Emonics Tower
Deedo IDDP-PAL-H01KIts promised completion date, Jun 2026, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 18% of its units are booked.
Vasaivirar City (M Corp), Palghar 401208 · by Munish Group Of Companies, Munish Group Of Company
Buying a flat here?
See every deed registered on it.
Its promised completion date, Jun 2026, has passed and MahaRERA does not show it completed
- This projectRegistered 18 Feb 2021, completion promised 30 Jun 2026, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP99000028345
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000028345 | 18 Feb 2021 | 30 Jun 2026 | 30 Jun 2026 | Munish Group Of Companies | Project page |
Documents88
2 documents held by Deedo, 86 filings listed on MahaRERA's project page
Show all 88 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportTITLE REPORT.pdf · uploaded 13 Feb 2021Source
- 1 Details of encumbrancesENCOMBURANCE.pdf · uploaded 13 Feb 2021Source
- 1 Copy of Layout Approval (in case of layout)BLUEPRINT1.pdf · uploaded 13 Feb 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentBLUEPRINT.pdf · uploaded 13 Feb 2021Source
- 2 Building Plan Approval / NA Order for plotted developmentBLUEPRINT1.pdf · uploaded 13 Feb 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCCEMONICS.pdf · uploaded 13 Feb 2021Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 13 Feb 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CACERTIFICATE.pdf · uploaded 13 Feb 2021Source
- 1 Proforma of Allotment letterDRAFT AGREEMENT.pdf · uploaded 13 Feb 2021Source
- 1 Otherpower Emonic.pdf · uploaded 16 Feb 2021Source
- 1 Declaration about Commencement Certificate1 Commencement Certificates _ NA Order for plotted development.pdf · uploaded 21 Mar 2022Source
- 1 CERSAI detailsEMONICS TOWER (1).pdf · uploaded 21 Mar 2022Source
- 2 PAN CardMunish Group Revised PAN CARD.pdf · uploaded 7 Apr 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1Arch cft SEC-III BLDG 2 WING B (April-Jun 2023).pdf · uploaded 2 Jun 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 Arch cft SEC-III BLDG 2 WING B July-Sept 2023.pdf · uploaded 2 Jun 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1Arch cft SEC-III BLDG 2 WING B (Oct-Dec 2023).pdf · uploaded 2 Jun 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1Arch cft SEC-III BLDG 2 WING B (Jan-March 2024).pdf · uploaded 2 Jun 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-II APR -JUN 2023.pdf · uploaded 2 Jun 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-II JUL -SEP 2023.pdf · uploaded 2 Jun 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-II OCT -DEC 2023.pdf · uploaded 2 Jun 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-II 31 MAR 2024.pdf · uploaded 2 Jun 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Emonics cert 1.pdf · uploaded 2 Jun 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)emonics cert 2.pdf · uploaded 2 Jun 2024Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)emonics cert 3.pdf · uploaded 2 Jun 2024Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)emonics cert 4.pdf · uploaded 2 Jun 2024Source
- 1 Disclosure of sold/ booked inventorySOLD UNSOLD FLAT DETAILS.pdf · uploaded 2 Jun 2024Source
- 1 Proforma of Agreement for sale1 Proforma of Allotment letter (2).pdf · uploaded 2 Jun 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Qtr 3 Oct 24 to Dec 24.pdf · uploaded 22 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Qtr 3 Oct 24 to Dec 24.pdf · uploaded 22 Feb 2025Source
- 1 Disclosure of sold/ booked inventoryEmonics Tower - Sold- Unsold Details.pdf · uploaded 22 Feb 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Qtr 3 Oct to Dec 24.pdf · uploaded 22 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Fund Withdrawal_emonic tower.pdf · uploaded 24 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Jan 25 to Mar 25.pdf · uploaded 20 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Fund Withdrawal.pdf · uploaded 20 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 JAN 25 TO MAR 25.pdf · uploaded 20 Apr 2025Source
- 1 Disclosure of sold/ booked inventoryFLAT SOLD UNSOLD DETAILS.pdf · uploaded 20 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A JAN 25 TO MAR 25.pdf · uploaded 20 Apr 2025Source
- Form 1FORM 1 _ Q1 APR25 TO JUNE 25.pdf · uploaded 20 Jul 2025Source
- Form 2FORM 2 Q1 APRIL 25 TO JUNE25.pdf · uploaded 20 Jul 2025Source
- Form 3Form 3 Fund Withdrawal_Q1.pdf · uploaded 20 Jul 2025Source
- Disclosure of Sold and Booked InventoryQ1 APRIL 25 TO JUNE 25 SOLD UNSOLD DETAILS.pdf · uploaded 20 Jul 2025View
- OthersFORM 2A Q1 APR 25 TO JUNE 25.pdf · uploaded 20 Jul 2025Source
- Form 1FORM 1.pdf · uploaded 18 Apr 2026Source
- Form 2FORM 2.pdf · uploaded 18 Apr 2026Source
- Form 3Form 3 Fund Withdrawal_Q1.pdf · uploaded 18 Apr 2026Source
- Disclosure of Sold and Booked InventoryQ1 APRIL 25 TO JUNE 25 SOLD UNSOLD DETAILS.pdf · uploaded 18 Apr 2026View
- OthersFORM 2A.pdf · uploaded 18 Apr 2026Source
- Form 1Form 1 Qtr 3 Oct 24 to Dec 24.pdf · uploaded 18 Apr 2026Source
- Form 2Form 2 Qtr 3 Oct 24 to Dec 24.pdf · uploaded 18 Apr 2026Source
- Form 3Form 3 Fund Withdrawal_Q1.pdf · uploaded 18 Apr 2026Source
- Disclosure of Sold and Booked InventoryEmonics Tower - Sold- Unsold Details.pdf · uploaded 18 Apr 2026View
- OthersForm 2A Qtr 3 Oct to Dec 24.pdf · uploaded 18 Apr 2026Source
- Form 1Form 1 Jan 25 to Mar 25.pdf · uploaded 18 Apr 2026Source
- Form 2FORM 2 JAN 25 TO MAR 25.pdf · uploaded 18 Apr 2026Source
- Form 3Form 3 Fund Withdrawal.pdf · uploaded 18 Apr 2026Source
- Disclosure of Sold and Booked InventoryFLAT SOLD UNSOLD DETAILS.pdf · uploaded 18 Apr 2026View
- OthersFORM 2A JAN 25 TO MAR 25.pdf · uploaded 18 Apr 2026Source
- Form 1FORM 1.pdf · uploaded 18 Apr 2026Source
- Form 2FORM 2.pdf · uploaded 18 Apr 2026Source
- Form 3Form 3 Fund Withdrawal_Q1.pdf · uploaded 18 Apr 2026Source
- Disclosure of Sold and Booked InventoryEmonics Tower- Sold-Unsold Details...pdf · uploaded 18 Apr 2026View
- OthersFORM 2A.pdf · uploaded 18 Apr 2026Source
- Form 1FORM 1.pdf · uploaded 18 Apr 2026Source
- Form 2FORM 2.pdf · uploaded 18 Apr 2026Source
- Form 3Form 3 Fund Withdrawal_Q1.pdf · uploaded 18 Apr 2026Source
- Disclosure of Sold and Booked InventoryEmonics Tower- Sold- Unsold Details.....pdf · uploaded 18 Apr 2026View
- OthersFORM 2A.pdf · uploaded 18 Apr 2026Source
- Form 5 (FY 2025-2026)FORM 5 MUNISH GROUP OF COMPANIES.pdf · uploaded 30 May 2026Source
- Withdrawal Update Form 1form 1Arch cft SEC-III BLDG 2 WING B (Jan-March 2024).pdf · uploaded 17 Jul 2026Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 17 Jul 2026Source
- Withdrawal Update Form 3FORM 3.pdf · uploaded 17 Jul 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 2/1, 2/20
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Office space, Shop62 units in all
- Address
- Bldg. No. 2 Wing B, Survey No. 75, Hissa No. 1, 21 And 220, Emonics Tower, Near Agarwal Exotica, Madhuban Township, Gokhiware Vasai EastPIN 401208
- Village
- Vasai-Virar City (M Corp), Vasai taluka
- Land area for this project
- 5,574 sq m (60,001 sq ft)
- Permissible built-up area
- 2,258 sq m (24,305 sq ft)
- Sanctioned built-up area
- 2,258 sq m (24,305 sq ft)
- Recreational open space
- 5,574 sq m (60,001 sq ft)
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
BLDG. NO. 2 WING B, SURVEY NO. 75, HISSA NO. 1, 21 AND 220
Boundaries
- North
- Agarwal Exotica
- South
- Road
- East
- Madhuban Main Road
- West
- Foolbal Ground
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking62 units
11 of 62 units booked (18%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 35.45 sq m · 382 sq ft | 13 | 0 |
| 1BHK | 36.56 sq m · 394 sq ft | 26 | 4 |
| 2BHK | 50.67 sq m · 545 sq ft | 13 | 2 |
| Office space | 22.91 sq m · 247 sq ft | 1 | 0 |
| Office space | 36.38 sq m · 392 sq ft | 1 | 1 |
| Office space | 37.09 sq m · 399 sq ft | 1 | 0 |
| Office space | 53.49 sq m · 576 sq ft | 1 | 1 |
| Shop | 10.68 sq m · 115 sq ft | 1 | 0 |
Show all 13 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 13.63 sq m · 147 sq ft | 1 | 0 |
| Shop | 14.93 sq m · 161 sq ft | 1 | 1 |
| Shop | 15.26 sq m · 164 sq ft | 1 | 1 |
| Shop | 15.6 sq m · 168 sq ft | 1 | 0 |
| Shop | 18.58 sq m · 200 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Engineer | Mukesh Kumar | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Vasaivirar City (M Corp)
- Yashvi Pride Building No.3 Wing-ORERA P99000081100
- Urban HomesRERA P99000081093
- Tania WillowsRERA P99000081082
- Shalibhadra HeightsRERA P99000081076
- Mukti Narayan Co Op Hsg Soc LtdRERA P99000081056
- Marshal HeightsRERA P99000081046
- Dhananjay StarlightRERA P99000081038
- Crystal CrownRERA P99000081027
All 750 projects in Vasaivirar City (M Corp) · Compare Emonics Tower with another project