source
  • Withdrawal Update Form 3Form 3 - 33 Mayfair as on June 2025.pdf · uploaded 25 Nov 2025Source
  • Withdrawal Update Form 3Form 3 - 33 Mayfair as on Sept 2025.pdf · uploaded 25 Nov 2025Source
  • Withdrawal Update Form 1Form 1 - 33 Mayfair as on Dec 2025.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 1Form 1 - 33 Mayfair as on March 2026.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 2Form 2 - 33 Mayfair as on March 2026.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 2Form 2 - 33 Mayfair as on March 2026.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 3Form 3 - 33 Mayfair as on Dec 2025.pdf · uploaded 12 May 2026Source
  • Withdrawal Update Form 3Form 3 - 33 Mayfair as on March 2026.pdf · uploaded 12 May 2026Source
  • Form 5 (FY 2024-2025)Form 5 - 33 Mayfair as on Fy 2024-25.pdf · uploaded 4 Jun 2026Source
  • Form 2A (FY 2024-2025)Form_2A_2024_2025_19_08_2026.pdf · uploaded 21 Aug 2026Source
  • Form 2A (FY 2025-2026)Form_2A_2025_2026_19_08_2026.pdf · uploaded 21 Aug 2026Source
  • Withdrawal Update Form 1Form 1 - 33 Mayfair as on June 2026.pdf · uploaded 26 Aug 2026Source
  • Withdrawal Update Form 2Form 2 - 33 Mayfair as on June 2026.pdf · uploaded 26 Aug 2026Source
  • Withdrawal Update Form 3Form 3 - 33 Mayfair as on June 2026_compressed.pdf · uploaded 26 Aug 2026Source
  • Withdrawal Update Form 1Form 1 - 33 Mayfair as on June 2026.pdf · uploaded 3 Sep 2026Source
  • Withdrawal Update Form 2Form 2 - 33 Mayfair as on June 2026.pdf · uploaded 3 Sep 2026Source
  • Withdrawal Update Form 3Form 3 - 33 Mayfair as on June 2026_compressed.pdf · uploaded 3 Sep 2026Source

Technical

  • DocumentPlan 1_11zon.pdf · uploaded 19 Feb 2025Source
  • DocumentPlan 1_11zon.pdf · uploaded 19 Feb 2025Source
  • DocumentPlan 2_11zon.pdf · uploaded 19 Feb 2025Source
  • DocumentPlan 3_11zon.pdf · uploaded 19 Feb 2025Source
  • Other – TechnicalOrder No 50.pdf · uploaded 8 Mar 2025Source
  • Other – Technical1 Other – Technical (4).pdf · uploaded 8 Mar 2025Source
  • DocumentLayout Approval- Sheet 1- Highlighted.pdf · uploaded 3 Sep 2026Source
  • DocumentBuilding Approval- Sheet 2.pdf · uploaded 3 Sep 2026Source
  • DocumentBuilding Approval- Sheet 3.pdf · uploaded 3 Sep 2026Source

Technical (Architect)

  • DocumentForm 1 - 33 Mayfair as on March 2025.pdf · uploaded 12 Apr 2025Source
  • DocumentForm 1 - 33 Mayfair as on June 2026.pdf · uploaded 26 Aug 2026Source

Technical (Engineer)

  • DocumentForm 2 - 33 Mayfair as on March 2025.pdf · uploaded 15 May 2025Source
  • DocumentForm 2 - 33 Mayfair as on June 2026.pdf · uploaded 26 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 33/1/39, 33/4(p)

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
Studio Apartment70 units in all
Address
Survey No. 33/1/38, 33/1/39, 33/4(p), Balewadi, Pune, Balewadi, PunePIN 411045
Village
Balewadi, Haveli taluka
Land area for this project
1,125 sq m (12,109 sq ft)
Permissible built-up area
4,664 sq m (50,199 sq ft)
Sanctioned built-up area
4,664 sq m (50,199 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
82
Developed in phases
No

Survey, CTS, gat or plot numbers

33/1/3933/4(p)Survey No. 33/1/38

Land as published on MahaRERA's project page

Survey No. 33/1/38, 33/1/39, 33/4(p)

Boundaries

North
By Property S No 33-1-13 of MrsSangeeta VijayOswal
South
By Tejonidhi Apartment
East
By Road
West
By Amar Tech Park

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking70 units

0 of 70 units booked (0%), as the promoter reported to MahaRERA

Studio Apartment · 70 units
TypeCarpet areaUnitsBooked
Studio Apartment16.66 sq m · 179 sq ft100
Studio Apartment19.91 sq m · 214 sq ft600

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals6

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectT F Cube—
Chartered accountantManish G Agrawal—
Chartered accountantN B Sayed & Associates Chartered Accountant—
EngineerE-Struct Consulting Structural & Civil Engineers—
EngineerOmkar Kale—
EngineerVishal Vaghela—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Balewadi

All 1,319 projects in Balewadi · Compare 33 Mayfair with another project

33 Mayfair in numbers

Registered deals, summarised

Deedo has 1 registered document at 33 Mayfair, from Sep 2026 to Sep 2026: .

Where does this data come from?
The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at 33 Mayfair by Deedo, last updated with deals registered in Sep 2026.

Latest deal · Other · Sep 2026

Exact price & Index II

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · registered documents (Index II)Data through is when MahaRERA's project page was last read.Report a problemMethodology