Strawberry Garden
Deedo IDDP-PAL-6N1QIts promised completion date, Nov 2022, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 31% of its units are booked.
Vada (Ct), Palghar 421303 · Promoter: Tanish Realtors
Its promised completion date, Nov 2022, has passed and MahaRERA does not show it completed
- This projectRegistered 4 Apr 2018, completion promised 15 Nov 2022, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
3 buildings
Open a building to see every flat, floor by floor.
- Strawberry Garden Building A6 floors · 35 units0% booked
- Strawberry Garden Building B6 floors · 18 units100% booked
- Strawberry Garden Building C3 floors · 6 units0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP99000015898
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000015898 | 4 Apr 2018 | 15 Nov 2022 | 15 Nov 2022 | Tanish Realtors | Project page |
Documents36
1 document held by Deedo, 35 filings listed on MahaRERA's project page
Finance
- PAN CardPAN.pdf · uploaded 4 May 2023Source
Legal
Migrated
- 1 Copy of the legal title reportTITLE CERTIFICATE.pdf · uploaded 23 Mar 2018Source
- 1 Details of encumbrancesENCUMBRANCES.pdf · uploaded 23 Mar 2018Source
- 1 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 23 Mar 2018Source
- 1 Building Plan Approval (IOD)BLUE PRINT.pdf · uploaded 23 Mar 2018Source
Show all 36 documentsShow fewer documents
Migrated
- 2 Building Plan Approval (IOD)LAYOUT.pdf · uploaded 23 Mar 2018Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 23 Mar 2018Source
- 1 Declaration in FORM BFORM B SEE RULE 3(6) DEVELOPERS.pdf · uploaded 23 Mar 2018Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECH CERE TYPE A.pdf · uploaded 23 Mar 2018Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CER TYPE B.pdf · uploaded 23 Mar 2018Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECH CER TYPE C.pdf · uploaded 23 Mar 2018Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERT A.pdf · uploaded 23 Mar 2018Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERT B.pdf · uploaded 23 Mar 2018Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CER C.pdf · uploaded 23 Mar 2018Source
- 1 Certificates of CA (Form 3)CA CERT.pdf · uploaded 23 Mar 2018Source
- 1 Proforma of Allotment letterAGREEMENT compress.PDF · uploaded 23 Mar 2018Source
- 1 PAN CardPAN.pdf · uploaded 4 May 2023Source
- 2 a Details of encumbrances concerned to FinanceEncumbrances to legal.pdf · uploaded 4 May 2023Source
- 1 b Details of encumbrances concerned to LegalEncumbrances to legal.pdf · uploaded 4 May 2023Source
- 1 Declaration about Commencement CertificateFORM D.pdf · uploaded 4 May 2023Source
- 1 Disclosure of sold/ booked inventorydisclosure book sold.pdf · uploaded 4 May 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Annexure F form 5 18-19.pdf · uploaded 4 May 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Annexure F form 5 19-20.pdf · uploaded 4 May 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Annexure F form 5 20-21.pdf · uploaded 4 May 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Annexure F form 5 21-22.pdf · uploaded 4 May 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSEPERATE BANK ACCOUNT.pdf · uploaded 4 May 2023Source
- 1 Deviation Report with respect to Allotment letterdeviation report for allotment.pdf · uploaded 4 May 2023Source
- 1 Deviation Report with respect to model copy of AgreementDEVIATION REPORT OF SALE AGREEMENT-.pdf · uploaded 4 May 2023Source
Technical
Technical (Architect)
- DocumentARCHITECH CER TYPE C.pdf · uploaded 23 Mar 2018Source
Technical (Engineer)
- DocumentENGINEER CER C.pdf · uploaded 23 Mar 2018Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals164/2
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1 BHK, 2 BHK, Row house59 units in all
- Address
- 164/2, Shivaji Nagar Road, Shivaji NagarPIN 421303
- Village
- Vada (CT), Vada taluka
- Location
- 19.65260, 73.13830
- Designated bank account
- 19
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Boundaries
- North
- Mrs Kamla Kalale And Family
- South
- Bhagirathi Complex
- East
- Mr Maruti Raut And Suresh Patil
- West
- Shasthri Nagar Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking59 units
18 of 59 units booked (31%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Strawberry Garden Building A | 1 BHK | 42.17 sq m · 454 sq ft | 18 | 0 |
| Strawberry Garden Building A | 1 BHK | 42.61 sq m · 459 sq ft | 1 | 0 |
| Strawberry Garden Building A | 1 BHK | 43.06 sq m · 463 sq ft | 4 | 0 |
| Strawberry Garden Building A | 1 BHK | 43.91 sq m · 473 sq ft | 8 | 0 |
| Strawberry Garden Building A | 1 BHK | 45.65 sq m · 491 sq ft | 4 | 0 |
| Strawberry Garden Building B | 2 BHK | 53.76 sq m · 579 sq ft | 2 | 2 |
| Strawberry Garden Building B | 2 BHK | 56.08 sq m · 604 sq ft | 8 | 8 |
| Strawberry Garden Building B | 2 BHK | 57.93 sq m · 624 sq ft | 8 | 8 |
| Strawberry Garden Building C | Row house | 117.39 sq m · 1,264 sq ft | 6 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals2
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Aakar Architects And Interior Designer | — |
| Engineer | Meshram And Thukral | — |
Source: MahaRERA project page. Contact details are not shown.