Certificate Signed

Kurgaon, Palghar 401502 |Promoter: Ramara Developers

15 Dec 2025Registered with MahaRERA
31 Dec 2031Promised completion
30 Apr 2032Revised completionPushed back 4 months
4Buildings
44Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Buildings
4
Unit types
—44 units in all
Address
Panchmarg, KurgaonPIN 401502
Designated bank account
76
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.83142, 72.71867
Aarambh is at latitude 19.83142, longitude 72.71867.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
15 Dec 2025
Promised
31 Dec 2031
Revised
30 Apr 2032

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PM124000250177215 Dec 202531 Dec 203130 Apr 2032Ramara DevelopersProject page

4 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsFloors with CCUnits
A5—16
B7—28
Building No 1 Type- A5516
Building No 1 Type- B7828

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

44 units registered

— · 44 units
BuildingTypeCarpet areaUnits
A——16
B——28

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 36 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardpan card.pdf · uploaded 4 Nov 2025Source

Legal

  • Declaration Form BForm B.pdf · uploaded 18 Oct 2025Source
  • Declaration Form B7-12.pdf · uploaded 4 Nov 2025Source
  • OthersNo Encumbrance-Legal.pdf · uploaded 7 Nov 2025Source
  • OthersDeclaration about interest in Real Estate-Amruta.pdf · uploaded 24 Nov 2025Source
  • OthersDeclaration about interest in Real Estate-Chaitali.pdf · uploaded 24 Nov 2025Source
  • OthersDeclaration about interest in Real Estate-Jitendra.pdf · uploaded 24 Nov 2025Source
Show all 37 documentsShow fewer documents

Legal

  • OthersDeclaration about interest in Real Estate-Lekha.pdf · uploaded 24 Nov 2025Source
  • OthersDeclaration about interest in Real Estate-Nayana.pdf · uploaded 24 Nov 2025Source
  • OthersDeclaration about interest in Real estate-Nikhil.pdf · uploaded 24 Nov 2025Source
  • OthersCC screenshot.pdf · uploaded 24 Nov 2025Source
  • OthersNo Encumbrance-Legal.pdf · uploaded 24 Nov 2025Source
  • Declaration Form BLegal Tital Report.pdf · uploaded 24 Nov 2025Source
  • Declaration Form BRectification Deed 5.pdf · uploaded 24 Nov 2025Source
  • OthersReply to MahaRERA Queries.pdf · uploaded 4 Dec 2025Source
  • Declaration Form BPartnership Deed 5.pdf · uploaded 4 Dec 2025Source
  • Declaration Form BLand Purchase Deed 5.pdf · uploaded 4 Dec 2025Source

Migrated

  • Withdrawal Update Form 1FORM 1 December 2025.pdf · uploaded 31 Jan 2026Source
  • Withdrawal Update Form 2FORM 2 December 2025.pdf · uploaded 31 Jan 2026Source
  • Withdrawal Update Form 3Form 3 December 2025.pdf · uploaded 31 Jan 2026Source
  • Withdrawal Update Form 1Form 1 March 2026.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 1Form 1 March 2026.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2Form 2 March 2026.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2Form 2 March 2026.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3Form 3 March 2026.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3Form 3 March 2026.pdf · uploaded 20 Apr 2026Source
  • Form 5 (FY 2025-2026)Form 5 2025-26.pdf · uploaded 16 Jun 2026Source
  • Withdrawal Update Form 1june 26 architect form.pdf · uploaded 14 Aug 2026Source
  • Withdrawal Update Form 2jun 26 eng form rera.pdf · uploaded 14 Aug 2026Source
  • Withdrawal Update Form 3rera form 3 jun 26.pdf · uploaded 14 Aug 2026Source

Technical

  • DocumentLayout.pdf · uploaded 4 Nov 2025Source
  • DocumentBuilding Plan.pdf · uploaded 4 Nov 2025Source
  • DocumentOrder 50.pdf · uploaded 4 Nov 2025Source
  • Otherspan card.pdf · uploaded 4 Nov 2025Source

Technical (Architect)

  • Documentjune 26 architect form.pdf · uploaded 14 Aug 2026Source

Technical (Engineer)

  • Documentjun 26 eng form rera.pdf · uploaded 14 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Kurgaon, Palghar taluka

Survey, CTS, gat or plot numbers

19/A/1/2

Boundaries

North
Gut No 20 and 21
South
Gut No 25 and 18
East
Gut No 16 and 17
West
Gut No 20

Source: registration certificates and MahaRERA's project page, as stated there.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology