D K Residency
Deedo IDDP-PAL-GTM6Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 27% of its units are booked.
Tembhode, Palghar 401404 · Promoter: Kshipra Realty
Completion was pushed back 4 months, to Apr 2029
- This projectRegistered 17 Apr 2026, completion promised 31 Dec 2028, revised to 30 Apr 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
11 buildings
Open a building to see every flat, floor by floor.
- Row House No 13 floors · 1 unit0% booked
- Row House No 103 floors · 1 unit0% booked
- Row House No 113 floors · 1 unit0% booked
- Row House No 23 floors · 1 unit100% booked
- Row House No 33 floors · 1 unit100% booked
- Row House No 43 floors · 1 unit100% booked
- Row House No 53 floors · 1 unit0% booked
- Row House No 63 floors · 1 unit0% booked
- Row House No 73 floors · 1 unit0% booked
- Row House No 83 floors · 1 unit0% booked
- Row House No 93 floors · 1 unit0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPR1240002600127
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PR1240002600127 | 17 Apr 2026 | 31 Dec 2028 | 30 Apr 2029 | Kshipra Realty | Project page |
Documents41
1 document held by Deedo, 40 filings listed on MahaRERA's project page
Finance
- PAN CardPAN Card.pdf · uploaded 27 Feb 2026Source
- GSTIN DocumentGST Certificate pdf.pdf · uploaded 2 Mar 2026Source
- OthersCERSAI.pdf · uploaded 2 Mar 2026Source
- OthersDeclaration for project Cost.pdf · uploaded 27 Mar 2026Source
- OthersAffidavit by landowner for row house.pdf · uploaded 28 Mar 2026Source
Show all 41 documentsShow fewer documents
Legal
- OthersSelf Declaration of Land owners Share in the project.pdf · uploaded 20 Feb 2026Source
- OthersKshipra NA Order.pdf · uploaded 20 Feb 2026Source
- Otherskshira 7 12.pdf · uploaded 20 Feb 2026Source
- OthersForm B Affidavit for Landowner.pdf · uploaded 20 Feb 2026Source
- OthersCommencement Certificate Form D.pdf · uploaded 20 Feb 2026Source
- OthersAnnexure A Disclosure of Interest in other Real Estate Organizations.pdf · uploaded 20 Feb 2026Source
- Declaration Form BForm B Affidavit ( Yadnesh Gharat Promoter).pdf · uploaded 20 Feb 2026Source
- Declaration Form BKshipra DA_11zon (1).pdf · uploaded 20 Feb 2026Source
- OthersDeviation Report for model allotment.pdf · uploaded 23 Feb 2026Source
- OthersDeviation Report.pdf · uploaded 23 Feb 2026Source
- OthersLandowner no Sale declaration (2).pdf · uploaded 2 Mar 2026Source
- Declaration Form BKshipra Title Clearance.pdf · uploaded 2 Mar 2026Source
Migrated
Planning Authority
- DocumentCert_B_420045_2790UAKQSign.pdf · uploaded 23 Feb 2026Source
- DocumentNuTFaiaCgF7_12_latest.pdf · uploaded 23 Feb 2026Source
- Document1727946368_CBPPE-24-00461_R0.pdf_2_69DSE_Sign.pdfSign.pdf · uploaded 23 Feb 2026Source
- DocumentNuTFaiaCgFnp_letter.pdf · uploaded 23 Feb 2026Source
- Document1727946368_CBPPE-24-00461_R0.html · uploaded 23 Feb 2026Source
Technical
- DocumentApproval Plan (2).pdf · uploaded 9 Feb 2026Source
- DocumentKshipra NA Order.pdf · uploaded 9 Feb 2026Source
- DocumentAnnexure-A as per order Declaration cum undertaking.pdf · uploaded 20 Feb 2026Source
- DocumentLayout Plan.pdf · uploaded 2 Mar 2026Source
- OthersArchetech certificate Form 1.pdf · uploaded 2 Mar 2026Source
- OthersEngg Certificate Form 2.pdf · uploaded 2 Mar 2026Source
- OthersArchitect Declaration Cert260318165005 for Parking.pdf · uploaded 27 Mar 2026Source
- OthersSanction plan area highlight in Yellow.pdf · uploaded 27 Mar 2026Source
- DocumentLayout Plan and Approval Plan highlight (1).pdf · uploaded 12 Apr 2026Source
- DocumentRow house Approval Plan Highlight Parking and Floors (2) (1) (2).pdf · uploaded 12 Apr 2026Source
- Otherscc verification mail screenshot.pdf · uploaded 12 Apr 2026Source
Technical (Architect)
- DocumentArch cert 2026 Form 1.pdf · uploaded 20 Jul 2026Source
Technical (Engineer)
- Documentengg cert jun 2026 Form 2.pdf · uploaded 20 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsSURVEY NUMBER 75/2/1/2/2/12/13/B/1
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —11 units in all
- Address
- Survey Number 75/2/1/2/2/12/13/B/1, TembhodePIN 401404
- Village
- Tembhode, Palghar taluka
- Location
- 19.70234, 72.75556
- Designated bank account
- 76
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Boundaries
- North
- Land of Kadam Family
- South
- Land of Niraj Purushottam Patil
- East
- Land of Moreshwar Damodar Vaze
- West
- Land of the second party
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking11 units
11 units registered
| Building | Type | Carpet area | Units |
|---|---|---|---|
| Row House No 1 | — | — | 1 |
| Row House No 10 | — | — | 1 |
| Row House No 11 | — | — | 1 |
| Row House No 2 | — | — | 1 |
| Row House No 3 | — | — | 1 |
| Row House No 4 | — | — | 1 |
| Row House No 5 | — | — | 1 |
| Row House No 6 | — | — | 1 |
Show all 11 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units |
|---|---|---|---|
| Row House No 7 | — | — | 1 |
| Row House No 8 | — | — | 1 |
| Row House No 9 | — | — | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Mahendra Kale | — |
| Chartered accountant | Sachin Hukumchand Chordiya | — |
| Chartered accountant | Surendra Kumar Trivedi | — |
Source: MahaRERA project page. Contact details are not shown.