RERA projects in Kudus (Ct)
3 projects under 3 MahaRERA registrations, registered 2017–2026. 100% have a completion date extended beyond the one promised.
Locality
3RERA projects
3Registrations
3Completion still due0 past their completion date
4 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
30Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 0 |
| 2019 | 0 |
| 2020 | 0 |
| 2021 | 0 |
| 2022 | 0 |
| 2023 | 0 |
| 2024 | 0 |
| 2025 | 1 |
| 2026 | 1 |
Projects in Kudus (Ct)
3 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Dream ParkDream Builders | PR1240002600973 | 29 Jun 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Dream ParkDream Builders | P99000080566 | 16 Jun 2025 | 30 Jan 2028 | 30 May 2028 | Extended 4 mo | 0 |
| Shree Radheyshyam NagarSudesh Radheyshyam Gupta | P99000011878 | 31 Aug 2017 | 30 Dec 2023 | 30 Dec 2030 | Extended 84 mo | 0 |
Other localities in Vada
Most active promoters
By projects registered here, as named on MahaRERA.
- Dream Builders2 projects
- Sudesh Radheyshyam Gupta1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology