4 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects14
Registrations14
Completion still due95 past their date
Median extension4 months43% of registrations extended
Regulatory cases0none on MahaRERA's lists
7 in 10 registrations run late here
14 MahaRERA registrations in Vada (Ct)
4 not yet due5 extended, not yet due5 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Vada (Ct)
14 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Tathastu Shopping ComplexMs Construction | Due Dec 2027 | — | — |
| Sontakke ArcadeSiddhivinayak Developers | Due Mar 2031 | — | — |
| Swastik HeightsSwastik Developers | Due Apr 2030, extended 4 mo | — | — |
| Swami EnclaveM/s. Om Sai Ram Infra | Due Feb 2029, extended 4 mo | — | — |
| Dream ResidencyTrimurti Enterprise | Due Sep 2027, extended 4 mo | — | 23% |
| Parnkuti Row HouseSaideep Builders and Developers | Due Dec 2027 | — | 0% |
| Status Pride - Phase 1Milan Madhukar Patkar | Due Nov 2027, extended 4 mo | — | 11% |
| Rajeshree PlazaLiva Infra Builders and Developers | Due Mar 2027, extended 4 mo | — | 49% |
| Sitaram HeightsM/s. Om Sai Ram Infra | 1 yr 4 mo late | — | 16% |
| Swapnapurti ComplexYashlaxmi Creations | Due Dec 2029 | — | 0% |
| Parasharam PrideDurva Builders and Developers | 2 yrs 11 mo late | — | 0% |
| Mauli Residency - Navami DashamiSai Pooja Developers | 3 yrs 10 mo late | — | 0% |
| Strawberry GardenTanish Realtors | 3 yrs 11 mo late | — | 31% |
| Bhagirathi C WingChittaranjan Estates Pvt. Ltd. | 8 yrs late | — | 41% |
Nearby: other localities in Vada
Most active promoters
- M/s. Om Sai Ram Infra2 projects
- Chittaranjan Estates Pvt. Ltd.1 project
- Durva Builders and Developers1 project
- Liva Infra Builders and Developers1 project
- Milan Madhukar Patkar1 project
- Ms Construction1 project
- Saideep Builders and Developers1 project
- Sai Pooja Developers1 project
- Siddhivinayak Developers1 project
- Swastik Developers1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology