Completion was pushed back 4 months, to Apr 2031; no MahaRERA orders on record; 4% of its units are booked.

Tembhode, Palghar 401404 · by Nivaas Realtor

DeliveryExtended 4 moPromised Dec 2030 · now due Apr 2031RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales4% booked2 of 48 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2031

  • This projectRegistered 15 May 2026, completion promised 31 Dec 2030, revised to 30 Apr 2031.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

4 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationPM1240002600439
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PM124000260043915 May 202631 Dec 203030 Apr 2031Nivaas RealtorProject page
Documents31

1 document held by Deedo, 30 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan card.pdf · uploaded 22 Feb 2026Source
  • GSTIN DocumentGST Nivaas.pdf · uploaded 13 Apr 2026Source

Legal

  • OthersPartnership Deed Scanned.pdf · uploaded 22 Feb 2026Source
  • OthersDisclosure of interest in other rera estate organizations -KASHYAP SONI.pdf · uploaded 22 Feb 2026Source
  • OthersDisclosure of interest in other rera estate organizations -NEEL DESAI.pdf · uploaded 22 Feb 2026Source
  • OthersDisclosure of interest in other rera estate organizations -SHAILESH DESAI.pdf · uploaded 22 Feb 2026Source
  • Declaration Form BTitle Report with Search.pdf · uploaded 22 Feb 2026Source
Show all 31 documentsShow fewer documents

Legal

  • Declaration Form BForm B - Developers.pdf · uploaded 23 Feb 2026Source
  • OthersAffidavit No Experience (1).pdf · uploaded 19 Mar 2026Source
  • Others7(12).pdf · uploaded 19 Mar 2026Source

Migrated

  • Withdrawal Update Form 1Form-1 June 2026.pdf · uploaded 14 Aug 2026Source
  • Withdrawal Update Form 2Form-2 June 2026.pdf · uploaded 14 Aug 2026Source
  • Withdrawal Update Form 3Form-3 June 2026.pdf · uploaded 14 Aug 2026Source

Planning Authority

  • Documenth2hBQpnV2cPartnership_Deed_Nivaas_Relator.pdf · uploaded 22 Feb 2026Source
  • DocumentCert_B_591717_279TKxMJSign.pdf · uploaded 22 Feb 2026Source
  • Document1767681668_CBPPE-25-138630_R0.pdf_2_14DSE_Sign.pdfSign.pdf · uploaded 22 Feb 2026Source
  • DocumentJ7DbKhR0OBटेंभोडे_129_85_प्लॉट_नं._9_Satbara.pdf · uploaded 22 Feb 2026Source
  • Document1767681668_CBPPE-25-138630_R0.html · uploaded 22 Feb 2026Source

Technical

  • DocumentApproved Plan.pdf · uploaded 22 Feb 2026Source
  • OthersAffidavit No Experience.pdf · uploaded 22 Feb 2026Source
  • OthersForm 1.pdf · uploaded 7 Mar 2026Source
  • OthersFORM 2.pdf · uploaded 7 Mar 2026Source
  • DocumentAnnexure-A.pdf · uploaded 9 Mar 2026Source
  • DocumentLayout Plan Highlighted.pdf · uploaded 13 Apr 2026Source
  • DocumentBuilding plan.pdf · uploaded 13 Apr 2026Source
  • OthersPARKING STATEMENT .pdf · uploaded 13 Apr 2026Source
  • OthersClarification Regarding Parking.pdf · uploaded 28 Apr 2026Source
  • OthersClarification Regarding parking with parking statement.pdf · uploaded 28 Apr 2026Source

Technical (Architect)

  • DocumentForm-1 June 2026.pdf · uploaded 14 Aug 2026Source

Technical (Engineer)

  • DocumentForm-2 June 2026.pdf · uploaded 14 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel PLOT NO.09, S.NO.129/85

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Unit types
—52 units in all
Address
Manor-Mahim Highway, Palghar WestPIN 401404
Village
Tembhode, Palghar taluka
Land area for this project
1,339 sq m (14,410 sq ft)
Permissible built-up area
5,212 sq m (56,097 sq ft)
Sanctioned built-up area
5,064 sq m (54,509 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
76
Developed in phases
Yes

Survey, CTS, gat or plot numbers

PLOT NO.09S.NO.129/85

Land as published on MahaRERA's project page

plot_no 9 city_survey_gut_no S.NO.129/85, PLOT NO.09 final_plot_no 9 sector_no - mauje TEMBHODE road_street 45MT. & 12MT. society -

Boundaries

North
45 Mtr Wide Dp Road
South
Adj Plot
East
Adj Plot
West
12 Mytr Wide Dp Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking52 units

52 units registered

— · 52 units
BuildingTypeCarpet areaUnits
Wing-A——20
Wing-B——32

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.