Balaji Complex Phase-2
Deedo IDDP-PAL-VX7FCompletion was pushed back 4 months, to Apr 2028; no MahaRERA orders on record; 16% of its units are booked.
Kurgaon, Palghar 401504 · by B R Housing
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2028
- This projectRegistered 24 May 2022, completion promised 31 Dec 2027, revised to 30 Apr 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
- Balaji Complex Building No 12 Wing A And B5 floors · 40 units5% booked
- Balaji Complex Building No 3 A And B Wing5 floors · 36 units28% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP99000045553
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000045553 | 24 May 2022 | 31 Dec 2027 | 30 Apr 2028 | B R Housing | Project page |
Documents69
1 document held by Deedo, 68 filings listed on MahaRERA's project page
Finance
- PAN CardPANCARD-converted.pdf · uploaded 4 Apr 2022Source
Legal
Show all 69 documentsShow fewer documents
Migrated
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 4 Apr 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATE .pdf · uploaded 4 Apr 2022Source
- 1 CERSAI detailsCERSAI.pdf · uploaded 4 Apr 2022Source
- 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 4 Apr 2022Source
- 2 Proforma of Allotment letterDraft Sale Agreement_compressed.pdf · uploaded 4 Apr 2022Source
- 1 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 12 Apr 2022Source
- 1 Details of encumbrancesNO EMCUMBRANCE CERTIFICATE.pdf · uploaded 13 Apr 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentBLDG 12.pdf · uploaded 13 Apr 2022Source
- 2 Building Plan Approval / NA Order for plotted developmentBldg No - 3, Wing - A.pdf · uploaded 13 Apr 2022Source
- 3 Building Plan Approval / NA Order for plotted developmentBldg No 3 - Wing - B.pdf · uploaded 13 Apr 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE.pdf · uploaded 13 Apr 2022Source
- 1 Copy of the legal title reportLegal Tittle and Search Report_compressed.pdf · uploaded 27 Apr 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentCC AND NA 2018_compressed.pdf · uploaded 27 Apr 2022Source
- 1 Declaration in FORM BFORM B BHERULAL JAIN_compressed.pdf · uploaded 27 Apr 2022Source
- 2 Declaration in FORM BAFFIDAVIT CUM DECLARATION.pdf · uploaded 18 May 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)BR HOUSING FORM 1.pdf · uploaded 28 Feb 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)BR housing form 2.pdf · uploaded 17 Aug 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 23-8-2024 b r housing.pdf · uploaded 17 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 28-10-2024 b r housing.pdf · uploaded 17 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 31-12-2023 br housing.pdf · uploaded 17 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2-31-03-2024.pdf · uploaded 17 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 30-6-24 b r housing.pdf · uploaded 17 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 30-9-24 b r housing.pdf · uploaded 17 Nov 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM-2A -2024-25.pdf · uploaded 17 Nov 2024Source
- 1 Disclosure of sold/ booked inventorysold and unsold b r housing-15-11-24.pdf · uploaded 17 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form-3 b r housing.pdf · uploaded 17 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 23-8-2024 b r housing.pdf · uploaded 17 Nov 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 28-10-2024 b r housing.pdf · uploaded 17 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form-3 b r housing.pdf · uploaded 17 Nov 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 31-12-2023 br housing.pdf · uploaded 17 Nov 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2-31-03-2024.pdf · uploaded 17 Nov 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 30-6-24 b r housing.pdf · uploaded 17 Nov 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 30-9-24 b r housing.pdf · uploaded 17 Nov 2024Source
- 1 Disclosure of sold/ booked inventorysold and unsold b r housing-15-11-24.pdf · uploaded 17 Nov 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM-2A -2024-25.pdf · uploaded 17 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)form-5 b r housing 2022-23.pdf · uploaded 19 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5 b r housing 2023-24.pdf · uploaded 19 Nov 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)FORMAT A.pdf · uploaded 19 Nov 2024Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)FORMAT A.pdf · uploaded 19 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)form-5 b r housing 2022-23.pdf · uploaded 19 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5 b r housing 2023-24.pdf · uploaded 19 Nov 2024Source
- Form 5 (FY 2022-2023)form-5 b r housing 2022-23.pdf · uploaded 21 Jun 2025Source
- Form 5 (FY 2023-2024)form 5 b r housing 2023-24.pdf · uploaded 21 Jun 2025Source
Technical
Technical (Architect)
- DocumentB R HousingFORM -1 -Q1 19-09-2024.pdf · uploaded 19 Sep 2024Source
- Documentform 1 23-8-2024 b r housing.pdf · uploaded 17 Nov 2024Source
- Documentform 1 28-10-2024 b r housing.pdf · uploaded 17 Nov 2024Source
- Documentform 1 23-8-2024 b r housing.pdf · uploaded 17 Nov 2024Source
- Documentform 1 28-10-2024 b r housing.pdf · uploaded 17 Nov 2024Source
Technical (Engineer)
- DocumentRERA FORM-02 Q1-19-09-2024.pdf · uploaded 19 Sep 2024Source
- Documentform 2 31-12-2023 br housing.pdf · uploaded 17 Nov 2024Source
- Documentform 2-31-03-2024.pdf · uploaded 17 Nov 2024Source
- Documentform 2 30-6-24 b r housing.pdf · uploaded 17 Nov 2024Source
- Documentform 2 30-9-24 b r housing.pdf · uploaded 17 Nov 2024Source
- Documentform 2 31-12-2023 br housing.pdf · uploaded 17 Nov 2024Source
- Documentform 2-31-03-2024.pdf · uploaded 17 Nov 2024Source
- Documentform 2 30-6-24 b r housing.pdf · uploaded 17 Nov 2024Source
- Documentform 2 30-9-24 b r housing.pdf · uploaded 17 Nov 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 76, 77
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1RK, 2BHK76 units in all
- Address
- 76, 77, Parnalinaka, BOISAR WESTPIN 401504
- Village
- Kurgaon, Palghar taluka
- Location
- 19.82600, 72.72564
- Land area for this project
- 2,848 sq m (30,658 sq ft)
- Permissible built-up area
- 2,848 sq m (30,658 sq ft)
- Sanctioned built-up area
- 2,848 sq m (30,658 sq ft)
- Recreational open space
- 0 sq m (0 sq ft)
- Designated bank account
- 19
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
76,77
Boundaries
- North
- Property Of Anup Parekh
- South
- Property Of Chandra Shekhar Naik
- East
- Nalla
- West
- Property Belonging To Raut And Anup Parekh
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking76 units
12 of 76 units booked (16%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Balaji Complex Building No 12 Wing A And B | 1BHK | 27.27 sq m · 294 sq ft | 8 | 1 |
| Balaji Complex Building No 12 Wing A And B | 1BHK | 29.6 sq m · 319 sq ft | 2 | 0 |
| Balaji Complex Building No 12 Wing A And B | 1RK | 20.2 sq m · 217 sq ft | 24 | 1 |
| Balaji Complex Building No 12 Wing A And B | 1RK | 22.53 sq m · 243 sq ft | 6 | 0 |
| Balaji Complex Building No 3 A And B Wing | 1BHK | 34.93 sq m · 376 sq ft | 16 | 3 |
| Balaji Complex Building No 3 A And B Wing | 1BHK | 35.9 sq m · 386 sq ft | 8 | 1 |
| Balaji Complex Building No 3 A And B Wing | 1BHK | 41.08 sq m · 442 sq ft | 2 | 0 |
| Balaji Complex Building No 3 A And B Wing | 2BHK | 42.88 sq m · 462 sq ft | 8 | 6 |
| Balaji Complex Building No 3 A And B Wing | 2BHK | 50.13 sq m · 540 sq ft | 2 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Nishant P Patil | — |
| Chartered accountant | Anil Patwa | — |
| Engineer | Mukesh Prabhakar | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Kurgaon
- Elite ResidencyRERA PR1240002602101
- AarambhRERA PM1240002501772
- Nisarg -Building No.2RERA PR1240002500767
- Bhakti AvenueRERA P99000080819
- Aster Hans HeritageRERA P99000080705
- Whitehill ResidentialRERA P99000078529
- Emerald Woods 2RERA P99000051317
- SwarnaRERA P99000032620
All 18 projects in Kurgaon · Compare Balaji Complex Phase-2 with another project